Name of Site :
Inspected By :
Date :

Sl. Points Observation Measures


No.

1 Verticality of the Passenger Hoist Mast


2 Condition of the Mast & Car
3 Anchorage for the Mast and supporting structure
is adequate
4 End Mast piece is provided
5 Over-Hoist Limit Switch
6 Over run limit switch
7 Over load limit switch with warnings
8 Condition of the manual descender
9 Condition of Ropes / Rack & Pinion
10 All landing floors are provided with interlocking
arrangements (to ensure gate cannot be opened
till car comes to that particular floor).
11 Is Hoist position is safe, free from falling material
hazard
12 Emergency stop push button is functional
13 All floors are identified with suitable identities
14 Hoist is protection from unauthorised operations.
15 Earthing is provided
16 Hoist break is checked
17 Rotating parts of the Hoist is adequately
guarded
18 Ground level entry to hoist area is restricted with
wicket gate
19 Daily check procedure is followed
20 Operator Fitness
21 Authorised operators are allowed all the time.
22 Validity of the Third Party Fitness is checked
23 Display of Load chart & Emergency
preparedness