AG Piping ITP
AG Piping ITP
* All applicable formats shall be identified from the ITP and records sha II be maintained.
Note:
1. Each specific Inspection and Test Plan (ITP) will h6ve a revision number, which is individually changed as the ITP
is revised. The referenced forms are included in and controlled by the referenced document. Therefore, the latest
revision of these forms, at the time of initiation of the ITP, will be utilized. The referenced forms will be incl uded
only during ITP review cycles prior to issue for construction (IFC).
This ITP shall be used as Inspector and Test Plan before execuUon of the Job, whereas during
and after iob
execution it shall be used as checklist.
Leo en d of Z nso ection Reg uirements:
H: Hold Point is a mandatory inspection pot nt and work shall not oroceed without the presence of a
representative of the cognizant organization.
Witness Inspection Point: Designated Witness Points for the involved personnel, which are required to be
signed off by Witnessed person net. All activities, which have a ”W” point, will require a written notification to
Company Inspector, in the event that the Company Inspector does not attend within an agreed period the
work may oroceed. In such cases, the Vendor‘s /contractor‘s Inspectors will record in the aopropriate
signature space on the forms "Not Witnessed”, and shall sign and date such spaces.
% Witness Inspection Point: Designated percentage Witness Point assigned by the Company, which will
Require written notification from the Vendor/contractor. In the event Company Inspector does not aLtend
within an agreed period the work may proceed. The percentage shall mean a minimum of 10% inspection, if
not otherwise agreed in the contract; however this nnay be increased at discreNon ofthe Company
Inspector.
S: Surveillance/ monitoring: Random observation of the controls of process activities. However, such
activities are not required to be sipned off by Company Inspector.
DR: Document Review/ Review: This entails review of appropriate documenta of.
EPCMD-2-QMO0-ITP-PP-010 ¿• (- ‘@*‘" ,‹
08 30.11.2015 Issued for Implementation P@/ QMD Leads )" SP
07 28.11.2015 Issued for Implementation NNS PPP SNS
06 15.10.2015 issued for Implementation PPP QMD Leads SNS
05 27.03.2015 Revised & Issued for Review PPP QMD Leads SNS
04 21.02.2015 Revised & Issued for Implementation PPP QMD Leads SNS
SNS / Rick
03 02.09.2013 Revised & Issued for Implementation PPP / AU KSS
Tucker
FIuor Comments & N!IQA requirements
02 22.12.2012 PPP KSS SNS / Karl
Incorporated - IFI
Prepared Checked Approved
Rev Date Revision
By By By
N one: - This FTP prov odes genera I information . This is vaiid (or speci lie pro3ecr onIy when reviewed and modified as per specific proJecr
requirements and approved by authorized person.
ITP No. : EPCMD 2 QM00 ITP PP
Inspection and Test Plan For
010 Rev. No. 08
Date : 30.11.2015
Above Ground Piping
Reliance Sheet No. : 2 of 17 Fabrication & Erection at Field
Project: Plant: Unit:
Reliance
Sr. Controlling
Activity Description Acceptance Criteria Verifying Forms Contractor
No. Document (s) Execution QMD O & M/CES
1.0 General
Check the release notes for pipe racks / sleepers
EPCMD
1.1 /structures / equipment / Civil Pipe Support (CPS) Approved drawing Approved drawing H H S S
2QM00FMTME226
etc. as applicable.
Approved Latest Approved Latest
Check availability of latest drawings, project Document Control
1.2 Drawings, Drawings, H H S S
specification. Register
Specifications Specifications
2.0 Site Storage & Material Verification
Ensure Pipes & spools are stored on proper EPCMD EPCMD EPCMD
H H S S
2.1 dunnage 2QM00JEPPP002 2QM00JEPPP002 2QM00FMTPP039
Below 12" pipes are provided with end caps, if EPCMD EPCMD EPCMD
2.2 H H S S
missing replenish 2QM00JEPPP002 2QM00JEPPP002 2QM00FMTPP039
Flanges are stored properly without any flange EPCMD EPCMD EPCMD
2.3 H H S S
face serration damage 2QM00JEPPP002 2QM00JEPPP002 2QM00FMTPP039
Valves are stored properly with end caps/ original EPCMD EPCMD2QM00FMT
2.4 EPCMD2QM00JEPPP002 H H S S
packing 2QM00JEPPP002 PP039
Lay down areas are available with proper draining EPCMD EPCMD EPCMD
2.5 H H S S
facilities to avoid water logging 2QM00JEPPP002 2QM00JEPPP002 2QM00FMTPP039
EPCMD
Verify physical condition of the piping materials /
Project Specification/ 2QM00FMTPP011
2.6 pipe spools, before erection. Ensure internal Project Specification H H S W
Physical condition Spool sheets
cleanliness of the piping components.
Release note
Check the thickness o rusted or pitted raw Project Specification EPCMD
2.7 Project Specification H H H S
materials, if any. f 2QM00FMTME050
Legend: CES: Central Engineering Services-Inspection, NDT: Non Destructive Testing, P & ID: Process & Instrumentation Diagram, O & M: Operations & Maintenance
Contractor Engineer Reliance Execution Reliance QMD Reliance O & M / TPI
Signature
Name
Date