Kano Racks Methd Statement

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

WORK METHODOLOGY

FOR
INSTALLATION OF ADJUSTABLE
PALLETS STORAGE RACKS AT
KANO WAREHOUSE

PREPARATION AND APPROVAL HISTORY


PREPARED BY OGUNNIYI HABEEB 31/07/2023
REVIEWED/APPROVED BY AKEEM SOYINKA 31/07/2023
METHOD STATEMENT FOR INSTALLATION OF ADJUSTABLE PALLETS
STORAGE RACKS AT KANO WAREHOUSE

SCOPE AND PURPOSE

This "METHOD STAEMENT" covers the onsite:


INSTALLATION OF ADJUSTABLE PALLETS STORAGE RACKS AT KANO WAREHOUSE.
And the requirement of checks to be carried out.

REFERENCE DOCUMENTS

1. Project requirements
2. Approved material submittals

DOCUMENTS:

The following documents shall be provided to TOTALENERGIES as part of the


project Documentation;

1. Qualified welder list.


2. HSE policy.
3. Medical Certificates.
4. NMDPRA Certificate.
5. JRA.
6. Emergency Rescue Plan Fire.
7. Work At Height Rescue Plan.

GENERAL

INSTALLATION OF ADJUSTABLE PALLETS STORAGE RACKS generally includes all types of


Installations, etc.

EQUIPMENT

1. Welding Machine.
2. Grinding Machine.
3. Spirit Level.
4. Supply Cable.
5. Extension Cable.
6. Welding Cable.
7. First Aid Kit.
8. Mallet Hammer.
9. System Scaffold.
10.Chalk Line.

PPE

1. Safety helmets.
2. Hard hats.
3. Cover all.
4. Eye protection.
5. Safety boots.
6. Hand gloves.
7. Safety Harness.
8. Shock Absorber Lan Yards.
9. Nose mask.

RESPONSIBLE PERSONNEL

1. Project Engineer
2. Site supervisor.
3. Safety officer
4. Welders
5. Assistant Welders

SAFETY

1. Work will commence as per safety regulations laid down in the contract specification and
project safety plan.
2. All personal protective equipment shall be used as appropriate according to the nature of job.
3. Housekeeping shall be of good standard and all cut lengths shall be removed.
4. For safety reasons all equipment structures and accessories shall be protected with fire blanket
to avoid damage.
5. Safety barriers shall be used to barricade the area where the activity is to be carried out in order
to prevent any unauthorized person entering the area and to serve as warning signal to other
people.
6. All personnel involved shall put on their personal protective equipment (PPE).
7. Major installation works shall be done on-site as practicable as possible.
8. Fire extinguishers and safety officer shall be provided by KEMDIO at the site of the activity.
9. KANO WAREHOUSE will support the fire-fighting when necessary.
10. Kemdio will bring their own explosimeter to site of activities
11. KANO WAREHOUSE safety and operations personnel are to be present throughout the
duration of any hot work.
12. During installation activities, all necessary safety measures shall be adopted in order to prevent
any unsafe condition for the personnel involved. Particular care shall be taken when lifting
heavy fittings.
13. Additional safety precautions such as barriers, signs, and protective screen, warning tapes shall
be used where necessary. Areas where major risk is expected shall be isolated and tagged.
14. In addition to the above, all safety measures detailed in SAFETY POLICY shall be adhered to.
15. Risk assessment/control shall be implemented with the safety/security hazard register as in our
HSE PLAN.
16. Ensure availability of trained firewatcher round the clock during hot work activity.

ENVIRONMENTAL

1. All workers shall be educated on good environmental management practices and well-
disciplined to environment.
2. The garbage bin shall be provided at the working area and Supervisor shall ensure its must be
collected regularly and disposed-off at the approved dumpsite.
3. Safety team shall ensure that no open burning of construction or domestic wastes is practiced.
4. All workers shall ensure that all tools and equipment/machinery are in good condition to avoid
any oil leakage that can be harmful to the environment.
METHOD STATEMENT

General

The work shall include but not limited to the following:

1. Installation of adjustable pallets racks.

POSSIBLE HAZARDS ON HOT WORK

1. Electrocution.
2. Fire outbreak.
3. Flying particles.
4. Trip and fall.
5. Fall from height

SAFETY MEASURES TO PUT IN PLACE FOR HOT WORKS

1. Weld only in well-ventilated areas.


2. Use the require PPE.
3. Do not weld, cut or grind near flammable or combustible materials, liquids, vapors and dusts.
4. Have the appropriate fire extinguisher close by (DCP 9kg)
5. Uses only approved equipment in good condition and follow the manufacturer's instructions.
6. Inspect equipment for loose connections, bare wires or cables before operating.
7. Handle compressed gas cylinders safely, following proper use and storage procedures.
8. Keep aisles and stairways clear of cables and equipment.
9. Keep other people a safe distance from welding and cutting operations.
10. Learn first aid techniques for burns, poison inhalation, shock and eye injuries.
11. Know where the safety showers and eyewash stations are and how to use them.
12. Provide safety watch for high-risk activities.

