Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

How to assign resource / resource loading / make resource


plan in Primavera P6
Posted Fri, 2017-09-01 07:50 by Khuong Do

In Primavera P6, after finish creating the schedule, you may need to assign resource to activity to make the resource
plan.

I will show you how to do it.

Let say you have a schedule like in below picture:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 1/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

To assign resource, first you need to create one.

Go to menu Enterprise -> Resource.

Click on Plus icon to create a new resource.

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 2/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

In my case, I create 4 resources in Material type.

For the Unit of Measure, if you don't see the Unit you need, Go to menu Admin -> Admin Categories

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 3/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Go to Units of Measure tab and click Add to create a new Unit

After finish creating resource, Go back to Activities window (Go to menu Project -> Activities)

Select activity, Go to Resource tab, click on Add Resource:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 4/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Click on Display -> Filter By -> All Active Resource to see your resource

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 5/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Select the resources you want to assign and click Assign button:

In Budget column, enter the correct quantity:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 6/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

By default, when you assign resource to activity, the unit will be distributed linearly. For example: assign 80 m3 to 10
days activity, each day will take 08 m3.

In case you don't want distribute resource linearly, you can show the resource curve column. Right click in Resource
tab, click Customize Resource Columns:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 7/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Show the Curve column.

Click on the Curve column and select Back Loaded for example.

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 8/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Now we can see the resource is distributed more at the end period of activity:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 9/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Go to menu Project -> Resource Assignments. We can make the layout look like below picture:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 10/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

(You can download the Primavera layout here)

Now we can easily see the Quantity Plan:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 11/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 12/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Another useful report is Concrete Plan Chart.

Go to Activities window, Click on Resource Usage Profile.

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 13/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Select Concrete resource, on the chart area Right click and select Resource Usage Profile Option:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 14/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Adjust option like below picture:

Now we can have the report like this:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 15/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

(You can download the Primavera layout here)

Later, when we update process (having Actual data), the report will be like this:

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 16/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Thank you for your time to read this article.

You can also find other post at my personal blog : https://doduykhuong.com


Printer-friendly version Login or register to post comments Send to friend
MARKET PLACE
Title: Eastwood Harris Pty
Advert: Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an
internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or
public courses.
Website: http://www.eh.com.au/

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 17/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls

Website Development by Hunt Data Solutions and Vit-al Interactive. CMS: Drupal THEME: Acquia Marina

www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 18/18

You might also like