DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/1/2023 DAILY ACTIVITY REPORT: DAY 25 % DAYS ELAPSE: 21%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 0.84% 0.84% 0.00% Ongoing
30 WEATHER : S S S S F S S F S
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 7
40 Labor : 8
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Scaffoldings : 15
46 Ladder : 4
47 Shovel : 3
48 Bara : 4
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Generator Set : 8
55 Chainsaw : 6
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 Boulders : 10 cubic
60 1.5" GI Pipe Schd. 20 : 20
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 There was a fallen tree that is hazardous to cut Ask for the assistance of ERT
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/2/2023 DAILY ACTIVITY REPORT: DAY 26 % DAYS ELAPSE: 22%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 0.88% 0.88% 0.00% Ongoing
30 WEATHER : S S F S S F F S S
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 9
40 Labor : 13
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Cyclone wire : 2
46 DB 10mm : 10
47 Welding rod :
48 Bara : 4
49 Shovel : 3
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Generator Set : 8
55 Chainsaw :
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 Boulders : 10cubic
60 1.5" GI Pipe Schd. 20 : 10
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 There was a fallen tree that is hazardous to cut Ask for the assistance of ERT
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/3/2023 DAILY ACTIVITY REPORT: DAY 27 % DAYS ELAPSE: 23%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 0.91% 0.91% 0.00% Ongoing
30 WEATHER : S C C F F S F F F
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 9
40 Labor : 13
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Cement : 7
46 Gravel : 14
47 Sand : 21
48 Bara : 4
49 Shovel : 3
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Generator Set : 8
55 Chainsaw : 6
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 Stop work for Combatan due to ERT assessment of the Wait for the assessment of ERT
73 hazardous tree at the top of the dam
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/4/2023 DAILY ACTIVITY REPORT: DAY 28 % DAYS ELAPSE: 23%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 0.94% 0.94% 0.00% Ongoing
30 WEATHER : F F S S S F F S S
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 9
40 Labor : 14
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Cement : 18 Bags
46 Gravel : 36 Bags
47 Sand : 54 Bags
48 :
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Two Generator Set : 8
55 :
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 Sand : 10 Cubic
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 There are trees identified that are hazardous for work Coordinate with ERT and Proponent
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/5/2023 DAILY ACTIVITY REPORT: DAY 29 % DAYS ELAPSE: 24%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 0.98% 0.98% 0.00% Ongoing
30 WEATHER : F F F S S S F F S
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 7
40 Labor : 9
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Bara : 3
46 Shovel : 4
47 :
48 :
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Generator Set : 8
55 Breaker : 4
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 There is a presence of H2S in stucked in the ground while we Check the gas meter if it is safe to work.
73 were excavating
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/7/2023 DAILY ACTIVITY REPORT: DAY 30 % DAYS ELAPSE: 25%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.01% 1.01% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 0.00% 0.19% 0.19% Ongoing
30 WEATHER : F C C C C R R
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 9
40 Labor : 14
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Bara : 3
46 Pala : 4
47 Mace : 4
48 :
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Two Generator Set : 8
55 Breaker : 5
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 Sand : 10cubic
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 Bad weather condition. It rained about 1345H Pullout from the area as per advice from the ERT
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/8/2023 DAILY ACTIVITY REPORT: DAY 31 % DAYS ELAPSE: 26%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.04% 1.04% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 0.19% 0.38% 0.19% Ongoing
30 WEATHER : F F S S S F F S S
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 9
40 Labor : 13
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Bara : 4
46 Pala : 3
47 Welding rods :
48 DB 10mm :
49 Mace : 4
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Two Generator Set : 8
55 Breaker : 4
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/9/2023 DAILY ACTIVITY REPORT: DAY 32 % DAYS ELAPSE: 27%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.08% 1.08% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 0.38% 0.58% 0.19% Ongoing
30 WEATHER : C C R R C C C
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 9
40 Labor : 16
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Cement : 12 Bag
46 Gravel : 20 Bags
47 Sand : 30 Bags
48 Bara : 4
49 Pala : 3
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Two Generator Set : 5
55 Portabale welding Machine : 5
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72
We started late about 1045H due to earthquake and we had to Coordinate with the ERT, Proponent, and PEM if there is a visible
73
pause the work due to the rain movement of soil.
