Professional Documents
Culture Documents
Student's Name & Number
Student's Name & Number
At first
1. Open PSCAD-program
2. Choose Open – Open Workspace and double-click from folder ‘Exercise 2’ ’Exercise_2’ –
workspace
PSCAD simulation exercise 2
Figure 1.
I) Choose 3 % value for the static/droop (Fig. 3). Run the simulation so that at t = 2.5 s load L1
(150 MW, Fig. 1 and Fig. 4) is connected to the power system.
Figure 3.
PSCAD simulation exercise 2
Figure 4.
Question 4.1: In which value the generator frequency (rotating speed) stabilizes at the end of the
simulation run? 49.656 HZ
Question 4.2: How large is the steady-state frequency deviation from nominal frequency in this
case? 50-49.656= 0:344HZ
Question 4.3: How much generator mechanical torque T m changes? 0.655 Pu to a maximum value
of 1.04 Pu and it stabilizes at 0.88765 Pu
Question 4.4: How much generator active power P output changes? from 185 MW to 608.565 MW
PSCAD simulation exercise 2
Question 4.5: How much generator reactive power Q output changes? from 0 to 107
MVAR
II) Choose 6 % value for the static/droop (Fig. 3). Run the simulation so that at t = 2.5 s load L1
(150 MW, Fig. 1 and Fig. 4) is connected to the power system.
Question 4.6: In which value the generator frequency (rotating speed) stabilizes at the end of the
simulation run? 49.30458HZ
Question 4.7: How large is the steady-state frequency deviation from nominal frequency in this
case? 50-49.30458=0.69542 HZ
Question 4.8: How much generator mechanical torque Tm changes? from 0.655Pu to 0.8889Pu
PSCAD simulation exercise 2
Question 4.9: How much generator active power P output changes? from 185.544MW to
606.997MW
Question 4.10: How much generator reactive power Q output changes? from 15.8065 MVAR to
103.715MVAR
Question 4.11: How the static/droop setting change 3% => 6 % affected on the results?
The steady sate error increases from 0.3 to 0.69.
The value the generator frequency (rotating speed) stabilizes at the end
reduced a bit when we change the droop setting from 3% to 6%.
The maximum value of the active and reactive power reduces a bit it when we
change the droop setting from 3% to 6%.
PSCAD simulation exercise 2
In previous case a) the steady state frequency deviated from the nominal frequency after
load change. In real systems frequency control tries to maintain frequency always close to
nominal value. This requires control system modification so that integrator is added to the
control system (in this case PI-controller, Fig. 5).
Figure 5.
PSCAD simulation exercise 2
III) Choose 3 % value for the static/droop (Fig. 3). Run the simulation so that at t = 2.5 s load L1
(150 MW, Fig. 1 and Fig. 4) is connected to the power system.
Question 4.12: In which value the generator frequency (rotating speed) stabilizes at the end of the
simulation run? 49.997 HZ
Question 4.13: How large is the steady-state frequency deviation from nominal frequency in this
case?50- 49.997= 0.003 HZ
Question 4.14: How much generator mechanical torque Tm changes? from 0 to 0.655067 Pu
Question 4.15: How much generator active power P output changes? from 0 to 614MW
Question 4.16: How much generator reactive power Q output changes? from 0.06 MVAR to
109.99 MVAR
PSCAD simulation exercise 2
IV) Choose 6 % value for the static/droop (Fig. 3). Run the simulation so that at t = 2.5 s load
L1 (150 MW, Fig. 1 and Fig. 4) is connected to the power system.
Question 4.17: In which value the generator frequency (rotating speed) stabilizes at the end of the
simulation run? 49.999HZ
Question 4.18: How large is the steady-state frequency deviation from nominal frequency in this
case? 0.001 HZ
Question 4.19: How much generator mechanical torque Tm changes? from 0.02 Pu to 0.65483Pu
Question 4.21: How much generator reactive power Q output changes? 0 to 113.4929 MVAR
Question 4.22: How the static/droop setting change 3% => 6 % affected on the results?
Figure 6.
a) Effect of static/droop setting
Open Project file Task_4_2a_final
PSCAD simulation exercise 2
V) Choose 3 % value for the static/droop of generator 1 and 6 % for the generator 2. Run the
simulation so that at t = 2.5 s load L1 (300 MW, Fig. 1 and Fig. 4) is connected to the power
system.
