Professional Documents
Culture Documents
BDD - PM005 - Maintenance Scheduling V2
BDD - PM005 - Maintenance Scheduling V2
PM005–Maintenance Scheduling
Revision History
Version Date Description Author
1 Aug 10, 2017 Initial Document Jose Munoz
2 Aug 17, 2017 Final version after Nicolas Folio review Jose Munoz
Table of Contents
PM005 – Maintenance Scheduling ............................................................................................................... 4
1. Purpose ................................................................................................................................................. 4
2. Assumptions .......................................................................................................................................... 4
3. Process Diagram.................................................................................................................................... 4
4. Process Steps ........................................................................................................................................ 4
4.1. T-Week Schedule .......................................................................................................................... 5
4.2. Revision ......................................................................................................................................... 5
4.3. Scheduling Orders to Available Capacity-Concept........................................................................ 6
4.3.1. Available Capacity ................................................................................................................. 6
4.3.2. Capacity Evaluation – Work Center ...................................................................................... 6
4.3.3. Transaction CM01 ................................................................................................................. 7
4.4. Scheduling - Detail Process ........................................................................................................... 8
4.4.1. Reschedule ............................................................................................................................ 9
4.4.2. Materials availability ............................................................................................................. 9
4.4.3. Maintenance, Operations and Planning Meeting ................................................................. 9
4.5. Backlog Management ................................................................................................................. 10
4.6. Dispatching – assigning work orders to individuals .................................................................... 10
4.7. Shutdown Scheduling.................................................................................................................. 10
5. Business Needs & Requirements ........................................................................................................ 11
6. Business Control Risks ......................................................................................................................... 11
7. Configuration Considerations ............................................................................................................. 11
7.1. Tracking Work Orders during the process .................................................................................. 12
7.2. Priority......................................................................................................................................... 14
7.3. Available Capacity ....................................................................................................................... 15
1. Purpose
This document describes the weekly / daily running maintenance scheduling process. All work generated
from preventive maintenance, corrective maintenance, refurbishment and project work requests forms
the common order pool of work to be planned and scheduled. The scheduling is carried out using
available capacities of crews.
2. Assumptions
The following assumptions were made with respect to the design of this business process:
Emergency Orders are excluded from this scheduling process as they are executed using the “Fix
it Now” philosophy. Scheduling will be coordinated verbally for emergency orders.
Materials are assumed to be available for the work order at the time the schedule is prepared.
The scheduler will be preparing a 1 day and 7 day schedule.
Scheduling is carried out at the crew level (work center).
The shutdown/outage scheduling will be incorporated and be performed in coordination with
the weekly scheduling process, but will be managed as a separate scheduling activity.
Time entry confirmations and/or Technical completion of orders need to be completed on a
daily basis in order to have full visibility of the true backlog of orders and the current available
capacity of work centers.
3. Process Diagram
Not Applicable.
4. Process Steps
The scheduling process is a sub-process of other maintenance processes described in separate
documents. This process covers the scheduling stage of the maintenance work order process.
The following scheduling process is recommended as it has provided good results at other companies
and it is based on a number of activities which allows the preparation of a weekly schedule and up to 5
weeks look ahead of upcoming requirements.
4.2. Revision
The revision field in the work order is used to define weekly ‘buckets’ to which work orders are assigned.
Each work order is assigned a revision, which identifies which week the work is scheduled for.
1. Weekly
o Example: WK-42-17 or WK161017 with description “Week 42 – Oct 16, 2017 to Oct 22,
2017”
2. Outage
Determine the revision to assign the work order based on priority and system condition
(running, shutdown etc.) – Planner may have pre-determined the revision based on known
lead time of equipment or material availability.
Assess the capacity requirements at the crew level initially within the scheduling window (one
week window for example).
Assign orders based on capacity availability by:
NOTE:
Preventive and Corrective Maintenance Orders will be assigned revisions.
Preventive work orders will be scheduled or assigned to a revision first. Corrective work orders
will be assigned to the remaining capacity available for that particular work center. While this is
the general practice, priority also plays a role, with Urgent Corrective orders displacing
Preventive orders when needed. The actual firm date of execution of a work order will be
determined in the Daily/Weekly maintenance planning meeting with supervisors and
operations.
Emergency Orders
Sick leave, training and vacation (work centers available capacity will need to be
maintained)
Possible underestimating of man-hours required for jobs
Hence, the remaining available capacity in nearby weeks is < 100% of the total available
capacity, and the scheduler will schedule the orders on the basis of:
Capacity Evaluation does not take vacation/absences into account. For this reason
adjustment to the work centers available capacity need to be regularly maintained.