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/10/2023 DAILY ACTIVITY REPORT: DAY 33 % DAYS ELAPSE: 28%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.11% 1.11% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 0.58% 0.58% 0.00% Ongoing
30 WEATHER : C R R HR HR R R
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 10
40 Labor : 15
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Mace : 3
46 Shovel : 4
47 Alvenous :
48 Bara : 3
49 Scaffoldings :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Generator Set : 1
55 :
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 Bad weather condition Early pullout from the Area
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/11/2023 DAILY ACTIVITY REPORT: DAY 34 % DAYS ELAPSE: 28%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.15% 1.15% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 0.77% 0.77% 0.00% Ongoing
30 WEATHER : R R C C C C F F C
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 11
40 Labor : 15
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Mace : 3
46 Shovel : 3
47 Bara : 4
48 Alvenous :
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Generator Set : 6
55 :
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 Wait for the rain to pass by.
Bad weather condition at first hours
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/12/2023 DAILY ACTIVITY REPORT: DAY 35 % DAYS ELAPSE: 29%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.18% 1.18% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 0.96% 0.96% 0.00% Ongoing
30 WEATHER : C R C C R C C C C
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 1
38 Foreman : 2
39 Skill : 11
40 Labor : 14
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Cable 25mm : 170m
46 Cable 5/16 inch : 340m
47 Lagaraw : 4
48 Cement : 3
49 Sand : 12
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Service Vehicle : 8
54 Two Generator Set : 5
55 Breaker : 5
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 The rain sprinkled mostly all day. Work stoppage if the rain is too heavy to work.
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/14/2023 DAILY ACTIVITY REPORT: DAY 36 % DAYS ELAPSE: 30%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.21% 1.21% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 1.15% 1.15% 0.00% Ongoing
30 WEATHER : C C F C C F F C C
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 9
40 Labor : 13
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Bara : 4
46 Shovel : 4
47 Mace : 3
48 :
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Two Generator Set : 8
54 Chainsaw : 4
55 Breaker : 8
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72
Assign spotters
73 Fog is constantly visiting the area
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/15/2023 DAILY ACTIVITY REPORT: DAY 37 % DAYS ELAPSE: 31%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.25% 1.25% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 1.34% 1.34% 0.00% Ongoing
30 WEATHER : F C C C R C C C C
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 10
40 Labor : 13
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Mace : 3
46 Shovel : 4
47 Bara : 4
48 :
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Two Generator Set : 8
54 Breaker : 8
55 :
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 Fogs is prominent thoughout the day Assign multiple spotters
73
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : Construction of Tobaco and Combatan Dam
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- COMBATAN AND TABACCO CREEK
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : June 13, 2023 : ACTUAL START : July 3, 2023
10 : PLANNED COMPLETION : December 3, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 120 : ACTUAL DURATION :
12
DATE: 8/16/2023 DAILY ACTIVITY REPORT: DAY 38 % DAYS ELAPSE: 32%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 4.04% 1.28% 1.28% 0.00% Ongoing
23 2.1 Lay Outing and General Works 7.68% 1.54% 1.54% 0.00% Ongoing
30 WEATHER : F C C C R R C HR HR
33 MANPOWER REPORT:
34 CLASSIFICATION: : NO RATE AMOUNT REMARKS
35 Field Engineer : 2
36 Safety Officer : 1
37 Competent Person : 2
38 Foreman : 2
39 Skill : 8
40 Labor : 12
41
42 TOTAL MANPOWER COST PHP
43 MATERIAL UTILAZATION REPORT :
44 CLASSIFICATION: : QTY UNIT PRICE AMOUNT REMARKS
45 Mace : 3
46 Shovel : 3
47 Bara : 4
48 :
49 :
50 DAILY MATERIAL COST PHP
51 EQUIPMENT UTILIZATION REPORT :
52 CLASSIFICATION: : HOURS RATE AMOUNT REMARKS
53 Two generator set : 8
54 Breaker : 8
55 :
56 DAILY EQUIPMENT COST PHP
57 DELIVERY REPORT :
58 CLASSIFICATION: : QTY UNIT TOTAL REMARKS
59 :
60 :
61 :
62 :
63 :
64 OTHER INDIRECT COST :
65 CLASSIFICATION: : QTY RATE AMOUNT REMARKS
66 :
67 :
68 DAILY INDIRECT COST PHP
69
70 TOTAL DAILY COST PHP
71 PROBLEMS ENCOUNTERED ACTION TAKEN REMARKS
72 Fog is prominent, rain is sprinkling throughout the day, and Work stoppage when the rain is too heavy and the fog is too thick.
