MCC - General Notes

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

lOMoARcPSD|36487264

Typical Drawing Ref.


Rev. Drawing No. Date
Z1 AB-TYP-S-201 11-Nov-17
A GENERAL CONCRETE MATERIAL SCHEDULE
A1 STRUCTURAL DRAWINGS READ IN CONJUNCTION WITH ALL OTHER DISCIPLINE DRAWINGS, DOCUMENTS, 28-DAY CUBE
ELEMENT GRADE COMPRESSIVE CEMENT TYPE REMARKS
SPECIFICATIONS ETC. AS MAY BE ISSUED DURING THE COURSE OF THE CONTRACT. ALL DISCREPANCIES TO ASTM C150
STRENGTH (Mpa)
REFERRED TO THE DESIGN CONSULTANT FOR DECISION BEFORE PROCEEDING.
SUBSTRUCTURE
A2 ALL DIMENSIONS ARE IN MILLIMETERS UNLESS NOTED OTHERWISE. DIMENSIONS NOT BE OBTAINED BY PILES K415 40.71 TYPE II
SCALING DRAWINGS. RAFT/ PILE CAPS K415 40.71 TYPE II
RETAINING WALLS K415 40.71 TYPE II DURABLE MIX
A3 ALL LEVELS SHOWN ARE IN METERS WITH REFERENCE TO ABU DHABI MUNICIPALITY DATUM UNLESS NOTED
OTHERWISE. GRADE BEAMS K415 40.71 TYPE II
GRADE SLAB K415 40.71 TYPE II
A4 FOR MAIN SETTING OUT LINES AND LEVELS REFER TO CIVIL DRAWINGS
BLINDING K140 13.73 TYPE I
A5 THE CONTRACTOR RESPONSIBLE FOR ENSURING THE SAFETY OF CONSTRUCTION AT ALL TIMES AND
D3 THE CONTRACTOR PERFORM AND SUBMIT FOR REVIEW INSTRUMENT SURVEYS OF FINISHED CONCRETE
ENSURE THAT NO PARTLY COMPLETED CONSTRUCTION IS HAZARDOUS.
SLAB SURFACES, BOTH BEFORE AND AFTER REMOVAL OF FORMWORK AND/OR SHORING SYSTEM TO
A6 THE CONTRACTOR PROVIDE TEMPORARY BRACING AND SHORING AGAINST LATERAL FORCES AND ALL
VERIFY AS-BUILT TOLERANCES.
CONSTRUCTION LOADS THROUGHOUT THE CONSTRUCTION PROCESS.

A7 D4 REFER TO SPECIFICATIONS FOR REQUIREMENTS OF CONCRETE SURFACE FINISH AND CASTING


ALL ELEMENTS OF THE STRUCTURE DESIGNED BY THE CONTRACTOR SUBMITTED TO DESIGN CONSULTANT
TOLERANCE.
FOR REVIEW. D5 PROVIDE UPWARD CAMBER TO SLABS AND BEAMS AS NOTED ON STRUCTURAL DRAWINGS AND/OR

THE DESIGN CONSULTANT'S REVIEW PROCESS FOR ALL SUBMITTALS, DRAWINGS, METHOD STATEMENTS SPECIFICATIONS. CAMBER BOTH UNDERSIDE AND TOP OF CONCRETE TO MAINTAIN THE SLAB AND BEAM
A8
AND DOCUMENTS IS ONLY COMPLETE ONCE A STATUS OF 'NO OBJECTION' IS REACHED. THE SUBMITTAL DEPTH SHOWN ON THE DRAWINGS UNLESS NOTED OTHERWISE.

REVIEWED BY THE DESIGN CONSULTANT FOR COMPLIANCE WITH THE DESIGN INTENT. THIS DOES NOT D6 AGGREGATE FOR CONCRETE FROM APPROVED SOURCE AND COMPLY WITH THE SPECIFICATION
RELIEVE THE CONTRACTOR FROM HIS CONTRACTUAL RESPONSIBILITIES. REQUIREMENTS.

