Download as pdf or txt
Download as pdf or txt
You are on page 1of 40

ANSI/IEEE Std 516-1987

(Revision of IEEE Std 516


February 1986 for trial use.)

IEEE Guide for Maintenance Methods on


Energized Power-Lines

Published by The Institute of Electrical and Electronics Engineers, Inc 345 East 47th Street, New York, N Y 10017, USA
N m b e r 25, 1988 SH1.2096
An American National Standard
IEEE Guide for
Maintenance Methods on
Energized Power-Lines

1. General This guide is not establishing a standard for


maintenance of energized power-lines in the
electric utility industry as such.
1.1 Scope. This guide provides general recom-
mendations for performing maintenance work on 1.3 Application. This guide is broad enough yet
energized power-lines. It is not intended to include specific enough to be applicable to all aspects of
all of the proven, practical methods and proce- energized-line maintenance.
dures; however, these selected comprehensive Since energized-line-maintenance practices for
recommendations are based on sound engineer- different projects are influenced by the magni-
ing principles, engineering safety considerations, tude and nature of each project, and by local con-
and decades of field experience by many utilities. ditians and circumstances, mme a!ternative
Included are technical explanations as required methods that have been successfully employed
to cover: certain laboratory testing of tools and are presented.
equipment; field maintenance and care of tools The practices described provide for the safe
and equipment; work methods for the mainte- performance of energized-line maintenance. They
nance of energized lines and for persons working are based on practices of operating utilities with
in the vicinity of energized lines. many years of successful experiences. Advance-
ment in technology or changes in system design
1.2 Purpose. The purpose of this guide is to will probably j u s t a modlfylng the minimum
(1) Present in one guide sufficient details of requirements recommended in this guide.
some of the methods and equipment pres- The approach used within this guide is as
ently in use to enable the performance of follows:
safe, energized-line maintenance. (1) To present definitions required for clarity.
(2) Direct attention to appropriate standards (2) To indicate the engineering and other
and other documents for the acquisition of technical considerations essential to the
knowledge on the care and use of required safe performance of energized-line main-
tools and equipment. tenance.
(3) Provide guidance for establishing a safe (3) To provide guidance for the necessary test
work area, taking into consideration the equipment and procedures associated with
physical effects of the work area on per- manufacturer and user's acceptance, test-
sonnel. ing, and care of equipment.
It is not intended that this guide should replace (4) To detail various work methods for work-
present proven utility practices or imply that ing on or near energized lines and asso-
these recommendations are superior to existing ciated devices.
practices and, therefore, should be universally
adopted as utility standards. This compilation of
many accepted practices is presented specifically 1.4 Other Requirements. Requirements of fed-
in the form of a guide to be used by those electric eral, state, or local regulations should be observed.
power utilities and agencies that are seeking guid- When any conflict exists between guide and the
ance in establishing methods and procedures for rules of the owner of the line, the owner's rules
maintenance of energized power-lines. should take precedence.

7
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

1.5 References. This guide shall be used in con- [ 171 ASTM F 479-88, Specification for In-Service
juction with the following publications: Care of Insulating Blankets.
[ I ] ANSI A92.2-1979, American National Stan- [ 18) ASTM F 496-85, Specification for In-Service
dard Vehicle Mounted Elevating and Rotating Care of Insulating Gloves and Sleeves.
Devices.'
[ 191 ASTM F 71 1-83,Fiberglass-Reinforced Plas-
[2] ANSI C2-1987, American National Standard tic (FRP) Rod and Tube Used in Live-Line Tools.
National Electrical Safety Code.
[ 201 ASTM F 855-83,Temporary Grounding Sys-
[3] ANSI C29.1-1982, American National Stan- tems to be Used on De-Energized Electrical Power
dard Precision Power Transmission Chains, At- Lines and Equipment.
tachments, and Sprockets.
[ 2 1] ASTM F 968-85, Electrically Insulating Plas-
[ 4 ] ANSIIIEEE Std 4-1978, IEEE S t a n d a r d tic Guard Equipment for Protection of Workers.
Techniques for High-Voltage Testing. [22] CFR, Section 29 1926.955(e)(11) Federal
[5] ANSI/IEEE Std 100-1988, IEEE Standard OSHA Code.
Dictionary of Electrical and Electronics Terms. [23] CFR, Section 29. 1926/551 and 1910. 183,
[6] ANSI/IEEE Std 524-1980, IEEE Guide to the osm.3
Installation of Overhead Transmission Line Con- (241 CSA C225-76, Vehicle-Mounted Aerial
ductors. Devices."
[7] ANSI/IEEE Std 978-1984, IEEE Guide for In- [25] Data Sheet 12304-598-1980.5
Service Maintenance and Electrical Testing of [ 261 EPRI Transmission-Line Reference Book
Live-Line Tools. (EL2500, 2nd ed).6
[SI ASTM D120-87, Standard Specification for [27] IEC 265-1968, High-Voltage Switches7
Rubber Insulating Gloves2
[28] IEEE Std 62-1978, IEEE Guide for Field
[9] ASTM D149-87, Standard Test Methods for Testing Power Apparatus Insulation?
Dielectric Breakdown Voltage a n d Dielectric
[29] IEEE Std 957-1987, Guide for Cleaning
Strength of Electrical Insulating Materials at
Insulators.
Commercial Power Frequencies.
[30] Application Guide for Insulator Contamina-
(101 ASTM D1048-88a,Standard Specification for tion. See Application Guide for Insulators in Con-
Rubber Insulating Blankets. taminated Environment. IEEE Paper F77-639-8.
[ 11] ASTM D1049-88, Standard Specification for [ 3 1] ASANOVA, T. P. and Rakov, A. I. The State of
Rubber Insulating Gloves. Health of Persons Working In Electric Field of
[ 121 ASTM D1050-85,Standard Specification for Outdoor 400 kV and 500 kV Switchyards. Hygiene
Rubber Insulating Line Hose. of Labor and Professional Diseases, no 5 1966,
USSR.
[13] ASTM D1051-87, Standard Specification for
Rubber Insulating Sleeves.
3CFR publications are available from Superintendent of
[ 141 ASTM D1078-86, Standard Test Method for Documents, US Government Printing Office, Washington, DC,
Distillation Range of Volatile Organic Liquids. 20402.
41n the United States, CSA Standards are available from the
[15] ASTM F 96-77(1982), Specification for Elec- Sales Department of American National Standards Institute,
tronic Grade Alloys of Copper and Nickel in 1430 Broadway, New York, NY 10018. In Canada they are
Wrought Forms. available a t the Canadian Standards Association (Standards
Sales), 178 Rexdale Blvd, Rexdale, Ontario, Canada M9W 1R3.
[ 161 ASTM F 478-87, Specification In-Service 5This publication is available from the National Safety
Care of Insulating Line Hose and Covers. Council, 444 North Michigan Ave, Chicago, IL 6061 1.
'This publication is available from the Research Report
Center, PO Box 50490, Palo Alto, CA 94303.
ANSI publications are available from the Sales Depart-
ment, American National Standard Institute, 1430 Broadway, IEC publications are available from the Sales Department,
New York, NY 10018. American National Standards Institute, 1430 Broadway, New
York, NY 10018.
%ASTMpublications are available from the American Society
for Testing and Materials, 1916 Race Street, Philadelphia, PA IEEE publications are available from IEEE Service Center,
19103. 445 Hoes Lane, Piscataway, N J 08854-1331.

