‫مثال‪ :1-‬من انمعهوماث أدناه انخاصت بأحذ انمشاريع‪ .

‬انمطهوب حساب مذة انمشروع انخي ححقق اقم كهفت أجمانيت ممكنت‬
‫باسخخذاو حقنيت انـ )‪ (Crashing‬أرا كانج انكهف انغير انمباشرة (‪350 $/week= )Indirect Cost‬‬

‫‪Act.‬‬ ‫‪Dep.‬‬ ‫‪NT‬‬ ‫‪CT‬‬ ‫‪NC‬‬ ‫‪CC‬‬ ‫‪ΔT = NT–CT‬‬ ‫‪ΔC = CC–NC‬‬ ‫‪CS = ΔC/ ΔT‬‬
‫‪A‬‬ ‫‪-‬‬ ‫‪5‬‬ ‫‪3‬‬ ‫‪2000‬‬ ‫‪2500‬‬ ‫‪2‬‬ ‫‪500‬‬ ‫‪250‬‬
‫‪B‬‬ ‫‪A‬‬ ‫‪8‬‬ ‫‪2‬‬ ‫‪3000‬‬ ‫‪5000‬‬ ‫‪6‬‬ ‫‪2000‬‬ ‫‪333‬‬
‫‪C‬‬ ‫‪A‬‬ ‫‪6‬‬ ‫‪4‬‬ ‫‪3000‬‬ ‫‪4500‬‬ ‫‪2‬‬ ‫‪1500‬‬ ‫‪750‬‬
‫‪D‬‬ ‫‪A‬‬ ‫‪4‬‬ ‫‪4‬‬ ‫‪2500‬‬ ‫‪2500‬‬ ‫‪0‬‬ ‫‪0‬‬ ‫‪---‬‬
‫‪E‬‬ ‫‪B,C,D‬‬ ‫‪5‬‬ ‫‪3‬‬ ‫‪1500‬‬ ‫‪4000‬‬ ‫‪2‬‬ ‫‪2500‬‬ ‫‪1250‬‬
‫=‪‬‬ ‫‪12000‬‬
1- Without crashing (Normal) – C.P. (A-B-E)

5 13
B 8 Act. ΔT CS
5 13 A 2 250
B 6 333
E 2 1250
0 5 5 11 13 18
A 5 C 6 E 5
0 5 7 13 13 18 Legend
ES EF
5 9 Act. Dur.
D 4 LS LF
9 13

Direct Cost = 12,000

Indirect Cost = 18 × 350 = 6,300

Total Cost = Direct Cost + Indirect Cost = 12,000 + 6,300 = 18,300


2- Crash A by 2 weeks
3 11
B 8
Act. ΔT CS
3 11
A 0 250
B 6 333
0 3 3 9 11 16 E 2 1250
A 3 C 6 E 5
0 3 5 11 11 16 Legend
ES EF
3 7 Act. Dur.
D 4 LS LF
7 11

Direct Cost = 12,000 + 2 × 250 = 12,500

Indirect Cost = 16 × 350 = 5,600

Total Cost = Direct Cost + Indirect Cost = 12,500 + 5,600 = 18,100


3- Crash B by 2 weeks

3 9
B 6 Act. ΔT CS
3 9 A 0 250
B 4 333
0 3 3 9 9 14 E 2 1250
C 2 750
A 3 C 6 E 5
0 3 3 9 9 14 Legend
ES EF
3 7 Act. Dur.
D 4 LS LF
5 9

Direct Cost = 12,500 + 2 × 333 = 13,166

Indirect Cost = 14 × 350 = 4,900

Total Cost = Direct Cost + Indirect Cost = 13,166 + 4,900 = 18,066


4- Crash B & C by 2 weeks
3 7
Act. ΔT CS
B 4
A 0 250
3 7 B 2 333
E 2 1250
0 3 3 7 7 12 C 0 750
A 3 C 4 E 5
0 3 3 7 7 12 Legend
ES EF
3 7 Act. Dur.
D 4 LS LF
3 7

Direct Cost = 13,166 + 2 (750+ 333) = 15,332


Indirect Cost = 12 × 350 = 4,200
Total Cost = Direct Cost + Indirect Cost = 15,332+ 4,200= 19,532
 Since the new TC (total cost) is greater than previous TC, stop the iteration.
 The previous iteration solution (No. 3) is the best for implementation.
 Therefore, the final crashed project completion time is 14 weeks and the TC is 18,066 $