73 about 1445H the rain started pouring heavily
74
75
76 Prepared by : Noted By : Checked and Verified By:
77
78 KIM DAWN B. SOLANIA ARNEL M. PONCE _______________________
79
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH
1
DAILY WORK ACTIVITY REPORT
2
3 PROJECT TITILE : INSTALLATION OF HDPE LINER PAD- G
4 LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
5 CONTRACTOR : MATKR-MPC
6 P.O. No. :
7 COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
8 COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
9 TIME LINES : PLANNED START : O8/21/2023 : ACTUAL START : August 30, 2023
10 : PLANNED COMPLETION : October 21, 2023 : ACTUAL COMPETION :
8:00 - 4:00
11 : PLANNED DURATION : 62 : ACTUAL DURATION :
12
DATE: 8/30/2023 DAILY ACTIVITY REPORT: DAY 9 % DAYS ELAPSE: 8%
13
14 PHYSICAL ACCOMPLISHMENT REPORT:
15
ACTIVITIES; Unit Wt% Target Actual Variance REMARKS
16
17 1 PRELIMINARY & GENERAL WORKS
21 1.4 PPE Benefits and Other cost 2.75% 0.40% 0.05% -0.36% Ongoing
28 2.6
29
30
31
32
36 WEATHER : S S F S S F F F F
39 MANPOWER REPORT:
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 1
Labor : 6
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold : 10
Clamps : 50
Bara : 3
Bolo : 2
Shovel : 3
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Generator Set : 5
Breaker : 5
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S F S
NO RATE AMOUNT REMARKS
2
1
1
1
1
6
1
PHP
5
5
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
15 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
S F F S F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
24%
REMARKS
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 0
Competent Person : 1
Foreman : 1
Skill : 1
Labor : 3
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold : 0
Clamps : 0
Bara : 3
Bolo : 2
Shovel : 3
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Cutting outfit 4
Generator Set : 6
Breaker : 6
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
R R C S
NO RATE AMOUNT REMARKS
2
0
1
1
1
3
1
PHP
4
6
6
PHP
PHP
PHP
ACTION TAKEN
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
16 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
R C R F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
Checked and Verified By:
_______________________
August 30, 2023
26%
REMARKS
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 0
Labor : 6
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold :
Clamps : 0
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Cutting outfit 0
Generator Set : 6
Breaker : 6
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
R R C S
NO RATE AMOUNT REMARKS
2
1
1
1
0
6
1
PHP
0
2
2
4
PHP
0
6
6
PHP
PHP
PHP
ACTION TAKEN
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
17 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
R C R F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
Checked and Verified By:
_______________________
August 30, 2023
27%
REMARKS
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 0
Labor : 7
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold : 0
Clamps : 0
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Cutting outfit 0
Generator Set : 3
Breaker : 3
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F C HR
NO RATE AMOUNT REMARKS
2
1
1
1
0
7
1
PHP
0
3
3
PHP
PHP
PHP
ACTION TAKEN
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
18 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
HR R C R F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
Checked and Verified By:
_______________________
August 30, 2023
29%
REMARKS
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 0
Labor : 7
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold : 0
Clamps : 0
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Generator Set : 0
Breaker : 0
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F C F
NO RATE AMOUNT REMARKS
2
1
1
1
0
7
1
PHP
0
0
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
19 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F F F R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
30%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 4
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold : 0
Clamps : 0
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Generator Set : 0
Breaker : 0
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S F F
NO RATE AMOUNT REMARKS
2
1
1
1
2
4
1
PHP
0
0
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
21 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F F F R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
33%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 4
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold : 0
Clamps : 0
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F C F S
NO RATE AMOUNT REMARKS
2
1
1
1
2
4