8
ANSI/ IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

[32] BRIDGES, J. E. Biological Effects of 60 Hz barehand work. A technique of performing live-


Electric Fields. IIT Research Institute Final line maintenance on energized wires and equip-
Report E8151, EPRI Project RP-381-1, ment whereby one or more linemen work directly
Nov 1975. on an energized part after having been raised and
bonded to the energized wire or equipment. These
[33] BRIDGES, J. E. Environmental Considera-
linemen are normally supported by an insulated
tions Concerning the Biological Effects of Power-
ladder, nonconductive rope, insulated aerial
Frequency (50 Hz or 60 Hz) Electric Fields. IEEE
device, helicopter, or the energized wires or equip-
Paper F77 256-1.
ment being worked on. Most barehand work
[34] ELEK and SIMPSON. Safe Clearance and includes the use of insulating live-line tools.
Protection Against Shocks During Live-Line Work.
AIEE Paper, Feb 1962, pp 61-1019. bonded. The mechanical interconnection of con-
ductive parts to maintain a common electrical
[35] IEEE COMMITTEE REPORT 31-TP67-96.
potential. Synonym:connected.
Recommendations for Safety in Live-Line
Maintenance.
bucket. A device designed to be attached to the
[36] KOUWENHOVEN, W. B., et al. Body Current boom tip of a line truck, crane, or aerial lift and
in Live-Line Working. IEEE Paper 31-TP65-673. support workers in an elevated working position.
It is normally constructed of fiberglass to reduce
(371 KOUWENHOVEN, W. B. e t al. Medical its physical weight, maintain strength, and obtain
Evaluation of Man Working in AC Electric Fields.
good dielectric characteristics. Synonym: basket.
IEEE Paper 31-TP66-395.
[38] KOUWENHOVEN,W. B., and LANGWORTHY, bypass. See: jumper.
0. R. Effects of Electric Shock. AIEE Transactions
capacitive current. The component of the mea-
vol49, Jan 1930, p p 381-394.
sured current that leads the applied voltage by
[39] KRIVOVA, T. I., et al. Standardization of the 90" due to the geometrical capacitance of the tool
Intensity of an Electrical Field of Commercial or equipment.
Frequency by the Threshold of Stimulation with
Painful Initiation of Electrical Discharges. USSR. clearance. See: work permit.
[40] Live-Line Maintenance Methods. Task Group conduction current. The component of the mea-
for Live-Line Maintenance Methods. IEEE Paper sured current in phase with the applied voltage
T-73 157-5. that is delivered to the volume of the tool or
(41] SINGEWALD, M. R., et al. Medical Follow-up equipment, due to the physical resistance of the
Study of High-Voltage Lineman Working in AC material comprising the tool or equipment.
Electric Fields. IEEE Paper T73 154-2.
conductive clothing. Clothing made of natural or
[42] Study in the USSR of Medical Effects of synthetic material either conductive or inter-
Electric Fields on an Electric Power System. woven with conductive thread to provide from
Translated from Russian by KNICKERBOCKER, electrostatic effects of high-voltage energized
G. G. IEEE/PES Special Pub, no 10. electrical conductors and equipment.

2. Definitions conductor. A wire or combination of wires not


insulated from one another, suitable for carrying
aerial device. A vehicular mounted articulating an electrical current. However, it may be bare or
device or telescoping boom-type personal lift insulated. Synonyms: cable, Wire.
device, or both, equipped with an insulating boom
and one or more buckets or a platform used to conductor cover. Electrical protection equip-
position a worker. ment designed specifically to cover conductors.
Synonyms: Cover-up,eel, hard cauer,hose, snake,
aerial work. Work performed on equipment blanket. See: cover-up equipment.
used for the transmission and distribution of elec-
tricity, which is performed in an elevated position conductor grip. A device designed to permit the
on various structures, conductors, or associated pulling of a conductor without splicing on fittings,
equipment. eyes, etc. I t permits the pulling of a continuous

9
I
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

conductor where threading is not possible. The and ground, or the clear space between any
designs of these grips vary considerably. Grips objects.
such as the Klein (Chicago) and Crescent utilize
an open-sided, rigid body with opposing jaws and dynamometer. A device designed to measure
swing latch. In addition to pulling conductors this loads or tension on conductors. Various models of
type is commonly used to tension guys and in these devices are used to tension guys or sag con-
some cases, pull wire rope. The design of the ductors. Synonyms: clock, load cell.
come-along (pocket-book, suitcase, four bolt, etc)
incorporates a bail attached to the body of a energized. Electrically connected to a source of
clamp that folds to completely surround and potential difference, or electrically charged so as
envelop the conductor. Bolts are then used to to have a potential different from that of the
close the clamp and obtain a grip. Synonyms: buf- ground. Synonyms: alive, current carrying, hot,
falo, Ch,kwgrip, come-abng, Crescentfour bolt, live.
grip, Klein, pocketbook, seven bolt, six bolt, slip-
grip, suitcase, Kellem grip.
equipotential. An identical state of electrical
potential for two or more items.
cover-up equipment. Equipment designed to pro-
extra-highvoltage (ehv). A term applied to volt-
tect persons from energized parts in a specific
work area. Many different types are available to age levels that are higher that 240 000 V.
cover conductors, insulators, dead-end assem-
gin. An assembly, which when attached to a sup-
blies, structures, and apparatus. Cover-up mate-
port or assembled on a structure, provides a rig-
rial may be either flexible or rigid.
ging point for rope blocks, blocks, etc, so as to
current-carrying part. A conducting part manipulate various pieces of apparatus. The gin,
intended to be connected in an electric circuit to unlike the davit, is not as rigid as the boom swiv-
a source of voltage. Noncurrent-carrying parts are els, affording greater maneuverability.
those not intended to be so connected.
gloving. A method of performing live-line main-
davit. An assembly attached to a support or tenance on energized electrical conductors and
assembled on a structure to provide a rigging equipment whereby a worker or workers, wearing
point for rope blocks, chains, or hoists so as to specially-made and tested insulating gloves, with
manipulate various pieces of apparatus. The davit or without sleeves, and using cover-up equipment
is a rigid assembly and does not swivel. while supported by the structure or insulated
aerial-liftequipment, work(s) directly on the ener-
dead. A circuit that has been de-energized so gized electrical conductor or equipment.
t h a t t h e circuit has been disconnected from all
intended electrical sources. However, it could be grounded. Connected to earth or to some
electrically charged through induction from ener- extended conducting body that serves instead of
gized circuits in proximity to it, particularly when the earth, whether the connection is intentional
the circuits are parallel. See: de-energized. or accidental.

dead-end. The point at which mechanical force high voltage (hv). A term applied to voltage lev-
(primarily) and longitudinal strain is applied to a els that are higher than 1000 V.
reliable support. Synonyms: termination, anchor
point, strain attachment. hoist. An apparatus for moving a load by the
application of pulling force and not including a
de-energized. Free from any electric connection car or platform running in guides. These devices
to a source of potential difference and from elect- are normally designed using roller or link chain
ric charge; not having a potential different from and built-in leverage to enable heavy loads to be
that of the ground. The term is used only with lifted or pulled. They are often used to dead-end a
reference to current-carrying parts that are some- conductor during sagging and clipping-in opera-
times alive (energized). tions and when tensioning guys. Synonyms: chain
hoist, chain tugger, m#in hoist.
distance clearance. The minimum separation
between two conductors, between conductors and hold out. Operating order, or operating-order
supports or other objects, or between conductors identification tag, or marker. Synonym: hold card.
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

hot. See: energized. master ground. A portable device designed to


short circuit and connect (bond) a de-energized
insulated tool or device. A tool or device that circuit or piece of equipment, or both, to an elec-
has conductive parts and is either coated or trical ground. Normally located remote from, and
covered with a dielectric material. on both sides of, the immediate work site. Primar-
ily used to provide safety for personnel during
insulating clothing. Clothing made of natural or construction, reconstruction or maintenance oper-
synthetic material that is designed primarily to ations. Synonyms: ground set, ground stick
provide insulation from an energized part or (ANSI/IEEE Std 100-1988 [ 5 ] ' ) .
conductor.
minimum approach distance. The shortest per-
missible distance between energized electrical
insulating tool or device.
apparatus and any part of a worker's body and
(1) A tool or device designed primarily to pro-
tools or material being handled.
vide insulation from an energized part or
conductor. It can be composed entirely of
minimum tool distance. The minimum distance
insulating materials. Examples: conductor
that must be maintained between tools and ener-
c w , stick, insulating tup.
gized lines or devices.
(2) A tool or device that has conductive parts
separated by a dielectric.
minimum tool-insulation distance. The shortest
permissible distance between energized electrical
insulator cover. Electrical protection equipment apparatus and any part of a worker's body or
designed specifically to cover insulators. Exam- conducting object while performing live line-work
ples: dead-end cover, pole-top cover, ridge-pin with an insulating tool in the air gap.
cover. Synonyms: hood, pocketbook. See: cover-up
equipment. NESC. National Electrical Safety Code, ANSI
C2-1987 [Z].
isolated.
(1) Physicallyseparated, electrically and mech- protective gap. A gap placed between live parts
anically, from all sources of electrical and ground to limit the maximum overvoltage
energy. Such separation may not eliminate that may occur.
the effects of electrical induction.
(2) Not readily accessible to persons unless rigging. An assembly of material used to manipu-
special means for access are used. late or support various tools and equipment in
both energized and de-energized line-work.
jumper. A conductive tool used to maintain elec-
trical continuity across equipment, or a conduc- rope block. A device designed with one or more
tor that shall be opened mechanically to enable sheaves, a wood or steel shell, and an attachment
various operations of live-line work to be per- hook or shackle, commonly used in pairs with a
formed. Synonym: bypass. rope reeved through the sheaves. The primary
purpose of this device is to provide mechanical
leakage current. A component of the measured advantage so as to lift or move equipment. Syn-
current that flows along the surface of the tool or onym: block and tackle.
equipment, due to the properties of the tool or
equipment surface, including any surface deposits. snatch block. A device normally designed with a
single sheave, a wood or metal shell, and a hook.
lineman. A person qualified to perform various One side of the shell usually opens to eliminate
line-work operations including aerial and ground the need for threading of the line. It is commonly
work. used for lifting loads on a single line, or as a device
to control the position or direction, or both, of a
line-work. Various operations performed by a per- fall line o r pulling line. Synonyms: skookum,
son on electrical facilities, including ground work, Washington, Western.
aerial work, and associated maintenance.
'The numbers in brackets correspond to those of the refer-
live. See: energized. ences in 1.5.
ANWIEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