The scheduler will look at the available capacity for a particular week and assign work
orders to that week via IW38 and Revision Number until the desired capacity has been
consumed
If capacity is exceeded, and the assignment is for a specific date, the scheduler may
want to consider the rescheduling of the individual order
Back log will be displayed in the first row. This is the day or week before current period, as show
above.
The detailed capacity view will show the orders that are loaded to the capacity in a given day or
week as shown below:
NOTE:
At this point work orders are associated only with a weekly bucket and the capacity evaluation is
performed for the whole week against the work center. Specific dates, i.e. Mon, Tues, Wed etc.
as to when the work order is to be performed within the revision is NOT done until the next
step.
The scheduler will be able to view a work center available capacity and act accordingly. If capacity is
exceeded, the scheduler will try and reschedule the job.
The scheduler using IW38 will select all outstanding orders that have been planned by searching those in
user status Planning Complete/To Schedule (PLND) and assigning a revision week code after verifying
work center capacity availability using CM01. Usage of two screens is preferable, lacking that scheduler
should use multiple sessions.
If the work order is in status EXEC (work in progress) see “Backlog Rescheduling” below.
If the work order is in status SCHD (on the schedule), after verifying that capacity is
available for the work center(s) (CM01), change the start date of the first operation to
the new date and then reschedule (this will maintain the basic start for the purpose of
schedule compliance reporting). In doing this more than one order may be affected and
more rescheduling may be necessary.
If the work order is in status PLND or SCHD, the order can be moved to a new date not
only by means of changing the basic start date but also through applying a new revision
code.
User status WMAT will be used to select orders that have this status set in order to
verify that all parts have been received, or, if parts have not been received, expedite
their delivery.
When running IW38, from the list display menu, will be possible to select “list of
available materials”; from the new displayed report you can determine what materials
still need to be deliver.
Material availability can be checked frequently and for a particular revision. The list
generated will allow the planner/scheduler to review all orders with missing materials
efficiently.
When a work order shows that all materials have been received, the status PLND (Planning
Complete) can be assigned to the order.
Using IW38 will print a list of orders that are in status ready to schedule and propose for
discussion all orders that are ready to be firmed up for the following week schedule
(T1).
The agreed upon list of work orders will be set in status EXEC the day before they are
due for execution
And any order that is not emergency or urgent should not have scheduled dates in the past (i.e.
they have to be rescheduled if they were not executed).
When rescheduling an order in EXEC status, the scheduler will change the starting date of the operation
next in line to be executed, maintaining the basic start date intact (this for scheduling compliance
purposes).
The scheduler should always schedule on the basis of priority. The following rules are to be observed:
Highest Priority should be scheduled first followed by the second highest then followed by lower
priorities
If there are two orders with the same priority but not enough resources for both. The scheduler
can always look at the criticality of the equipment to aid him in selecting the order that should
be executed first
Outage planning will require the creation of Maintenance Plans. The structure of these maintenance
plans may follow the following approach:
Specify the magnitude of the outage, by specifying the areas that need to be shutdown
Identify the equipment that need to be maintained within each of the areas that is shutdown
Identify the sequence of events (stages) that will need to take place in order to dismantle, maintain
and re-assemble the equipment in each area.
Create maintenance plans by plant areas. Multiple plans could be created for each shutdown stage.
When structuring these plans consider which plans could be performed in parallel
From this point work orders may be selected using the revision codes and downloaded to a spreadsheet
for further processing.
Actual costs of shutdowns will be available by summarizing total actual costs by revision code.
7. Configuration Considerations
Below are some configuration items previously discussed in other work order processes but which
predominantly affect the scheduling process. Specifically:
7.2. Priority
Priority should be determined based on objective criteria. To support this, a criticality assessment
should be used to aid in the assessing the priority of the job. The criticality assessment should be
performed on equipment based on measurable impact should an equipment fail. The impact is generally
categorized into “Safety”, “Environmental” and “Operational”. The criticality is a function of likelihood
and consequence of failure.
The equipment criticality level (ABC Indicator field) will be displayed in the notification and the work
order and will be defaulted from the functional location or the equipment. A priority number will be
given for the job using the equipment criticality level as a guide.
8.1. Forms
No custom forms specific to the Maintenance Scheduling Process are required.
8.2. Reports
Standard reports will be utilized to the extent possible for Operational Reports. The SAP PM module
offers a flexible reporting tool to use for Notifications, Notification Tasks, Orders and Operations.
8.3. Interfaces
No interfaces required for the Maintenance Scheduling Process.
8.4. Conversions
No conversions required for the Maintenance Scheduling Process.
8.5. Enhancements
No enhancements required for the Maintenance Scheduling Process.
Illumiti Consultant:
Jose Munoz
Illumiti QA Reviewer: