Professional Documents
Culture Documents
Applied Proj MGMT Final Project
Applied Proj MGMT Final Project
Applied Proj MGMT Final Project
1.
2) Please highlight the major areas of strength in the management of this phase of the project:
The highlighted major Strengths were the Time management, Human resources, and
Integration Management.
3) Please highlight the major opportunity for the improvement in the management of the phase of
the project:
The Inception Phase of the Project shows some promise in the beginning, but once the
project started there were some mishaps along the way. Having two countries working together
on the project, there were bound to be communication errors with both speaking different
languages and receiving information. These come along with the quality of material needing to
be redefined based on the approval of safety protocols and with the ICG laws. These factors push
both the scheduling and the total cost higher. This results in putting a burden on both parties
involved. If there was a way to communicate with each other faster, there would have not lost on
the financial level. Communication was the key part when it came to a big project. The risk
would be higher, but if people who work on the project also do more research on the
DEVELOPMENT PHASE:
Summary
The development phase of the project was an important phase. Unfortunately, this phase had a
approvals, yet a lot of these aspects of the project weren’t fulfilled. Detailed planning was hard
due to the enormous scope of the project. However, the project team was able to plan technical
equipment needed for the project at a reasonable performance. Unfortunately, this barely
mitigated the problems to understanding the scope of the project. IGC had problems with getting
approval for funding the project, which added more problems to the cost and scope management.
The difficulties in the cost management and planning can be partly blamed for the $2.25 billion
claim against Eurotunnel by a contracting company. Another problem that was brought to the
cost management is that the project involved being funded by banks. Since the banks had the
funds, they were given control on the project. In consequence, they were given too much leeway
on how to go about the project. The banks focused on minimizing risk. Usually, this can be a
good thing. However, this was taken to the extreme for the Chunnel Project. The efforts to
minimize cost and risk were soiled due to the claim and award settlement that went against
Eurotunnel. Fortunately, the quality aspect of the project was done well due to the IGC’s control
of the project.
Since the project consisted of two different countries speaking two different languages,
communication was a problem. There was no encouragement of teamwork. Even worse, the two
teams are at the opposite ends of each other. Even though both teams are working towards a
common goal, the lack of communication in its early stages led to different opinions in the later
The project management team’s views on the project were rather hopeful. They had a
clear understanding of the size of the project. Unfortunately, they couldn’t come up with a plan
to deal with the immense size of the project. The nail in the coffin was hammered once the
management team gave up most of its control to the IGC. The risk/cost minimization, cultural
differences between the two working teams, and other challenges faced in this phase cooked a
1.
Scope Management 1
Time Management 2
Cost Management 1
Quality Management 3
Communications Management 1
Risk Management 4
Procurement Management 3
Integration Management 1
2. The strengths during this phase of the project are that the project management team had a
grasp on how big the project was going to be. All technical aspects of the project was
well thought out and planned. In the later stages of the phase, when the IGC was
involved, risk management was heavily considered in the planning of this phase.
Moreover, the IGC’s involvement and control helped with the quality aspect of the
project.
3. An opportunity for improvement for the project can be that the project management team
could’ve kept their control of the project, and instead do further research to plan a way to
deal with the project scope. Another room for improvement is communication between
two countries. There could’ve been a way for both cultures to communicate their plan
and ideas in the early stages of project. Furthermore, teamwork between the two
Scope Management 2
Time Management 2
Cost Management 2
Quality Management 5
Communications Management 2
Risk Management 2
Procurement Management 3
Integration Management 3
2. The main strengths in the Implementation Phase of this project is quality management and
3. The Implementation Phase can improve on scope management and time management and cost
Summary
The implementation phase of the Chunnel project began in the fourth quarter in 1987, with the
(CTG/FM) bid for US $5.5 billion dollars. However, it ended on December 15th, 1994, with the
project being handed over fully operational. The main proposal was made under a “build-own-
transfer” (BOT) arrangement, granting CTG/FM the concession to run the project for a period of
55 years (Morris, 1994), after which ownership would revert to the French and British
governments. Having gotten the approval for the proposal CTG/FM were granted a
construction companies which had investors (through join ventures) with the CTG/FM winner.