A9 ALL DESIGN, WORKMANSHIP AND MATERIAL IN ACCORDANCE WITH THE CURRENT ACI, UBC, IBC, AISC AND D7 ALL CONCRETE CURED IN ACCORDANCE WITH THE SPECIFICATIONS.
LOCAL AUTHORITY STANDARDS AND PROJECT DESIGN CRITERIA UNLESS NOTED OTHERWISE. EQUIVALENT
D8 ALL REINFORCING BARS CONFORM TO BS 4449 GRADE 460 TYPE 2 DEFORMED HIGH YIELD BARS. DENOTED
BRITISH STANDARDS MAY BE ACCEPTABLE SUBJECT TO APPROVAL OF THE DESIGN CONSULTANT.
BY `T' ON STRUCTURAL DRAWINGS.

D9 REINFORCING BARS SHOULD BE EPOXY COATED


B FOUNDATIONS
D10 ALL REINFORCING BARS DETAILED, FABRICATED, LABELED, SUPPORTED, SPACED IN FORMS AND SECURED

B1 THE NET ALLOWABLE GROUND BEARING CAPACITY IS ASSUMED AS2 50kN/m AT 1.50m DEPTH FOR IN PLACE IN ACCORDANCE WITH THE PROCEDURES AND REQUIREMENTS OUTLINED IN THE CURRENT ACI

FOUNDATION TYPE 6 (PAD FOOTING FOUNDATIONS). 318 AND ACI 315 UNLESS NOTED OTHERWISE ON THE STRUCTURAL DRAWINGS.

D11 WELDING AND/OR SITE CUTTING OF THE REINFORCING BARS NOT BE PERMITTED UNLESS REVIEWED AND
B2 CONTRACTOR CARRY OUT GEOTECHNICAL INVESTIGATION AS NECESSARY TO SUPPORT HIS DESIGN OF
ACCEPTED BY THE DESIGN CONSULTANT.
CAST IN SITU DRILLED PIER FOUNDATION.
D12 ALL PROPRIETARY FIXING INSTALLED IN ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTIONS.
C EXCAVATION AND DE-WATERING
D13 MECHANICAL SPLICING OF LARGE DIAMETER BARS MAY BE ACCEPTABLE SUBJECT TO REVIEW BY THE
C1 THE CONTRACTOR PROVIDE SURFACE DRAINAGE CHANNELS, SUMPS AND SUMP PUMPS TO PROTECT ALL DESIGN CONSULTANT.
EXCAVATIONS FROM FLOODING. FLOODING OF ANY EXCAVATION AFTER APPROVAL OF SUBGRADE CAUSE
D14 ALL CONCRETE CONTAIN AN APPROVED WATER REDUCING, PLASTICIZING ADMIXTURE. APPROVED
FOR COMPLETE RE-PREPARATION AND APPROVAL OF THE SUBGRADE.
HIGH-RANGE WATER REDUCING ADMIXTURE MAY BE UTILIZED AT THE CONTRACTOR'S OPTION. ALL
C2 THE CONTRACTOR PROVIDE POSITIVE PROTECTION (MAT/SHEET COVERING) FOR ALL EXCAVATED SLOPES
CONCRETE PERMANENTLY EXPOSED TO WEATHER ALSO CONTAIN AN APPROVED AIR-ENTRAINING
TO PROTECT SLOPES FROM INSTABILITY AND DETERIORATION DUE TO ENVIRONMENTAL CONDITIONS.
ADMIXTURE TO PROVIDE PERCENTAGE OF AIR REQUIRED FOR SEVERE EXPOSURE AS PER ACI 318.

C3 THE EXCAVATION RETENTION SYSTEM DESIGNED AND INSTALLED BY THE CONTRACTOR, UNLESS NOTED D15 NO CALCIUM CHLORIDE USED IN ANY CONCRETE.
OTHERWISE, IN ACCORDANCE WITH THE GEOTECHNICAL DESIGN PARAMETERS AND SOIL PRESSURES AS
D16 THE FOLLOWING CONCRETE CLEAR COVER TO PRIMARY REINFORCEMENT PROVIDED, UNLESS LARGER
INDICATED IN THE GEOTECHNICAL INVESTIGATION REPORT.
COVER IS NOTED ON THE STRUCTURAL DRAWINGS.
C4 THE CONTRACTOR INSTALL AND CONTINUOUSLY SURVEY VERTICAL AND HORIZONTAL MOVEMENTS OF
THE TOP OF THE SOIL RETENTION SYSTEM, IF INSTALLED, BENCH MARKS ADJACENT TO AND AWAY FROM CONCRETE CLEAR COVER SCHEDULE
THE SITE PERIMETER FOR VERTICAL AND HORIZONTAL MOVEMENTS AND OBSERVATION WELLS FOR CLEAR COVER TO PRIMARY REINFORCEMENT (mm)

