INSPECTION REPORT
The works done by M/s Iceberg Industries and their Associates M/s Rakson
was jointly inspected on June 11, 2021. It was followed by the Project review meeting which
was attended by the following:
1. During the Site Visit, the following deficiencies were pointed to Mr. Yasin. He was
advised to get it rectified at the earliest.
1.1 Some of the welding joints were of poor quality. Proper “V” was not made
in the pipe. Such joints to be redone.
(b) There were gaps between the insulation joints, condensation was
visible on the pipes.
(c) On some pipes G.I. sheet jacketing has also been done.
2. Duct and pipe hangers should be painted with hamer grey paint. Only red oxide
has been done.
3. Cooling tower Basin has been placed on foundation pads. Leak testing to be
done by filling the water.
7.7 Area shut down shall be given to Contractor from June 21, 2021. They
must commence the internal works with full force.
8.1 Mr. Yasin’s Engineer will visit the site daily. Mr. Yasin has deputed their
Engineer Mr. Mashaf.
8.2 Progress review meeting shall be held at site daily at 2:00 PM.
For Y. H. Associates,
( YOUSUF HASAN )