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
22 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
C F F F R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
35%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 4
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
Scaffold : 0
Cement : 10
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F C F C
NO RATE AMOUNT REMARKS
2
1
1
1
2
4
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
23 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
R F F F R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
37%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 4
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Portable Welding Machine :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F C F C
NO RATE AMOUNT REMARKS
2
1
1
1
2
4
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
24 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
R F F F R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
38%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 3
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw : 2
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F C R R
NO RATE AMOUNT REMARKS
2
1
1
1
2
3
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
25 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
R F F F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
40%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
ongoing
ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LIN
LOCATION : MT. APO GEOTHERMAL PR
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 3
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw : 2
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S F F
NO RATE AMOUNT REMARKS
2
1
1
1
2
3
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
26 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F F F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
41%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
ARKS
____________
PROJECT TITILE :
LOCATION :
CONTRACTOR :
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES :
:
8:00 - 4:00
:
DATE: 9/18/2023
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @15
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM :
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: :
Field Engineer :
Safety Officer :
Competent Person :
Foreman :
Skill :
Labor :
Driver
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: :
10" spigot :
Butterfly valve S-150 :
Bara :
Bolo :
Shovel :
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: :
Chainsaw :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: :
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: :
:
:
DAILY INDIRECT COST
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START :
PLANNED COMPLETION : Octo
PLANNED DURATION :
Wt%
1 2 3 4 5 6 7 8 9
S S
NO RATE AMOUNT
2
1
1
1
2
3
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
ARNEL M. PONCE
CTIVITY REPORT
: PREVIOUS
: PREVIOUS
O8/21/2023 : ACTUAL START
October 21, 2023 : ACTUAL COMPETION
62 : ACTUAL DURATION
10 11 12 13 14 15 16 17 18
F F C F F R R
REMARKS
REMARKS
REMARKS
REMARKS
OUNT REMARKS
APSE: 45%
Variance REMARKS
-2.10% DONE
0.00% DONE
-2.03% Ongoing
-1.39% Ongoing
0.00% DONE
0.00% Ongoing
0.00% DONE
0.00% DONE
0.00% DONE
-1.65% Ongoing
-2.54% Ongoing
-2.99% Ongoing
0.00%
0.00%
0.00%
-11.19% Ongoing
-0.90% Ongoing
-24.79%
19 20 21 22 23 24 25
REMARKS
By:
_______________________
PROJECT TITILE :
LOCATION :
CONTRACTOR :
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES :
:
8:00 - 4:00
:
DATE: 9/19/2023
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @15
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM :
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: :
Field Engineer :
Safety Officer :
Competent Person :
Foreman :
Skill :
Labor :
Driver
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: :
10" spigot :
Butterfly valve S-150 :
Bara :
Bolo :
Shovel :
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: :
Chainsaw :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: :
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: :
:
:
DAILY INDIRECT COST
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START :
PLANNED COMPLETION : Octo
PLANNED DURATION :
Wt%
el anchor bolts with washer placed @150mm O.C
1 2 3 4 5 6 7 8 9
S S
NO RATE AMOUNT
2
1
1
1
2
9
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
ARNEL M. PONCE
CTIVITY REPORT
: PREVIOUS
: PREVIOUS
O8/21/2023 : ACTUAL START
October 21, 2023 : ACTUAL COMPETION
62 : ACTUAL DURATION
10 11 12 13 14 15 16 17 18
F C F C F F F
REMARKS
REMARKS
REMARKS
REMARKS
OUNT REMARKS
APSE: 46%
Variance REMARKS
-3.10% DONE
0.00% DONE
-1.03% Ongoing
-0.99% Ongoing
0.00% DONE
0.00% Ongoing
0.00% DONE
0.00% DONE
-1.65% Ongoing
-2.54% Ongoing
-2.99% Ongoing
