Steel Work Instruction
Steel Work Instruction
0 INTRODUCTION
1.1 General
intends to build Tube Settler Clarifier at Wolo, Kolaka with capacity 140 m3/hr in Sulawesi
Indonesia.
1.2 Scope
The scope of this document is to present the design calculation of Tube Settler Clarifier Leg
structure .
1.3 References
The following documents are used to design the structure of Tube Settler Clarifier Leg.
1.3.1 Project Documents
Process Design Basis PP Design Code, Doc no.DBS-1-000-P-0001
1.3.2 Codes
American Society of Civil Engineers - Minimum Design Loads for Buildings
and Other Structure, ANSI/ASCE 7-02.
American Concrete Institute - Building Code Requirement for Structural
Concrete, ACI 318-2005.
Tata Cara Perencanaan Ketahanan Gempa untuk Rumah dan Gedung, SNI 03-
1726-2012
Uniform Building Code 1997, UBC ’97.
1.3.3 Reference
Tube settler clarifier General Arrangement Drawing, no.Metito drawing
no.312231600-02-002
1.4 Quality of Material
Steel: ASTM A-36
1.5 Unit Weight of Material
Reinforced concrete concrete : 23.54 kN/m3
Lean concrete lean : 22.54 kN/m3
Steel steel : 77 kN/m3
Soil soil : 0.99 gr/cm3
Sand gravel gravel : 17.7 kN/m3
Water water : 10 kN/m3
1.6 Unit Measurement
Unit measurement is Metric system
1.7 Computer Software
For calculate this document use Staadpro v8.i and Microsoft excel
UNP 125x65x6
1.8 Summary
TUBE 75x75x4.5
1.8.1 Geometry
UNP 125x65x6
TUBE 60x60
Y
X
Z TUBE 75x75x4.5Load 1
UNP 125x65x6
Figure 1.1 Geometry
TUBE 60x60
TUBE 60x60
4. R4 Horizontal
Tube 60x60x3.2 0.388 OK LC.210
brace
DIAGONAL BRACE
Y
X RATIO 0.167
HORIZONTAL
Z BRACE Load 1
RATIO 0.388
Figure 1.2 Stress Ratio Steel Structure