SAFETY MEASURES TO PUT IN PLACE FOR WORK AT HEIGHT

1. Uses of hand rail.


2. Selection of the proper PPE.
3. Inspection of the PPE.
4. Use of scaffold for all works at height.
5. Understanding of fall distance.
6. Check and select acceptable anchor point.
7. Uses of proper equipment of work at height.
8. Knowing when and type of fall protection require for the job.
9. Explosimeter to check any gas or fumes in the atmosphere and to ensure safe working
environment.
10. Position fire extinguishers with a safety watch man on ground.

METHOD OF PRE JOB

1. Ensure that approved material required to carry out the work is available.

2. Prior to commencement of work, area and access will be inspected to confirm that the site
is ready to commence the work.
3. Physical verification of material will be carried out for any damages prior to taking from store.

4. Make sure all members of the installation crew are trained with regard to the installation
procedures and any safety procedures necessary to establish a safe working environment.
5. Review and count all rack materials and compare them with the project documents to make sure
that the proper materials have been received. Notify the client company immediately if any
shortages exist with respect to the bill of lading. Inspect the materials and make sure they are
undamaged. Stage all materials in an organized manner so they can be quickly located.
6. Verify the proper location of the racks with the client contact person, engineer should verify that
the floor is adequate. The floor should be level so that a plumb installation of the rack can be
achieved.
7. Completely inspect the area verifying building column locations and checking for any other types
of obstructions such as piping, electrical panels, ducts, lights, doorways, etc. Any such
obstructions should be flagged with tape and called to the attention of the client contact person,
and plans should be made to avoid or remove the obstruction. Building column locations should
be noted, and if there are any places where aisle widths are compromised, the installer should
notify the client contact person. If it becomes necessary to modify the configuration of the racks
in any way, prior approval must be obtained from TOTALENERGIES.
8. Determine a starting line and snap chalk lines to layout the floor. Make sure adequate aisle widths
are established. Down-aisle chalk lines should be made at the front face of the rack columns
from the start line.
9. All relevant documentation and material applicable to particular section of works will be
checked by site Project Engineer before commencement.
10. The site supervisor will give necessary instruction to workers.
11. The site supervisor will also check that tools and equipment available are in compliance
to Contract requirements.
12. The site supervisor is to conduct a toolbox meeting for all workers on the job.
13. Ensure availability of firefighting system.

INSTALLATION WORKS

1. Determine the layout of your warehouse or storage area. This includes the height, width, and
depth of the rack system, the number of levels, and the spacing between the beams.
2. Install the vertical uprights. Start by anchoring the first upright to the floor using anchor bolts.
Then, slide the second upright onto the first, ensuring the teardrop-shaped holes are aligned. Use
a rubber mallet to tap the uprights into place until they are fully seated. Repeat this process for
all the uprights.
3. Use shims to level the uprights and ensure the rack is stable in case of uneven floor.
4. Install the horizontal beams. Start by inserting the beam into the top teardrop hole of one
upright, then repeat for the other side. Keep tapping the beams into place with a rubber mallet
until they are secure.
5. Install the diagonal braces by inserting them into the teardrop holes at the bottom of the
uprights. Secure the braces to the beams using the provided bolts and nuts.
6. Tighten all the bolts and nuts using a torque wrench. This will ensure that the rack is stable and
can withstand the load.
7. Test and inspect it to ensure it is safe and secure. Load the rack with pallets and test its stability
by pushing and pulling them to simulate movements during storage and retrieval.
8. After tested and inspected the teardrop pallet rack, make any necessary adjustments to ensure it
is level and plumb. Then, bolt down the rack to the floor using anchor bolts. This will provide
additional stability and prevent the rack from shifting or tipping over.

PAINTING PROCESS AS REQUIRE

1. Painting of Primer coat with roller and brush.


2. Painting of Finishing coat with roller and brush.

COMMISSIONING & HAND OVER OF ENTIRE FACILITY

1. Demobilize equipment and materials from site.


2. General House-keeping.
3. Hand over.

EMERGENCY PROCEDURES
FIRST AID FACILITIES AND ON SITE
LOCATION
FIRST AIDER OGUNNIYI HABEEB

EVACUATION METHOD AND KANO WAREHOUSE MUSTER POINT


ASSEMBLY POINT

NAME DESIGNATION DATE


Ogunniyi Habeeb Supervisor 31/07/2023

Ololade Odejobi Safety Officer 31/07/2023

Shobola Rasheed Project Engineer 31/07/2023

Ahmed Ismaila Welder 31/07/2023

Saheed Nureni Welder 31/07/2023

Hammed Onaopepo Welder 31/07/2023

Samson Afolabi Ass/Welder 31/07/2023

Seye Shodiya Welder 31/07/2023

Charles Eke Welder 31/07/2023

Chuks Chukwudi Welder 31/07/2023

You might also like