0.00%
0.00%
0.00%
-11.19% Ongoing
-0.90% Ongoing
-24.99%
19 20 21 22 23 24 25
REMARKS
By:
_______________________
PROJECT TITILE :
LOCATION :
CONTRACTOR :
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES :
:
8:00 - 4:00
:
DATE: 9/20/2023
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @15
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM :
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: :
Field Engineer :
Safety Officer :
Competent Person :
Foreman :
Skill :
Labor :
Driver
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: :
10" spigot :
Butterfly valve S-150 :
Bara :
Bolo :
Shovel :
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: :
Chainsaw :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: :
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: :
:
:
DAILY INDIRECT COST
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START :
PLANNED COMPLETION : Octo
PLANNED DURATION :
Wt%
1 2 3 4 5 6 7 8 9
S S
NO RATE AMOUNT
2
1
1
1
2
10
1
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
ARNEL M. PONCE
CTIVITY REPORT
: PREVIOUS
: PREVIOUS
O8/21/2023 : ACTUAL START
October 21, 2023 : ACTUAL COMPETION
62 : ACTUAL DURATION
10 11 12 13 14 15 16 17 18
F HR HR C F R F
REMARKS
REMARKS
REMARKS
REMARKS
OUNT REMARKS
APSE: 48%
Variance REMARKS
-3.93% DONE
0.00% DONE
-1.03% Ongoing
-0.99% Ongoing
0.00% DONE
0.00% Ongoing
0.00% DONE
0.00% DONE
-1.65% Ongoing
-2.54% Ongoing
-2.99% Ongoing
0.00%
0.00%
0.00%
-11.19% Ongoing
-0.90% Ongoing
-25.22%
19 20 21 22 23 24 25
REMARKS
By:
_______________________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 10
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw :
Generator Set : 3
Breaker : 3
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Temporary stop activity due to bad weather condition . Heavy rain around 2pm.
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S F F
NO RATE AMOUNT REMARKS
2
1
1
1
2
10
1
PHP
3
3
PHP
PHP
PHP
ACTION TAKEN
pm.
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
31 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F R HR HR HR
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
45%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 0
Safety Officer : 0
Competent Person : 0
Foreman : 0
Skill : 0
Labor : 0
Driver 0
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 0
Butterfly valve S-150 : 0
Bara : 0
Bolo : 0
Shovel : 0
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw :
Generator Set : 0
Breaker : 0
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F C S S
NO RATE AMOUNT REMARKS
0
0
0
0
0
0
0
PHP
0
0
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
32 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F R R F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
51%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 10
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw :
Generator Set : 4
Breaker : 4
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F F F
NO RATE AMOUNT REMARKS
2
1
1
1
2
10
1
PHP
4
4
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
33 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F S F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
53%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 12
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw :
Generator Set : 3
Breaker : 3
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F F F
NO RATE AMOUNT REMARKS
2
1
1
1
2
12
1
PHP
3
3
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
35 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F S F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
56%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
DONE
DONE
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 2
Skill : 2
Labor : 14
Driver 1
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw :
Generator Set : 4
Breaker : 4
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F R R
NO RATE AMOUNT REMARKS
2
1
1
2
2
14
1
PHP
4
4
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
36 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F R R R R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
58%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 0
Safety Officer : 0
Competent Person : 0
Foreman : 0
Skill : 0
Labor : 0
Driver 0
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 0
Butterfly valve S-150 : 0
Bara : 0
Bolo : 0
Shovel : 0
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw :
Generator Set : 4
Breaker : 4
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
NO RATE AMOUNT REMARKS
0
0
0
0
0
0
0
PHP
4
4
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
37 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
59%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 14
Driver 2
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Chainsaw :