MONITORING WATER LEVELS BELOW GROUND SURFACE. ELEMENT ABOVE GROUND ABOVE GROUND
SURFACE IN CONTACT REMARKS
WITH GROUND INTERIOR EXTERIOR
C5 AFTER COMPLETION OF THE PERIMETER SOIL RETENTION SYSTEM, THE SITE DE-WATERED, AS ENVIRONMENT ENVIRONMENT
PILES 75 - -
NECESSARY, BEFORE (OR AS) THE EXCAVATION PROCEEDS. THE CONTRACTOR PROVIDE ALL COLUMNS/PEDESTAL 75 40 50
FOOTING 75 - -
CONSTRUCTION AND EQUIPMENT FOR THE DE-WATERING SYSTEM INCLUDING, BUT NOT LIMITED TO,
EQUIPMENT PADS 40 40
TRENCHES, SUMPS, DE-WATERING WELLS, WELL POINTS, OBSERVATION WELLS, PUMPING SYSTEM,
DISPOSAL LOCATION, SETTLING BASINS, MAINTENANCE AND EMERGENCY BACK-UP EQUIPMENT, ETC. . D17 SPLICES IN REINFORCEMENT CONFORM TO THE REQUIREMENTS OF THE RELEVANT BRITISH STANDARD
AND MADE ONLY IN THE POSITIONS SHOWN OR AS OTHERWISE APPROVED BY THE KEO. THE FOLLOWING
C6 THE DE-WATERING SYSTEM MAINTAIN THE WATER LEVEL AT MINIMUM OF 0.50 METER BELOW THE
MINIMUM SPLICE LENGTH USED UNLESS OTHERWISE NOTED
DEEPEST FOUNDATION SUBGRADE AT ALL TIMES.
BAR SIZE (mm) LAP LENGTH (mm)
10 500
D REINFORCED CONCRETE 12 600 NOTES:
D1 THE CONTRACTOR SUBMIT DETAILED RC DRAWINGS AND BAR BENDING SCHEDULES SHOWING BAR SIZES,
16 800 SPLICE LENGTHS PROVIDED FOR
SPACING, PLACEMENT AND SUPPORT DETAILS OF DOWELS AT EXPANSION JOINTS AND LAPS ETC. FOR
20 1000 THE SMALLER OF THE TWO BARS BEING
REVIEW AND ACCEPTANCE OF THE DESIGN CONSULTANT. WORK NOT COMMENCE UNTIL THE SHOP SPLICED
25 1250
DRAWINGS ARE REVIEWED AND ACCEPTED. REVIEW OF SHOP DRAWINGS DOES NOT ALLEVIATE THE 32 1600
CONTRACTOR'S RESPONSIBILITY TO COORDINATE THE INPUT OF ALL TRADES ON THE SHOP DRAWINGS. E PROTECTIVE COATINGS FOR CONCRETE
E1 UNLESS SHOWN OTHERWISE, ALL EXTERNAL CONCRETE SURFACE EXPOSED TO SOIL PROTECTED AS
D2 ALL CAST-IN-SITU CONCRETE HAVE MINIMUM 28-DAY CUBE COMPRESSIVE STRENGTH FOR VARIOUS
FOLLOWS: HORIZONTAL AND VERTICAL SURFACES: PROTECTION OF EXTERNAL CONCRETE SURFACE IN
ELEMENTS AS GIVEN IN THE CONCRETE MATERIAL SCHEDULE. ALL CONCRETE NORMAL WEIGHT
CONTACT WITH WATER & SOIL BELOW GROUND. ONE COAT PRIMER+ONE LAYER 5MM THICK TORCH
CONCRETE MINIMUM DENSITY OF 2400Kg/m³. AND MAXIMUM SIZE OF COURSE AGGREGATES OF 20mm
APPLIED SBS MODIFIED WATER PROOFING MEMBRANE+ONE LAYER OF 3MM THICK PROTECTION BOARD.
UNLESS NOTED OTHERWISE.

STRUCTURAL DRAWING NOTES (13 / 24)

You might also like