stick. A type of insulating tool used in various laboratory electrical testing for design, certifica-
operations of live-line work. Synonyms:w k stick, tion, and acceptance testing. Other applicable test
pole,w k pole, hot stick, live-line tool. methods may also be utilized but comparison of
data between different test procedures is not
strain stick. An insulating support tool that is practical because of the variations in test condi-
used primarily to relieve mechanical loading at tions. A major part of this section is devoted to
suspension and dead-end configurations so as to dielectric-current measurements (phase sum of
replace damaged insulators or hardware. capacitive and resistive current) for certification
and acceptance. Some aspects of watt-loss testing
stray current. Currents or components that do are also included.
not constitute information desired for measure-
ment. Examples: currents due to the stray capac- 3.2 Basic Concepts. A major part of this section
itance of a n object to the ground plane, walls, etc. is devoted to tool and equipment current mea-
surements for certification and acceptance pur-
structure. Material assembled to support con- poses.
ductors or associated apparatus, or both, used for 3.2.1 Insulating Properties. Personal safety
transmission and distribution of electricity. Exam- and operational security in energized line-work
ples: service ple, tower. depend on the insulating properties of insulating
materials and air.
suspension of reclosing. To make inoperative
3.2.1.1 Insulating Materials. Insulating
automatic reclosing equipment. Synonyms: hold
materials are generally defined as a function of
out, live-line permit, hold order,hold 08.
their electrical insulating and dielectric strength.
(1) Electrical insulation is the property of
tool or equipment current. The total current de-
material to prevent the flow of current
livered to the tool or equipment.
through it.
ultra-highvoltage (uhv). A term applied to vol- (2) Dielectric strength is the maximum poten-
tage levels that are higher than 800 000 V. tial gradient that the material can with-
stand without rupture.
universal stick. A stick, or type of insulating tool, (3) Factors affecting insulating materials
to t h e e n d of which universal tools can be include temperature, altitude, moisture,
attached. contamination, impurities, and aging.
3.2.1.2 Air As Insulation. The insulating
universal tool. An accessory designed to attach characteristics of air are defined as its capability
to a universal stick allowing one insulated stick to to withstand a n electric field. The dielectric
be used to perform many different operations. strength of air is represented by gradients of
potential. The disruptive gradient is influenced by
work permit. The authorization to perform work the air density, humidity, temperature, pressure,
on a circuit. Synonyms:clearance, guarantee. dimensions and separation of the electrodes or
separation of the'metal terminals, shape of the
electrodes, and the characteristics of the applied
3. Technical Considerations and Testing voltage.
3.2.1.3 Contamination -Equipment. The
3.1 Introduction. The performance of energized- insulating portions of aerial-lift equipment, insu-
line-maintenance work requires the use of equip- lating tools, and cover-up equipment should be
ment and tools that in many cases are specific to kept free from contamination.
the work operation. Development of equipment Barehand work and work with insulating tools
and tools is based on requirements generated can be performed on dry contaminated insula-
from field needs and experiences related to tech- tors. Work on wet contaminated devices should
nical considerations and safe work methods. be avoided, but can be performed with insulating
References or specific guidance concerning the tools using special precautions.
specialized tools a n d equipment needed for 3.2.2 Clearance Formulas
energized-line maintenance are provided. These 3.2.2.1 General
tools and devices are produced in accordance (1) The formulas are derived empirically. In
with certain standards, requirements, or perfor- Fig 1 a saturation factor is derived from
mance factors, including the essential elements of rod-gap switching-surge flashover data.

12
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

Fig 1
60 Hz Switching-Surge Saturation Factor

The switching-surge factor S as given in These data substantiate the clearance for-
Fig 2 should be correlated with character- mula for air gaps and insulating tools, and
istics of each individual power system. as the derivation of clearances from modi-
Switching surges are important in deter- fied rod-gap data.
mining alternating-current clearances. The Distances determined by means of the
maximum switching surge represents the formulas should not be applied without
maximum rise in voltage during a distur- reference to the other relevant factors con-
bance on an operating line or system. Max- tained in this section.
imum switching surge values should be The distance determined by the formulas
used when calculating distances. should be applied only at elevations below
The configuration of electrodes influences 3000 ft (914 m). Higher elevations require
flashover as a function of the polarity of applicable correction factors as indicated
the switching surge. in Table 1.
In usual applications for solid insulating The minimum tool-insulation distance and
tools, the dry, negative-polarity, switching- the mimimum approach distances given in
surge flashover voltage is substantially Tables 2, 3, 4, and 5 are calculated dis-
above power frequency and positive-polarity tances. In practice, however, distances are
values. I t has been shown that the flash- rounded off up to the next highest 6 in
over curve for the conductor-tower config- (15 cm). When system voltages are higher
uration lies approximately midway between than nominal, actual voltage values should
the rod-rod and rod-plane gaps as in Fig 2. always be used.

13
ANWIEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

1600

1400

1200

I- 1000
v)

a
V
v)

-1
0
$ 800
-
-I
Y

600

400

200

1 1 1 1 1 1 1 I I I I J
4 E 12 16 20
ID) D I S T A N C E ( F E E T I

' T H I S C U R V E C A N N O T BE L I N E A R A T H I G H V O L T A G E S D U E TO T H E
SIZE A N D SHAPE OF T H E R O D - G A P E L E C T R O D E S

Fig 2
Typical -Withstand Voltage
for Switching Surges

(7) In determining dc clearance, values equiv- 3.2.2.2 Minimum Tool-InsulationDistance.


alent to ac peak voltages related to dc sys- In practice, it is generally accepted that insulating
tem voltage-to-ground should be used. material (clean and dry) has a dielectric-strength
(8) The minimum tool-insulation distance as characteristic equal to or greater than that of air,
given in the tables should be maintained based on rod-gap withstand values.
between an energized part and a person at The following formula is recommended for deriv-
ground potential performing a work opera- ing a minimum, safe insulation distance for clean
tion on energized lines or devices. In bare- and dry, solid or fiUed insulating tools intended
hand work, the minimum tool-insulation for energized-line maintenance on ac transmis-
distances should be maintained between a sion systems (351.
person energized at phase potential and
D = (ClC2 + a) S kVLG (Eq 1)
ground.

14
ANSI/IEEE
METHODS ON ENERGIZED POWR-LINES Std 516-1987

where Table 1
Altitude Correction Factor
D = insulation distance, ft
c, =
0.01, or one percent of line-to-ground Altitude Correction
c, = 1.1,composed of 1.06 for energized-line (m) (ft) Factor
tool-to-air withstand distance ratio plus 900 3000 1.oo
intangibles [35] 1200 4000 1.02
a = saturation factor for crest ( r 2 S kV,) 1500 5000 1.05
1800 6000 1.08
voltages of 630 kV and above (see Fig 1) 2100 7000 1.11
S = maximum anticipated per-unit switch- 2400 8000 1.14
ing surge 2700 9000 1.17
3000 10 000 1.20
kVLG = rms system phase-to-ground kilovolts- 3600 12 000 1.25
actual 4200 14 OOO 1.30
4800 16 OOO 1.35
5400 18 000 1.39
The general formula for insulating tools at all 6000 20 000 1.44
voltages becomes D = (0.011 + a) S kVLGlo
NOTE: Multiply the distance D given in Tables 2,3,4, and 5 by
louse crest voltage 345 fi
. -. overvoltage. the indicated correction factor.
fi

Table 2
Minimum Tool-Insulation Distance AC Energized Line-Work On Insulation
(a) Distance Measured (cm)
kV (rms)
LL 115 121 138 145 161 169 230 242 345 362 500 552 700 800
LG 67 70 80 85 95 100 133 140 200 210 290 320 405 462