Generator Set : 4
Breaker : 4
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F C C
NO RATE AMOUNT REMARKS
2
1
1
1
2
14
2
PHP
4
4
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
38 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F C F F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
61%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 1
Skill : 2
Labor : 14
Driver 2
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Mixer : 6
Generator Set : 4
Breaker : 4
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F C C
NO RATE AMOUNT REMARKS
2
1
1
1
2
14
2
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
39 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F F F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
62%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 2
Skill : 2
Labor : 15
Driver 2
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Mixer : 6
Generator Set : 4
Breaker : 4
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
F F F C
NO RATE AMOUNT REMARKS
2
1
1
2
2
15
2
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
40 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F F F F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
64%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
Ongoing
22 23 24 25
MARKS
____________
DAILY WORK ACTIVITY REPORT
PROJECT TITILE : INSTALLATION OF HDPE LINER PAD- G
LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN : THIS PERIOD : PREVIOUS :
COMMULATIVE ACTUAL : THIS PERIOD : PREVIOUS :
TIME LINES : PLANNED START : O8/21/2023 : ACTUAL START : August 30, 2023
: PLANNED COMPLETION : October 21, 2023 : ACTUAL COMPETION :
8:00 - 4:00
: PLANNED DURATION : 62 : ACTUAL DURATION :
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 2
Skill : 4
Labor : 15
Driver 2
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
:
Cement : 20
Bara : 1
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Mixer : 6
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S S S
NO RATE AMOUNT REMARKS
2
1
1
2
4
15
2
PHP
20
1
2
4
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
43 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
S F S S F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
67%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
DONE
DONE
DONE
DONE
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 2
Skill : 4
Labor : 15
Driver 2
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Mixer : 6
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S S S
NO RATE AMOUNT REMARKS
2
1
1
2
4
15
2
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
44 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
R R S S F
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
70%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
DONE
DONE
DONE
DONE
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 2
Skill : 4
Labor : 15
Driver 2
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Mixer :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S F F
NO RATE AMOUNT REMARKS
2
1
1
2
4
15
2
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
45 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F R R R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
72%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
DONE
DONE
DONE
DONE
22 23 24 25
MARKS
____________
PROJECT TITILE : INSTALLATION OF HDPE LINER
LOCATION : MT. APO GEOTHERMAL PROJEC
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN :
COMMULATIVE ACTUAL :
TIME LINES : PLANNED START
: PLANNED COMPLETION
8:00 - 4:00
: PLANNED DURATION
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer : 2
Safety Officer : 1
Competent Person : 1
Foreman : 2
Skill : 4
Labor : 15
Driver 2
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
10" spigot : 2
Butterfly valve S-150 : 2
Bara : 2
Bolo : 2
Shovel : 4
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Mixer :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
S S F F
NO RATE AMOUNT REMARKS
2
1
1
2
4
15
2
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
46 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
F F R R R
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
74%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
DONE
DONE
DONE
DONE
22 23 24 25
MARKS
____________
DAILY WORK ACTIVITY REPORT
PROJECT TITILE : INSTALLATION OF HDPE LINER PAD- G
LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
TIME LINES : PLANNED START : O8/21/2023 : ACTUAL START : August 30, 2023
: PLANNED COMPLETION : October 21, 2023 : ACTUAL COMPETION :
8:00 - 4:00
: PLANNED DURATION : 62 : ACTUAL DURATION :
The Competent person was not around, thus theres no work done.
Prepared by : Noted By : Checked and Verified By:
The Competent person was not around, thus theres no work done.
