Communication Assignment 5
Communication Assignment 5
Email:jdenterprices@gmail.com
____________________________________________________
Received by,
Gilmer
Manager
PNP construction
Windsor,ON.
Observation:
A problem with a structural beam interfering with the HVAC system of the building The conduit for
the lighting fixtures appears to be cast into the same structural beam that is interfering with the
Mechanical operations, according to the Electrical drawings.
Instruction:
Conduit line 01 must be routed beneath the beam (B1) at a 90ᵒ angle from the bottom of the slab to
the north side of the beam in a parallel direction of the beam. For your convenience, I've included a
section drawing of the circuit below. The deadline for completing the allocated assignment is 15th
March 2022. A shop drawing must be supplied and approved by the Project Manager before work
may begin.
Signature
Perarasan Devaraj.
JD Enterprises Pvt. Ltd
1037, Bruce Avenue, Windsor, ON.
JD ENTERPRISES PVT.LTD
1037, Bruce Avenue, Windsor, ON, N9A4Y1
Email:jdenterprices@gmail.com
____________________________________________________
SKETCH