S D D D D D D D D a D a D a D a D a D a D
1.5 0 146 0.3 165 1.6 233 2.5 285
1.6 0.2 158 0.6 181 2.0 257 3.0 315
1.7 0.4 171 1.0 199 2.4 282 3.5 347
1.8 0.7 186 1.3 216 2.9 309 4.0 380
1.9 1.0 201 1.6 233 3.3 335 4.5 415
2.0 45 47 54 56 64 67 89 94 0 134 0 141 1.3 218 2.0 254 3.8 365 5.0 450
2.1 47 49 56 59 67 70 94 98 0 141 0 148 1.6 234 2.3 272 4.2 394 5.6 491
2.2 51 52 59 62 70 74 98 103 0 148 0.1 156 1.9 251 2.6 292
2.3 52 54 62 65 73 77 102 108 0.1 156 0.3 166 2.2 268 2.9 312
2.4 54 56 64 68 77 80 107 113 0.3 165 0.6 178 2.5 287 3.3 335
2.5 56 59 67 70 80 84 112 117 0.5 175 0.8 189 2.8 305 3.6 356
2.6 59 61 70 73 83 87 116 123 0.7 185 1.0 200
2.7 61 63 73 76 86 91 120 127 0.9 196 1.2 211
2.8 63 66 75 79 89 94 125 131 1.1 207 1.4 222
2.9 65 68 78 82 92 97 129 136 1.3 217 1.6 234
3.0 67 70 80 84 96 101 134 141 1.5 228 1.8 246

LL Phase to phase
LG Phase to ground
S Maximum anticipated per-unit switching surge
D Distance measured (cm)
a Given in thousandths (saturation factor)
NOTES (1) Distances listed are for standard atmospheric conditions.
(2) Distances are based on altitudes below 1000 m.
(3) Distances do not include any factor for inadvertant movement.

15
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

Table 2
Minimum Tool-Insulation Distance AC Energized Line-Work On Insulation
(b) Distance Measured (ft)
kV (rms)
LL 115 121 138 145 161 169 230 242 345 362 500 552 700 800
LG 67 70 80 85 95 100 133 140 200 210 290 320 405 462

S D D D D D D D D a D a D a D a D a D a D
~ ~~~~~ ~ ~ ~~ ~~~ ~~

1.5 0 4.79 0.3 5.42 1.6 7.65 2.5 9.35


1.6 0.2 5.20 0.6 5.94 2.0 8.42 3.0 10.34
1.7 0.4 5.62 1.0 6.53 2.4 9.22 3.5 11.39
1.8 0.7 6.11 1.3 7.08 2.9 10.11 4.0 12.47
1.9 1.0 6.61 1.6 7.66 3.3 11.00 4.5 13.61
2.0 1.47 1.54 1.76 1.85 2.09 2.20 2.93 3.08 0 4.40 0 4.62 1.3 7.14 2.0 8.32 3.8 11.99 5.0 14.78
2.1 1.55 1.62 1.85 1.94 2.19 2.31 3.07 3.23 0 4.62 0 4.85 1.6 7.67 2.3 8.94 4.2 12.93 5.6 16.11
2.2 1.62 1.69 1.94 2.03 2.30 2.42 3.22 3.39 0 4.84 0.1 5.12 1.9 8.23 2.6 9.57
2.3 1.70 1.77 2.02 2.13 2.40 2.53 3.36 3.54 0.1 5.11 0.3 5.46 2.2 8.80 2.9 10.23
2.4 1.77 1.85 2.11 2.22 2.51 2.64 3.51 3.70 0.3 5.42 0.6 5.85 2.5 9.40 3.3 10.98
2.5 1.84 1.93 2.20 2.31 2.61 2.75 3.66 3.85 0.5 5.75 0.8 6.20 2.8 10.01 3.6 11.68
2.6 1.92 2.00 2.29 2.40 2.72 2.86 3.80 4.00 0.7 6.08 1.0 6.55
2.7 1.99 2.08 2.38 2.49 2.82 2.97 3.95 4.16 0.9 6.43 1.2 6.92
2.8 2.06 2.16 2.46 2.59 2.93 3.08 4.10 4.31 1.1 6.78 1.4 7.29
2.9 2.14 2.23 2.55 2.68 3.03 3.19 4.24 4.47 1.3 7.13 1.6 7.67
3.0 2.21 2.31 2.64 2.77 3.14 3.30 4.39 4.62 1.5 7.50 1.8 8.06

LL Phase to phase
LG Phase to ground
S Maximum anticipated per-unit switching surge
D Distance measured (ft)
a Given in thousandths (saturation factor)
NOTES: (1) Distances listed are for standard atmospheric conditions.
(2) Distances are based on altitudes below 1000 m.
(3) Distances do not include any factor for inadvertant movement.

Table 3
Minimum Tool-Insulation Distance DC Energized Line-Work
DC Pole-to-GroundVoltage
LG 250 kV 400 kV 500 kV 600 kV 750 kV
S D D a D D a D D a D D a D D
(ft) (cm) (ft) (cm) (ft) (cm) (ft) (em) (ft) (cm)
1.2 2.33 71 0 3.73 114 0 4.67 142 0.6 5.91 180 1.9 8.21 250
1.3 2.53 77 0 4.05 123 0 5.06 154 1.o 6.62 202 2.5 9.30 283
1.4 2.48 83 0 4.36 133 0.5 5.20 173 1.5 6.83 236 3.0 9.65 317
1.5 2.91 89 0 4.66 142 0.8 6.26 192 1.9 8.22 251 3.6 11.60 354
1.6 3.1 1 95 0 4.98 152 1.2 6.90 210 2.3 9.02 275 4.2 12.90 393
1.7 3.31 101 0.3 5.43 166 1.5 7.52 229 2.8 9.95 303 4.8 14.20 433
1.8 3.51 107 0.6 5.90 180 1.9 8.22 251 3.3 10.90 332 5.4 15.60 475
1.9 3.70 113 0.9 6.40 195 2.3 8.93 272 3.7 11.80 360 6.0 17.10 521
2.0 3.89 119 1.2 6.91 211 2.6 9.61 293 4.2 12.90 393 6.6 18.71 537
2.1 4.08 124 1.5 7.42 226 3.0 10.40 317 4.7 14.00 427
2.2 4.28 130 1.8 7.96 243 3.4 11.20 34 1 5.2 15.10 460

LG DC pole-to-ground voltage
S Maximum anticipated per-unit switching surge (transient overvoltage)
D Distance measured (ft and cm)
a Given in thousandths (saturation factor)
NOTES: (1) Consideration should be given to increasing some of the minimum insulation distances above, so as to reduce the
stress due to the steady-state voltage a maximum steady-state stress of 60 kV/ft is suggested as an allowance for average worlung
conditions.
(2) If the minimum insulation distances are used, the maximum relative humidity should be restricted to 85%.
(3) Distances listed are for standard atmospheric conditions.
(4) Distances are based on altitudes below 1000 m.
(5) Distances do not include any factor for inadvertant movement.

16
ANSVIEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

Table 4
Minimum Approach Distance AC Energized Line-Work Air Insulation
(a) Distance Measured (em)
kV (rms)
LL 115 121 138 145 161 169 230 242 345 362 500 552 700 800
LG 67 70 80 85 95 100 133 140 200 210 290 320 405 462
S D D D D D D D D a D a D a D a D a D a D
1.5 0 134 0.3 151 1.6 215 2.5 264
1.6 0.2 144 0.6 166 2.0 237 3.0 293
1.7 0.4 156 1.0 182 2.4 260 3.5 323
1.8 0.7 170 1.3 198 2.6 286 4.0 355
1.9 1.0 185 1.6 215 3.3 312 4.5 388
2.0 41 43 49 52 58 61 81 85 0 122 0 128 1.3 200 2.0 234 3.8 341 5.0 422
2.1 43 45 51 55 61 64 85 90 0 128 0 134 1.6 215 2.3 252 4.2 368 5.6 461
2.2 45 47 54 57 64 67 89 94 0 134 0.1 142 1.9 231 2.6 270
2.3 47 49 56 60 67 70 93 98 0.1 142 0.3 151 2.2 248 2.9 290
2.4 49 51 59 62 69 73 98 102 0.3 151 0.6 163 2.5 265 3.3 311
2.5 51 53 61 65 73 76 101 107 0.5 161 0.8 173 2.8 285 3.6 332
2.6 53 56 63 67 75 79 105 111 0.7 170 1.0 183
2.7 55 58 66 70 78 82 110 115 0.9 180 1.2 194
2.8 57 60 68 73 81 85 113 119 1.1 190 1.4 204
2.9 59 62 71 75 84 88 118 124 1.3 200 1.6 215
3.0 61 64 73 78 87 91 122 128 1.5 211 1.8 226

LL Phase to phase
LG Phase to ground
S Maximum anticipated per-unit switching surge
D Distance measured (cm)
a Given in thousandths (saturation factor)
NOTES: (1) Distances listed are for standard atmospheric conditions.
(2) Distances are based on altitudes below 1000 m.
(3) Distances do not include any factor for inadvertant movement.