Prepared by : Noted By : Checked and Verified By:
ACTIVITIES; Unit
1 PRELIMINARY & GENERAL WORKS
1.1 Mobilization and Demolization
1.2 Tempory Facilities
1.3 Supervission
1.4 PPE Benefits and Other cost
2.0 CIVIL STRUCTURAL WORKS
2.1 OVERFLOW AND DRAIN CATCHMENT BASIN
2.2.1 Manual Excavation
2.2.2 3000Psi Concrete
2.2.3 Reinforcement Bars
2.2.4 6" CHB Wall
2.2.5 Plastering and Finishing
INSTALLATION OF 10" HDPE OUTLET AND DRAIN
2.2.1 chipping of concrete wall
2.2.2 supply and installation of butterfly valves S-150 with flange and stud bolts
2.2.3 Supply and installation of 10" HDPE spigot
INSTALLATION OF 2MM THK. HDPE LINER
2.3.1 Supply and installation of 2mm thk. HDPE LINER
2.3.2 (HDPE fastener) : supply and install 6mm. Thk.x 50mm. Wide stainless steel flat bar
2.3.3 ( HDPE fastener ) : supply and install 10mm dia.x 75mm long stainless steel anchor bolts with washer placed @150
STONE MASONRY CASCADING CANAL
2.4.1 Manual Excavation
2.4.2 stone masonry works
TOTAL
WEATHER REPORT : (S - SUNNY, F - FAIR,C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
TIME 8AM - 4PM : 1
WEATHER :
(S - SUNNY, F - FAIR, C-CLOUDY, R - RAIN, HR - HEAVY RAIN)
FINANCIAL ACCOMPLISHMENT REPORT:
MANPOWER REPORT:
CLASSIFICATION: : NO
Field Engineer :
Safety Officer :
Competent Person :
Foreman :
Skill :
Labor :
Driver
TOTAL MANPOWER COST
MATERIAL UTILAZATION REPORT :
CLASSIFICATION: : QTY
:
Cement :
Bara :
Bolo :
Shovel :
DAILY MATERIAL COST
EQUIPMENT UTILIZATION REPORT :
CLASSIFICATION: : HOURS
Mixer :
Generator Set :
Breaker :
DAILY EQUIPMENT COST
DELIVERY REPORT :
CLASSIFICATION: : QTY
:
:
:
:
:
OTHER INDIRECT COST :
CLASSIFICATION: : QTY
:
:
DAILY INDIRECT COST
Prepared by :
Prepared by :
JOHNRAY L. BALAYANAN
DAILY WORK ACTIVITY REPORT
INSTALLATION OF HDPE LINER PAD- G
MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
MATKR-MPC
: THIS PERIOD :
: THIS PERIOD :
PLANNED START : O8/21/2023
PLANNED COMPLETION : October 21, 2023
PLANNED DURATION : 62
Wt%
13.86%
1.31%
5.74%
2.75%
0.48%
0.50%
1.16%
1.81%
1.79%
100.00%
2 3 4 5 6 7 8 9 10 11
NO RATE AMOUNT REMARKS
PHP
PHP
PHP
PHP
PHP
ACTION TAKEN
Noted By :
Noted By :
ARNEL M. PONCE
: PREVIOUS :
: PREVIOUS :
O8/21/2023 : ACTUAL START :
October 21, 2023 : ACTUAL COMPETION :
62 : ACTUAL DURATION :
55 % DAYS ELAPSE:
12 13 14 15 16 17 18 19 20 21
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
REMARKS
_______________________
August 30, 2023
88%
REMARKS
DONE
DONE
Ongoing
Ongoing
DONE
Ongoing
DONE
DONE
DONE
DONE
DONE
DONE
Ongoing
Ongoing
Ongoing
DONE
DONE
22 23 24 25
MARKS
____________
DAILY WORK ACTIVITY REPORT
PROJECT TITILE : INSTALLATION OF HDPE LINER PAD- G
LOCATION : MT. APO GEOTHERMAL PROJECT - BRGY. ILOMAVIS, KIDAPAWAN CITY- PAD G
CONTRACTOR : MATKR-MPC
P.O. No. :
COMMULATIVE PLAN : : THIS PERIOD : : PREVIOUS :
COMMULATIVE ACTUAL : : THIS PERIOD : : PREVIOUS :
TIME LINES : PLANNED START : O8/21/2023 : ACTUAL START : August 30, 2023
: PLANNED COMPLETION : October 21, 2023 : ACTUAL COMPETION :
8:00 - 4:00
: PLANNED DURATION : 62 : ACTUAL DURATION :