There were instances of conflicts between the client-contractor relationship. This would cause
problems as the project was implemented. When the construction contract was assigned, the cost
estimated to be US $4.3 billion dollars and the original start date was May 15th,1993. After the
implementation phase was completed, the project was 19th months late and had cost exceed of
some US $3 billion (total construction cost was US $7.1 billion). The close out phase goes more
in depth on the total cost impacted not only the construction cost but also more crucially, the lost
in profits and carrying cost of the project during the 19-month period. It is generally designated
that the Chunnel project displays magnificent opportunities for lesion learned in project
management, especially for capital-intensive projects, using new or proven technology, under
uncommon, or new high-risk conditions. There were other issues that stood out that should’ve
1. Some of the rolling stock had not yet been designed (vehicle and freight cars).
2. No contingency was set aside to cover “unknown unknows.” (In this case, the need for a
3. The specification for British rolling stock and French rolling stock were not the same.
All these issues should have been noticed before and the details needed to be agreed to in
advance, and not having a resolution would only result in more delays and cost overrun. The
priorities of this project were to be identified and communicated clearly from the beginning.
This was perhaps a huge and most damaging failure of the governments of France and
Britain. The financial model that they created was far too promising given the risks involved,
and the face that the project was run by bankers that made it difficult. By not having real
objectives and having a scope defined early on, and by not implementing a contracting
method that directly connected thew rewards to contractors. Both governments set the stage
2. Please highlight the major areas of strength in the management of this phase of the project
Quality management was the only management area that proved to be a strong point in the
closeout phase of the project and in the project in general. The quality standards that were
achieved by the project were above the industry average and the project was deemed one of the
3. Please highlight the major opportunities for improvement of this phase of the project
During the closeout phase, the Chunnel project had a couple of opportunities to improve upon,
mainly regarding project scope and communication. In terms of scope, the overall scope of the
project changed many times throughout the project. There were many change requests that were
brought up including requirements such as an air conditioning system throughout the tunnel.
Summarizing the project, Kirkland states: “We should seek to advise future generations
contemplating the creation of very large infrastructure developments not to get carried away by
the excitement of the design and construction process”. This statement made by Kirkland
describes the scope situation very well. There was a great opportunity to fix the overall scope of
the project through closeout by rejecting some scope modifications and having set requirements
and sticking with them. This open-ended nature of the scope led to many schedule and cost
delays that caused considerable damage and was impossible to mitigate during the closeout
phase. Another opportunity that could have improved the project is the introduction of team-
building activities. With the language barrier between countries and stakeholders, an effective
team-building exercise could prove very beneficial to communication between the two parties.
Although small in change, this exercise could have caused change management aspects of the
project to improve drastically regarding funding requests and schedule delays. Overall, the
2. Please highlight the major areas of strength in the management of this project
3. Please highlight the major opportunities for improvement in the management of this project
The areas of importance regarding the weaknesses of the project are mostly to do with cost and
contract management. In the case study, there were many contractual issues that could have been
addressed better. A solution to the contractual issues that have arisen during the management of
the project could be to establish a standardized set of rules that must be met to issue changes in
the project. This promotes a more uniform decision-making process and does not allow the
different groups involved in the project to force a change. This way of determining if the project
needs to be changed helps better structure the overall scope and risk of the project and the
changes associated with it. Overall, a standardized set of rules that must be met before change
will give the project management more control. For example, without rules, the project scope
became more favorable towards the bankers of the project as opposed to the actual delivery of a
quality product. This led to many obstacles arising regarding cost and deliverability as well as
conflict between priorities and parties.
4. Please highlight the major project management lessons learned from this project
The Chunnel project provided a lot of mistakes and success that is valuable in teaching project
management. Some major lessons learned from the project range from strategic planning to the
importance of communication. Being such a large project that is also international, it is important
to take away the fact that the project must be very meticulously planned. Technical specifications
and requirements for the project must be agreed upon and established before the project is even
implemented to have an accurate estimate of cost and time. Having clear objectives for the
project with appropriate compensation for the stakeholders is also extremely important for the
success of the project as well. Other aspects of project management such as having a method for
evaluating and approving changes in the project should be established before implementation as
well. The Chunnel project also showed the importance of collaborating and working in a team.
Establishing roles in a team with set expectations and responsibilities should be defined upfront
to make sure there are minimal mistakes that lead to control and risk problems.