Table 4
Minimum Approach Distance AC Energized Line-Work Air Insulation
(a) Distance Measured (R)
kV (rms)
LL 115 121 138 145 161 169 230 242 345 362 500 552 700 800
LG 67 70 80 85 95 100 133 140 200 210 290 320 405 462
~~

S D D D D D D D D a D a D a D a D a D a D
1.5 0 4.33 0.3 4.97 1.6 7.05 2.5 8.66
0.0 0.2 4.73 0.6 5.46 2.0 7.78 3.0 9.60
1.7 0.4 5.13 1.o 5.98 2.4 8.54 3.5 10.60
1.8 0.7 5.59 1.3 6.51 2.9 9.40 4.0 11.64
1.9 1.0 6.06 1.6 7.08 3.3 10.23 4.5 12.73
2.0 1.34 1.40 1.60 1.70 1.90 2.00 2.66 2.80 0 4.00 0 4.20 1.3 6.55 2.0 7.68 3.8 11.19 5.0 13.86
2.1 1.41 1.47 1.67 1.79 2.00 2.10 2.79 2.94 0 4.20 0 4.41 1.6 7.06 2.3 8.27 4.2 12.08 5.6 15.14
2.2 1.47 1.54 1.76 1.87 2.09 2.20 2.92 3.08 0 4.40 0.2 4.70 1.9 7.59 2.6 8.87
2.3 1.54 1.61 1.82 1.96 2.19 2.30 3.05 3.22 0 4.60 0.4 5.01 2.2 8.10 2.9 9.49
2.4 1.61 1.68 1.92 2.04 2.28 2.40 3.20 3.35 0 4.94 0.6 5.34 2.5 8.66 3.3 10.21
2.5 1.67 1.75 2.00 2.13 2.38 2.50 3.32 3.50 0 5.24 0.8 5.67 2.8 9.23 3.6 10.92
2.6 1.74 1.82 2.08 2.21 2.47 2.60 3.45 3.64 0 5.55 1.0 6.01
2.7 1.81 1.89 2.16 2.30 2.57 2.70 3.60 3.76 0 5.88 1.2 6.36
2.8 1.88 1.96 2.24 2.38 2.66 2.80 3.72 3.92 1.1 6.22 1.4 6.73
2.9 1.94 2.03 2.32 2.47 2.76 2.90 3.86 4.05 1.3 6.55 1.6 7.10
3.0 2.01 2.10 2.40 2.55 2.85 3.00 3.98 4.20 1.5 6.90 1.8 7.48

LL Phase to phase
LG Phase to ground
S Maximum anticipated per-unit switching surge
D Distance measured (ft)
a Given in thousandths (saturation factor)
NOTES ( 1 ) Distances listed are for standard atmospheric conditions
(2) Distances are based on altitudes below 1000 m.
(3) Distances d o not include any factor for inadvertant movement.

17
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

Table 5
Minimum Approach Distance DC Energized Line-Work Air Insulation
DC Pole-to-GroundVoltage
LG 250 kV 400 kV 500 kV 600 kV 750 kV

1.2 2.12 85 0 3.33 103 0 4.24 129 0.6 5.40 165 1.9 7.57 23 1
1.3 2.30 70 0 3.68 112 0.1 4.60 142 1.0 6.07 185 2.5 8.62 263
1.4 2.48 76 0 3.96 121 0.5 5.20 158 1.5 6.83 208 3.0 9.65 294
1.5 2.66 81 0 4.24 129 0.8 5.73 175 1.9 7.57 231 3.6 10.82 330
1.6 2.83 86 0 4.53 138 1.2 6.34 193 2.3 8.38 255 4.2 12.05 367
1.7 3.01 92 0.3 4.95 151 1.5 6.91 211 2.8 9.23 281 4.8 13.34 407
1.8 9.19 97 0.6 5.40 165 1.9 7.57 231 3.3 10.11 308 5.4 14.70 448
1.9 3.36 102 0.9 5.87 179 2.3 8.26 252 3.7 11.04 336 6.0 16.12 491
2.0 9.54 108 1.2 6.34 193 2.6 8.91 272 4.2 12.05 367 6.6 17.61 537
2.1 3.72 113 1.5 6.83 208 3.0 9.65 294 4.7 13.10 399
2.2 9.89 119 1.8 7.34 224 3.4 10.42 318 5.2 14.19 433

LG DC pole-to-ground voltage
A Maximum anticipated per-unit switching surge (transient overvoltage)
D Distance measured in feet and centimeters
a Given in thousandths (saturation factor)
NOTES: (1) Consideration should be given to increasing some of the minimum insulation distances so as to reduce the stress due
to the steady-state voltage. A maximum steady-state stress of 60 kV/ft is suggested as an allowance for average working conditions.
(2) If the minimum insulation distances are used, the maximum relative humidity should be restricted to 85%.
(3) Distances listed are for standard atmospheric conditions.
(4) Distances are based on altitudes below 1000 m.
(5) Distances do not include any factor for inadvertant movement.

3.2.2.3 Minimum Approach Distance. To forms- transient and steady state. The first type
obtain the minimum approach distance to ener- occurs before contact is made ( a person touching
gized lines or devices (air insulation using 3.2.2.2), an object that is at a potential different from
the aforementioned formula has been modified by hidher experience), the second, after contact has
reducing C2 by 10% from 1.1 to 1.0. Thus ClC2 been established. The sensation-of-shock problem
becomes 0.01. The general formula for the min- can be solved by bonding or shielding the person
imum approach distance for all voltages becomes: from the electric field, or both.
3.2.3.2 Shielding. When working on or near
energized lines or devices where the strength of
where the electric field is noticeable, workers generally
use shielding.
D insulation distance, f t
The field intensity inside a conductive shield is
CI 0.01, or one percent of line-to-ground
a function of the degree of shielding. The proxim-
c
2 1.0
ity to the line and the intensity of the field will
a saturation factor for system voltages of
determine the shielding required. When working
630 kVIO and above (see Fig 1)

S
(crest voltage a kVLG)
maximum anticipated per-unit switch-
on lines energized above 150 kV phase-to-phase
by the barehand method, for example, the worker
should have full shielding, such as conductive
ing surge
clothing, whereas when working near a lower-
rms system phase-to-ground kilovolts -
voltage line full shielding may not be necessary.
actual
The discomfort or electric sensation experienced
The general formula for the minimum approach inside the field of the line can serve as a useful
distance for all voltages becomes guide as to when shielding is required and to what
degree.
D = (0.01 + a ) S kVLG
Electrostatically induced current will normally
be much lower in the vicinity of dc lines than near
3.2.3 Electric Fields ac lines, although under certain weather condi-
3.2.3.1 General. One of the most common tions charges on workers and equipment can be
manifestations of an electric field on persons is accumulated as a result of ions carried by the air
the electric shock. This shock may have two from corona-generating points on the conductors