Question 4.23: In which value the generator frequency (rotating speed) stabilizes at the end of the
simulation run?
Question 4.24: How large is the steady-state frequency deviation from nominal frequency in this
case?
Question 4.31: How generators different static/droop settings affected on their P and Q output?
PI-controller is added to generator 1 control system i.e. generator 1 tries to return power
system frequency back to nominal value.
VI) Choose 3 % value for the static/droop of generator 1 and 6 % for the generator 2. Run the
simulation so that at t = 2.5 s load L1 (300 MW, Fig. 1 and Fig. 4) is connected to the power
system.
Question 4.32: In which value the generator frequency (rotating speed) stabilizes at the end of the
simulation run?
Question 4.33: How large is the steady-state frequency deviation from nominal frequency in this
case?
Question 4.40: How generators P and Q output changed in this case in which generator 1 control
system had a PI-controller?
Fig. 7 presents simple power system with generator, transformer and transmission line. Determine
critical fault clearing time (with five milliseconds accuracy) for 3-phase short-circuit faults occuring
at points A and B.
Fault duration/time can be changed from Timed Fault Logic” component.
Figure 7.
Question 5.1: What is critical fault clearing time with five milliseconds accuracy for 3-phase short-
circuit fault occuring at t = 2.5 s without losing transient/angle stability after first swing (initial fault
duration/time is 150 ms)?
Question 5.2: What is critical fault clearing time with five milliseconds accuracy for 3-phase short-
circuit fault occuring at t = 2.5 s without losing transient/angle stability after first swing (initial fault
duration/time is 150 ms)?
PSCAD simulation exercise 2
Figure 8.
a) Critical fault clearing time, fault at point A
Open Project file Task_5_2a_final
Question 5.3: What is critical fault clearing time with five milliseconds accuracy for 3-phase short-
circuit fault occuring at t = 2.5 s without losing transient/angle stability after first swing (initial fault
duration/time is 300 ms)?
PSCAD simulation exercise 2
Question 5.4: What is critical fault clearing time with five milliseconds accuracy for 3-phase short-
circuit fault occuring at t = 2.5 s without losing transient/angle stability after first swing (initial fault
duration/time is 300 ms)?
PSCAD simulation exercise 2
Determine critical fault clearing time for a 3-phase short-circuit fault occuring in point B (Fig. 9).
Figure 9.
Question 5.6: What other possibilities exist which could be used for increasing the critical fault
clearing time?
PSCAD simulation exercise 2
Run simulation once in order to see that the power system is unstable (low-frequency oscillations
increase slowly during the simulation).
Figure 10.
Power system damping (to prevent oscillations which may lead to black out) is traditionally
improved by utilizing power system stabilizers (PSSs) (Fig. 11).
PSCAD simulation exercise 2
Figure 11.
PSCAD simulation exercise 2
PSS-component which is used in the simulation model has initial values for different parameters.
Attach/connect PSS-component output Vs to AC exciter Vs input and run four different simulations
1)-4) with PSS time constants T1-T4 shown in Table 1.
Case 1) 2) 3) 4)
Unstable/
stable
Question 6.1: What is the effect of time constants T 1-T4 value on Fig. 12 parameters behavior on
different cases 1)-4)? Which Table 1 cases are unstable and stable?
Figure 12.
PSCAD simulation exercise 2
In order to increase the power transmission on the transmission line and improve system stability,
SVC is connected in the middle of the transmission line. Change the other system equivalent INF1
phase/angle as shown in Table 2 (equivalent INF2 phase/angle is 0 in all cases). Consider also
voltage levels for system equivalents in different cases (see Table 2).
Figure 13.
PSCAD simulation exercise 2
Question 7.1: How SVC’s 400 kV connection point voltage and reactive power output is changed
in different cases (Table 2)?
Table 2.
INF1 75 65 55 45 35 25 15 5 0 0 0
angle/phase
INF 1 and 400 400 400 400 400 400 400 400 400 410 420
INF2 voltages
(kV)
SVC
connection
point voltage
(kV)
SVC’s
reactive power
(MVAr)
PSCAD simulation exercise 2