Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

N

J M Notes:
1.All dimensions are in millimeters and levels
A B C D E F G H E L N P Q R S T U are in meters unless otherwise specified.
2.Drawing shall not be scaled, only written
1020 1850 1200 dimensions to be followed.
9900 9900 3240 4000 2660 9900 9830 4500 2420 2580 7250 6600 3300 2200 3450 3.Any Error or Discrepancies in the
Drawings are to be brought to the notice.
of the Architect/ Engineers.
4. This drawings shall not be used other than
the purpose marked/issued specified.
5. The drawings to be read with conjuction
8 with structural drawings.
6. All the drawings prepared by Design
and structural consultants are as per
6900

NBC norms and guidelines.


REMOVAL OF FORMWORK(SHUTTERING) :
Shuttering of any part of the structure shall not be
removed until the concrete attains 70% of the specified
7 strength of concrete however the following minimum
period (after final pour ) shall be allowed before
4250

removal of shuttering as per clause 11.3.1, is 456:2000


A. Vertical side of shuttering of columns,walls & beams
- 24 hours
B. Bottom shuttering of slabs (keeping the props)
6
2000

- 3 days
LIFT
CUTOUT C. Bottom shuttering of beams (keeping the props)
5 - 7 day
D. Props to slabs :
i .spanning upto 4.5 m - 7 days
3650

i i .spanning over 4.5 m - 14 days


E. Props to beams & arches :
i .spanning upto 6 m - 14 days
4 i i.spanning over 6 m - 21 days
LAP JOINTS FOR REINFORCEMENT BARS :
1. At any cross section of the member,not more than
6900

50% of the bars shall be lapped.


2. Laps shall be staggered with a minimum centre to
centre distance of 1.3 times lap length of the bar for
tension & compression members.
3. Development length (ld) shall be as per (sp:34-1999)
table below:
3 a) Development length for column bars - 40d
b) Development length for beam bars - 50d
4. Laps in columns shall be provided at mid height of
floor and not at slab level .
5. Laps in beams and slabs shall be provided at the
point of contraflexure.
6. Welding of bars shall be done as a stitch weld for 5
times diameter of bar and a gap of 5 times higher
diameter bar and again welding for another 5 times
diameter of bar using arc welding and special
electrodes after obtaining prior written approval from
the structural designer.
7. Detailing of rebars shall confirm to sp-34 & is 13920.
RCC WALL LAYOUT
GENERAL NOTES:
1. Concrete grade shall be M35(design mix) confirming to
is 456:2000
2. Minimum cement content = 380 kg/m3.
3. Min.grade of reinforcement marked thus (y) shall be Fe
550D confirming to IS 1786-1985
4. Clear cover for reinforcement
a) Column = 40mm d) Raft slab bottom = 75mm
b) R.C wall = 40mm e) Raft slab top = 50mm
c) Shear wall = 40mm
This drg. read in conjection with arch.drgs.
5. Raft & Columns are designed for Ground + Mezzanine +
Four floor loads only.
6. SBC of the soil is taken as 320kN / sqm. @ 2.40m below
from N.G.L. as per soil report.
7. Spacer bar - 25mm dia to be provided in between two
layer of reinforcement at every 750mm c/c
8. Structural engineer responsibility is limited to design &
issual of structural drawing only
9. Onus of construction lies with contractor/owner
10. For concreting water cement ratio should be (0.45) (for
1bag cement= max-25 lit of water only to be added.)
NOTES STRUCTURAL DESIGN QUALITY ASSURANCE
REVISIONS
Notice of no objection from Southern Railways Katpadi is being accorded for design principles based on the The drawing has been prepared based on actual site survey and other terms and conditions of the EPC Agreement. Responsibility of accuracy, correctness , This drawing including its design and detailing has been checked in accordance with the requirements of EPC Agreement and found
recommendations of the Architect/Lead Designer and proposal by the Contractor. However, the completeness, integrity and full compliance with byelaws, standards, statutory, regulations of relevant Codes & Manuals/ Rules and as per EPC Agreement suitable for the execution purpose. The overall responsibility of correctness of design,detailing and compliance with EPC agreement R.NO DATE DESCRIPTION
overall responsibility and design accuracy lies with the contractor (Engineering Projects (india) Pvt Ltd) provisions, rests with the Design Consultants and the Contractor without any financial implications. rests with the Structural Design Consultant and Contractor.
CLIENT: PROJECT: EPC Contractor: DESIGN CONSULTANT Authority Engineer (PMS) AXEN CN/MAS DY. CE CN/MAS CE CN/MAS
Drawing Title :
SOUTHERN RAILWAYS, REDEVELOPMENT OF ENGINEERING PROJECTS M/S VOYANTS SOLUTIONS PVT. LTD.
KATPADI. KATPADI JUNCTION (INDIA) LTD-CHENNAI Drawing Type :
Drawing No.: Scale: 1:100 Date: 12.12.23
Drawing Purpose: Sheet Size: A2 Rev. No: R0
AGM DESIGN DIRECTOR TEAM LEADER LEAD DESIGNER

You might also like