18
ANSVIEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

or tools. The charge that may be acccumulated is then the suit should also be bonded. These
extremely variable as it is dependent on humidity, bond cables should be installed in such a
duration of exposure, wind direction, and the way as to minimize probability of carrying
amount of corona. The use of conducting shoes, fault current or line current.
suits, shielding, and bonding as used for ac lines When any electrical circuit component is
with equivalent peak voltage to ground is just as to be opened or replaced, then a temporary
effective for dc. conducting jumper should be installed to
3.2.3.2.1 Forms of Shielding shunt the component being worked on.
Conductive Clothing. Conductive clothing, This jumper should be capable of carrying
comprising footwear, socks, gloves, and a the line current.
suit with a hood is a very effective means of To approach an energized high-voltage
shielding the worker from an electric field line, workers should wear a conductive
and has become widely accepted, particu- suit. Bonding to the energized conductor
larly in barehand work. may be done with an insulating tool. To
Conductive Screens and Liners. Conduc- eliminate electric shock in the area affected
tive screens can also be used for protection by the electric field conductive objects may
from an electric field. Properly employed, require bonding.
they are as effective as conductive clothing. 3.2.3.3 Current
Conductive liners are commonly used 3.2.3.3.1 Insulating Tools. The range of
inside aerial buckets. At extra-high voltage normal dielectric current on insulating tools has
(ehv) in additon to shielding personnel, been found to vary from <6 pA to 15 pA/100 kV.
liners sometimes provide the necessary Current exceeding these values may indicate
shielding to the upper portion of the aerial deterioration of insulating qualities.
lift boom in the proximity of the bucket. 3.2.3.3.2 Body Current. Human reaction
3.2.3.2.2 Grounding and Bonding to the electric current caused by an electric field
Grounding. Grounding may be defined as has been determined [38]. The steady-state ac
providing an electrical connection between range of the threshold-of-perception level is
equipment and earth (ground) or to some 0.6 mA to 1.1 mA while the let-go level may be
conductive medium that is a t earth considered as being below the 5 mA steady-state
(ground) potential. In line maintenance, current value. For dc, the threshold of perception
portable grounding equipment is used for level is 3.5 mA and the safe-let-go is 41 mA. See
this purpose. [26] (high voltage dc, to f 6 0 0 kV).
Grounding cables, ferrules, and clamps 3.2.3.4 Direct-Current Considerations
are tested for fault-current capability by While withstand values of dry surface insu-
manufacturers in accordance with ASTM lation and of air gaps are essentially the
F-855-83 [ 201. same for dc stresses as for ac stresses hav-
Grounds should be capable of carrying ing the same peak voltage to ground, small
full fault current long enough for protec- amounts of moisture and dirt on surface
tive devices to operate. Personnel should insulation have a much greater degrading
never be in series with a ground lead. effect for dc stresses than for ac, and con-
Bonding. Bonding is used to bring all per- sequently the insulation distance for tools
sonnel and objects in the work area to the and ladders used on a dc system is nor-
same potential. They are not intended to mally determined on the basis of steady-
carry fault current or line current. state insulating requirements rather than
Bond cables are used extensively during its impulse characteristics.
barehand, energized line-work to conduct Most of the high-voltage dc-system charac-
charging current and thus eliminate the teristics, such as two conductors versus
transient contact sensation between the three and the inherently lower overvoltage
worker and the object on which the person and fault current, make maintenance work
is working. The worker in the bucket is easier on a high-voltage dc line as opposed
bonded to the conductor by a bond cable, to an equivalent high-voltage ac line. The
which is connected to the bucket bonding major off-setting disadvantage of high-
system or shielding system. The use of con- voltage dc maintenance is the lower with-
ductive footwear is recommended. When stand value of surface insulation when wet
the worker is wearing a conductive suit, or dirty.
ANSIDEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

(3) It should be recognized that any moisture this current consists of three components
or dirt on surface insulation has a much (1) Capacitative current due to the insulating
greater degrading effect when exposed to material comprising the tool or equip-
dc steady-state stresses as compared to ac ment
stresses. The use of rope in direct contact (2) Conduction current through the volume of
with dc energized lines or devices should be the tool or equipment
avoided. Synthetic chains or fiberglass sticks (3) Leakage current along the surface of the
should be used in series with the rope tool or equipment
unless the insulation length of the rope is The conduction current is normally negligible.
significantly greater than the minimum. For clean, dry tools and equipment] the leakage
3.2.4 Electrical Properties of Tools and current is small and the capacitative current pre-
Equipment dominates. Surface deposits may increase the
3.2.4.1 Categories of Insulating Materials. leakage current significantly.
The basic tools and equipment used for work- 3.2.4.5 Current of Support, Lift or Reach-
ing on or near energized electric lines or power extending Tools and Equipment. For ac excita-
apparatus can be divided into the following cate- tion] this current consists of the capacitive cur-
gories: rent and the leakage current. For clean, dry tools
Personnel protective or cover-up tools and and equipment] the leakage current is small and
equipment, where the electric stress is app- t h e capacitive current predominates. Surface
lied essentially m o s s the thickness of the deposits may increase t h e leakage c u r r e n t
tool or equipment. Examples: gloves,sleeves, significantly.
overshoes, mats, line hoses. Such tools and For dc excitation, the capacitive current does
equipment are often made of natural rubber not exist.
and rubber-like materials. Such tools and 3.2.5 Protective Equipment
equipment may be flexible or rigid. 3.2.5.1 Barriers. Barriers or guards are fre-
Support, lift or reach-extending tools and quently provided by any method of energized line-
equipment where the electrical stress is work at voltages up to 69 kV so as to prevent the
applied essentially along the length of the worker from approaching too close to equipment
tool or equipment. Examples: suspended that is at a potential different from one’s self.
or supported aerial devices, ladders, plat- When working from insulated supports, either
forms, ropes, chains, poles. Such tools and phase-to-phaseor phase-to-ground voltages should
equipment are typically made of solid or be considered as they apply.
hollow insulating materials in whole pieces Insulation (dielectric) capable of withstanding
or small sections. the voltage is not classed as a guard or barrier but
3.2.4.2 Dielectric Strength of Personnel as cover-up equipment.
Protective or Cover Tools and Equipment. The 3.2.5.2 Protective Gaps. In cases where the
dielectric strength of the tool or equipment distance of the insulating material or air is affected
installed in service may depend on the material by a certain method of performing energized line-
thickness and on the air gaps between the worker work, a protective gap can be employed to pro-
and the tool or equipment plus the tool or equip- vide protection by decreasing the switching-surge
ment and the energized part. The resulting di- flashover probability in the immediate work area.
electric strength in service may then exceed that These gaps may be installed in close proximity to
of the tool or equipment itself but it cannot be the work area (at adjacent structures for exam-
determined from direct addition of the material ple) or at the terminals (line ends) on the ener-
thickness and air-gap sizes. gized part or parts where the work is being per-
3.2.4.3 Dielectric Strength of Support, and formed, or both.
Lift or Reach-Extending Tools and Equipment. 3.2.5.3 Determination of the Gap Length.
In the case of clean, dry tool or equipment, the Determination of the gap length and reduction of
dielectric strength defined as the voltage per unit the insulation distance can be made as follows [40]:
length (kV/ft) of the tool or equipment and is 3.2.5.3.1 To determine a new insulation
approximately constant up to 600 kV crest. Above distance that can be employed by inserting a pro-
600 kV crest, the dielectric strength is not con- tective gap
stant and exhibits saturation. (1) Determine t h e minimum gap distance
3.2.4.4 Current of Personnel Protective or (insulation distance) based on known rod-
Cover Tools and Equipment. For ac excitation, rod gap characteristics to withstand the

20
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

maximum switching-surge voltage antici- line at 5% slope to a probability value of


pated during the work period. - 3 sigma (0.14%)-FFig 3, point A.
Plot this value of voltage on probability (5) Read the value of the voltage at this point.
paper at the - 3 sigmavalue (0.14%)-Fig 3, (6) Using this new voltage, determine the pro-
point A. tective gap distance from Fig 3.
Unless a different value is known for a spe-
cific gap configuration, draw a line at 5% 3.3 Physical Aspects of Energized Line-Work
slope t o a + 2 sigma probability value 3.3.1 Electric Fields. In t h e vicinity of a n
(97.72%)-Fig 3, point B. energized transmission line, an electric field exists
Read the value of the voltage. in the space between the energized conductors
Again, using known gap characteristics for and ground. The strength or intensity of the field
the new voltage, determine the new min- depends upon the number of imaginary lines of
imum insulating distance from Fig 2. electric force per unit area. Field intensity (volt-
age gradient) is defined as kilovolts per unit
3.2.5.3.2 To determine the protective-gap length. A worker standing on the ground under
distance necessary to allow use of a new min- an energized transmission line conductor, a worker
imum insulation distance or approach distance on a tower or pole working on an energized con-
Use the new mimimum distance obtained ductor with live-line tools, or a worker in the
in 3.2.5.3.1(5). If the distance is based on bucket of an aerial lift working on the conductor
insulation, then correct by changing the are all within the electric field. The lines of the
value C2 in the formula given in 3.2.2.2. electric field terminate on the entire surface of
Find the value of the air minimum approach the body and induce an electric current, which
distance on Fig 2 and from this determine flows through the body to ground. An electric
the sparkover voltage. current that passes along the lines of force as a
Plot this voltage on probability paper, at result of the to-and-fro motions of the charges on
the + 2 sigma point (97.72%)-Fig 3, point B. the atoms of the dielectric is known as the dis-
Unless a different value is known for a spe- placement current. If the worker in the field is not
cific protective-gap configuration, draw a grounded, then the displacement current that

Fig 3
Method Used to Determine the Gap Length and
the Reduction of Insulation Distance

