SAFETY INSPECTION REPORT

LPS-01 PROJECT

Area
LPS-01 Date 15.02.2024 Time 08.00 PM
Location
Completed by Mark Signature

Items to be checked

1 Safety Plans 7 Waste Controls 13 Holes and Voids 19 Lifting Plant and Lifting Gear

2 Registers and Records 8 Fire and Gases/Hot work x 14 Working at height 20 Site Storage x

Access Walkways and


3 Signs and Notices 9 15 Internal Routes 21 House Keeping x
Stairs
First Aid and Medical Plant and
4 10 Ladder Access x 16 22 Portable Hand/Power Tools
Facility Machinery
Scaffolding/Working Guarding and
5 Health Hazards 11 17 23 Hygiene and Welfare
Platforms Fencing
Edge Protection/ Floor Electrics/
6 Chemicals x 12 18 x 24 Personal Protection Equipment
opening illumination
Photo
Observation Corrective Actions to be Taken Action Date Action By Followed By
No.
Using damaged lead cables at level Removed from usage, ensure all
1

Immediate
6. Zone C. lead cables are inspected prior to

2 Days

4 Days
use.


Foundprotruding threaded rod Provide caps for the protruding

x Immediate Immediate Immediate Immediate

2 Days

4 Days
without caps. threaded rods at level 5.
2

Found wooden debris at B-1, it’s a Ensure housekeeping at this


2 Days

4 Days
fire hazard. location.
3

Observed poor waste disposal. Non Conduct awareness training to


2 Days

4 Days

hazardous waste disposed in the work force regarding proper


4 chemical waste skip. waste disposal at site.

Found stagnant water at B-2. Ensure that stagnant water is


2 Days

4 Days

removed from the pit, otherwise it


5 may impose penalty from UDC.

Observations Closeouts

HBK-CRCC JV-HS-FRM-00044 Rev 1 Page 1 of 3


SAFETY INSPECTION REPORT
LPS-01 PROJECT

Using damaged lead cables at level 6. Zone C. Removed from usage, ensure all lead cables are
inspected prior to use.

Foundprotruding threaded rod without caps. Provide caps for the protruding threaded rods at
level 5.

Found wooden debris at B-1, it’s a fire hazard. Ensure housekeeping at this location.

HBK-CRCC JV-HS-FRM-00044 Rev 1 Page 2 of 3 -June-17


SAFETY INSPECTION REPORT
LPS-01 PROJECT

Observed poor waste disposal. Non hazardous Conduct awareness training to the work force
waste disposed in chemical waste skip. regarding proper waste disposal at site.

Found stagnant water at B-2. Ensure that stagnant water is removed from the
pit, otherwise it may impose penalty from UDC.

HBK-CRCC JV-HS-FRM-00044 Rev 1 Page 3 of 3 -June-17