21
~

ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

enters one side of the body flows through it and electric field as that of a counterpart working
lines of force emanate from the other side to with conventional tools from the tower. As can be
ground. Under these conditions, the body may seen from Table 6 the use of a conductive suit
assume a potential other than ground and the greatly reduces the effect of the electric field.
person will receive a small disturbing shock when 3.3.2.4 Effects of Fields
he/she touches a grounded object. The magnitude 3.3.2.4.1 General. An electric field, be it
of the displacement current flowing through the generated by alternating or electric sources, pro-
worker depends on his/her position in the field duces a charge on a conductive object. It can
and on the strength of the field at the power induce a current through the human body when
frequency. its strength is sufficient and a conducting path is
In this section we are basically considering ac provided. Protective measures for such field effects
fields. In dc the electric field is essentially static include shielding or bonding, or both.
and no current is induced to flow to the ground. The charge-discharge effect involves the possible
3.3.2 Field Intensities in the Work Area overt move or surprise reaction to the electro-
3.3.2.1 Shielding and Fields. The overall static discharge. The use of a bond cable effec-
field intensity within which the worker is situated tively takes care of this situation. Workers should
is readily controlled by shielding. Investigations take the same precautions of discharging their
and tests have been made to determine field bodies to ground on dc systems.
intensities and associated body current. Workers 3.3.2.4.2 Investigations. Investigations
with suitable shielding are subjected to values into the possible effects of alternating-current
well below the threshold of feeling or sensation electric field on humans commenced in 1962 [37].
(approximiately 1 mA) (361. Comparison of the Examinations were made of workers who used
body current based on the degree of exposure insulating tools and on workers employing the
(shielding) and the electric field for several differ- barehand method who were adequately shielded
ent situations follows [37]. from the electric field. Results indicate that a
3.3.2.2 Types of Shielding. The types of worker is not endangered in any way by working
shielding employed in this comparison ranged barehand in a high-voltage alternating-current
from none to conductive suit through four types electric field as verified by medical reports based
of screen, namely: on a nine-year study [37] and [41]. In 1971
Type A. Complete bucket shielding with a rear reports were made on the medical condition of
shield wall and overhead canopy selected switchyard personnel who were exposed
Type B. Complete bucket shielding with a rear to alternating-current fields of 4 kV/m - 27 kV/m
shield wall and no overhead canopy without being shielded [31]. Some adverse
Type C. Complete bucket shielding only psysiological effects were reported.
Type D. Partial bucket shielding To mitigate the reported effects, recommended
3.3.2.3 Comments. Note that the relative exposure values related to time and field intensity
body current a t a position normally employed on for some selected work areas, operations, and
the tower to perform hot-stick work is higher environments were published. However, since the
than the values obtained with complete bucket published values do not correlate with other
shielding. A worker doing barehand work from a investigations, these time and electric-field expo-
bucket provided with adequate shielding (Type B) sure values are suspect and subject to wide inter-
is exposed to approximately the same or less pretation [39] and [42].
3.3.2.4.3 Comments. The results of a com-
Table 6 prehensive literature survey on the effects of
Worker Exposure and Body Current electric fields have been summarized to describe
two contrasting sets of research findings [32].On
Position Type of Body Current
of Worker Shielding at 138 kV at 345 kV
the one hand, research results have failed to pro-
vide any evidence that human exposure to pres-
On tower* None 125 pA 395 pA
In bucket A 70 pA 130 pA ent levels of fields from high-voltage overhead
In bucket B 155 pA 300 pA power lines, as normally encountered, has any
In bucket C 320 pA **
** harmful biological effect. On the other hand, stu-
In bucket D 375 pA
In bucket Suit ** 50 /LA dies are reported to indicate some undesirable
effects on workers, not in the typical power-line
*Workeron tower approximately 240 cm ( 8 ft) from conduc-
tor and 320 cm (10.5 ft) from conductor at 345 kV. environment, but in the more complex environ-
**Notmeasured. ment found in high-voltage switchyards.

22
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

This disparity in results can be attributed to be considered as acceptable. Tools having


environmental differences between high-voltage values greater than 110%of the acceptance
lines and switchyards. Special measurements of value should be cleaned, dried, and refin-
the low-frequency acoustical noise in a high- ished as recommended or approved by the
voltage switchyard have disclosed a high level manufacturer and retested. Unless the
(104 dB [ref 1 A] of 120 Hz) sound. The high- retest value is less than 110%of the initial
intensity, 100 Hz or 120 Hz, sound can produce value of the tool, the tool should be consi-
symptoms similar to those reported for switch- dered as degraded and should be removed
yard workers that were attributed to the effects from service.
of the electric field. Other possible, biologically (3) Changes in tool or equipment current values
significant, environmental influences in switch- during a test may be indications of any or
yards include repeated spark discharges and the all of the following’factors:
chemical environment. (a) Contamination
Numerous studies have similarly neglected the (b) Moisture
total environment. This neglect presents a major (c) Specimen degradation
obstacle when attempts are made to coordinate (d) Instability of the test setup
results of studies. If the test setup is not at fault, the tool should
Research has failed to provide any convincing be cleaned, dried, and refinished as recommended
evidence t h a t electric fields from extra-high by the manufacturer and retested.
voltage/high-voltage transmission lines as nor- 3.4.3 Voltage, Voltage V,, is t h e maximum
mally encountered have any harmful biological operating voltage to which the equipment should
effect. Studies that report negative findings are be subjected during routine employment in work
considered either transmission-line or electric- operations. For example, for a 345 kV system with
field situations but not switchyard environments. a nominal maximum operating voltage of 362 kV,
The disparity in results could be attributed, there- V,,should be adjusted accordingly. In cases where
fore, to dlfferences in these two environments [33]. the bus voltage is unregulated, the user should
recognize the voltage transformation ratio possi-
3.4 Electrical Tests ble and the maximum voltage that can appear
3.4.1 Introduction. Tables are provided to under normal situations from the source line and
summarize the basic and ‘essential elements of then be reflected through the transformer.
electrical data and values that are applicable, and 3.4.4 Evaluation Equipment
therefore to be considered, in the employment of 3.4.4.1 General
tools, materials, and equipment in energized-line (1) A long specimen should be evaluated by
operations, namely design tests, certification tests, testing along its length. Electrodes should
and periodic tests. I t is recommended that the be oriented so that the section being tested
withstand or voltage check be made with elect- overlaps, or includes, from 5%to 10%of the
tricity of the same characteristics as that on previously tested section. The length of
which the equipment is being used. For example, time for voltage application may be a signif-
if the equipment is being used on 60 Hz, the peri- icant factor in evaluating the quality of new
odic withstand test should be made with 60 Hz ac. specimens. Testing at high voltages for
This requirement is dictated by the presence of ac extended periods to determine specimen
corona under test conditions. Use of dc will not conditions through heating is both ambig-
provide this effect nor provide a true indication of uous and difficult to detect objectively, and
equipment conditions with respect to corona. may lead to premature specimen degrad-
3.4.2 Dielectric Current ation.
(1) The preferred criterion is the measurement (2) Electrodes and cables should be shielded to
of tool or equipment current since this is ground out stray current so the monitored
the primary concern related to the use of current is indicative of the tool or equip-
the specimen. Tool or equipment current ment current through and along the sur-
measurement provides a numerical objec- face of the test specimen.
tive evaluation of the specimen quality. (3) Initial tool or equipment current readings
(2) Tool or equipment current values obtained should be made when the specimen is new
on subsequent tests of a given tool should and has clean uncontaminated surfaces so
be within 10%of the initial acceptance-test as to establish an as manufactured or as
value for that particular tool if the tool is to received condition. These data are used for

23
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

making a comparison between the speci- ( 2 ) Test Current. The supply-current magni-
men being tested and the acceptance limits tude is dependent on factors, such as the
established for that particular cross-section electrode design and the cross-section size
area and specific electrode configuration. of the test specimen.
The value of the tool or equipment current (3) Other Considerations
should be recorded for comparison with (a) Leads, bushings, a n d instruments
later test records of that particular speci- should be shielded to minimize erro-
men. Values of the tool or equipment cur- neous stray current.
rent that change during the test should be (b) Meters of other current-indicating
noted. A reading that shows a decrease devices should be incorporated to give
may be indicative of absorbed moisture quantitative data for material evalua-
drying out during the test. A reading that tion.
shows an increase may be indicative of (c) The power supply should have a n
incipient degradation of the specimen. adjustable interrupting device (circuit
Tests should be performed by competent breaker) to ensure against current
personnel on equipment that is clean and significantly greater than the lower
dry (unless otherwise specified). acceptance level for a given specimen
Historical data is very effective in noting and against damage to t h e power
degradation of electrical insulation and it supply.
is suggested that a base or benchmark be (d) Interlocks and grounding features
established for each piece of equipment should be included for operator pro-
(see 3.4.6.3). tection.
Insulation check. Verification of the integ-
rity of the equipment insulation should be 3.4.4.2.2 Electrode Design and Spacing.
made by one of the following methods: High, electrical-stress areas, particularly at the
(a) Watt-loss measurement edges of the electrodes may lead to streamers at
(b) Tool or equipment current measure- the test-specimen surface unless electrode design
ment and spacing are considered. These streamers occur
Any other test method for detecting breakdown within at voltages below flashover, erode the insulation
the insulation should be approved by a competent authority by ionic bombardment, and cause electrons to
before being used.
rupture the insulation chemical bonds leading to
(7) The test method and test equipment should degradation in the organic materials. The result-
be selected on the basis of the purpose of ing conductive deposits act as an extension of the
the product and the characteristic of fault electrode and cause further progressive degra-
that needs evaluation or detection. The test dation.
setup and test equipment capability must ( 1) Electrode Shielding. Shielding, guarding, or
also be reviewed in this light. improving the shape of the electrode helps
3.4.4.2 Dielectric-Current Measurement to reduce the corona damage of the test
Method specimen. Shielded electrodes modeled after
3.4.4.2.1 Fiberglass-Reinforced Plastic the one shown in Fig 4 should include the
( f r p ) and Wood Materials following features:
(1) Test-Voltage Supply. The power supply vol- (a) Intimate contact of the electrode to
tage parameters are dependent on factors, the test-specimen surface
such as electrode design and the distance (b) Shield oriented as shown in Fig 4,
over which the tests are conducted. The Detail 1 so that its leading surface is
required test-voltage capacity for manu- 25 mm (1 in) closer to the high-voltage
facturers' testing is that which will give a electrode than the contact spring on
voltage gradient of 100 kV rms/ft of t h e pickup electrode assembly, t o
fiberglass-reinforced plastic (frp) specimen ensure adequate shielding.
being tested. The required test-voltage ( 2 ) Electrode Spacing. The spacing of elec-
capacity for acceptance testing by users is trodes is determined by the purpose of the
that which will give a voltage gradient great test and the voltage chosen. For manufac-
enough for evaluation of material but not turers' or production testing of fiberglass-
so great as to lead to material degradation reinforced plastic (frp) materials, the volt-
from corona or streamer discharges. age should be 100 kV. Short spacing of

24
ANSI/IEEE

$
METHODS ON ENERGIZED POWER-LINES Std 516-1987

TO OUTER STRAY CURRENl

HIGH VOLTAGE LEAD

HIGH-VOLTAGE CORONA RING

O I L CURRENT COLLECTOR
DETAIL 1 DETAIL 2

SHIELDED CABLE
1 SHIELD
/ RAOIO- ,-SHIELD ED'ENCLOSURE

I VOLTMETER
HEWLETT-PACKARO 403A I POLE CLEARANCE
0 1 8 1 n O R 45 m m
STRAY CURRENT GUARO FOR
CURRENT COLLECTOR AT
GROUND EN0

DETAIL4 METER CIRCUIT DETAIL 3

GENERAL SET UP
lOOkV 60Hz

GROUND EN0 HIGH VOLTAGE CORONA


CORONA RING RING
WITH GUARO FOR
STRAY CURRENT
TO CURRENT BAND

METER L E A 0
TO CURRENT BAND

CURRENT BAND

BONO TO
SHIELDED CABLE INSULATED-
SUPPORT

II I
MINIMUM CLEARANCE
SHIELDED TO ANY GROUND
CABLE PLANE3ftOR90cm

TO METER
CIRCUIT
ENCLOSURE 7

Fig 4
Typical Setup for High-Voltage Tests

25
ANWIEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

electrodes allows inspection of more mi-


nute sections for quality control and thus
avoids the averaging effects of wider elec-
trode spacing, for example, 100 kV at 12 in where
(30 cm) spacing or an equivalent potential R = ohms
difference, such as 50 kV at 6 in (15 cm) I , = amperes
spacing prove satisfactory. Testing may also W = watts
be performed over a greater distance pro-
Measurement sensitivity should be sufficient to
vided the applied voltage and distance are
distinguish between 1Olo a and 10" 0 resistance.
proportionally increased.
NOTE: Capacitance and power-factor measurements are not
NOTE: High-voltage testing at less than 6 in (15 cm) electrode recommended for routine tests on specimens having a capac-
spacing is not recommended. itance on only a few picofarads. Accurate measurement of
these quantities depends on complete, specimen shielding sys-
tems, which are not feasible for routine tests.
3.4.4.2.3 Dielectric-Current Evaluation
Criteria. The curve data given in Fig 5 may serve (2) A guard shield to avoid measurement losses
as a guide in judging the test results. See 3.4.4.3.3. in the equipment itself must be incorpo-
3.4.4.3 Watt-Loss Method rated in the test equipment, including con-
3.4.4.3.1 General. The watt-loss method nections to the specimen. Preferably, the
is employed to determine the electrical condition test equipment should be able to make
of fiberglass-reinforced plastic (frp) and wood measurementss using ungrounded speci-
materials using the loss or absorption of energy by mens with t h e guard shield at ground
the material compared to a reference based on a potential (see IEEE Std 62-1978 [28]). The
new or good condition value. watt-loss test is relatively unaffected by
3.4.4.3.2 Test Equipment extraneous objects in the vicinity of the
(1) A suitable test voltage, usually at least specimen.
2500 V, must be supplied by the test equip- (3) Test electrodes are applied in the selected
ment. Provision for the measurement of area. Each electrode may be a conducting
watt loss or the loss (conduction plus leak- strap or collar wrapped tightly around the
age) component of the total specimen cur- specimen or clamped to it. A metal fitting
rent is required. The alternating-voltage attached to the specimen is sometimes
resistance of the specimen can be calcu- used as an electrode. A common arrange-
lated as ment is three electrodes with a spacing of

Fig 5
Typical Values of Dielectric Current for
Fiberglass-Reinforced-Plastic( f r p )
Poles of Various Diameters

ACCEPTlREJECT VALUES OF DIELECTRIC CURRENT FOR


INITIAL MANUFACTURING OR AS RECE/V€D TESTING
OF FOAM-FILLED POLE WHEN USING TEST SETUP OF
14 FIGURE 4 AT 100 kV/ft

12
3-
c
t 10
U
2
V
E 8
0
2
w
0 6

1 1/2m 2 In 2-1/2 in 3 in
(3 8 crn) (5 cm) (64 crn) (76 crn)
FIBERGLASS-REINFORCED-PLASTIC IFRP) POLE DIAMETER Icrn and in)

26
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

3 in (7.5 cm) (see Fig 6). The test voltage is usually indicates excessive moisture absorption,
applied to the center electrode and the dirt, or damage. Equivalent criteria in terms of
measurement made between it and the leakage current or watt loss at the specified test
outer electrodes. voltage may be derived from these resistance
NOTE: With 10 kV applied, the 6 in (15 cm) section under test values.
is stressed at 40 kV/1 ft (30 cm). 3.4.4.4 Orientation of Equipment and Test
(4) For long poles, sticks, and other specimens Specimen
of considerable length, measurements may (1) The high voltage should be applied to the
be made a t two or more locations along the end of the test specimen nearest to the
length using the three-electrode method power supply. The orientation of the high-
described in 3.4.4.3.2(3). An important test voltage bus and test specimen should be
location is a t both ends of the insulating such that nearby ground planes do not
tool, that is, the end normally applied to introduce significant capacitive effects.
the energized line and the end held by the (2) To reduce the effects of stray current on
worker. An alternative method is to use the specimen and on the meter indication,
two electrodes separated by a consider- the specimen being tested should be paral-
able distance although this usually requires lel to the high-voltage lead or bus (see
testing a t a high voltage so as to meet the Fig 4).
test-equipment sensitivity requirements (3) The orientation of the watt-loss test equip-
specified in 3.4.4.3.2(1).When making a ment should in accordance with the in-
two-electrode measurement, use of t h e structions of the test-equipment manufac-
ungrounded-specimen test specified in turer.
3.4.4.3.2(2) is recommended. 3.4.5 Standard Test Classification. The fol-
3.4.4.3.3 Watt-Loss Method Criteria. lowing tables are based on the life history aspect
The criteria for acceptance of tools checked of tools, material, and equipment.
by the watt-loss method should be based on watt- NOTE: To simphfy further references in this section, the term
loss values formulated from histogram data. Test equipment will be used to cover the three nouns cited.
criteria for specimens made of the same material 3.4.5.1 Design-Test Criteria. The values and
and similar dimensions are usually determined other criteria recommended should be used by
from statistical analyses. However, it can be stated the persons involved in the initial specification,
that wood, fiberglass-reinforced plastic, and many design, component selection and testing, and
composite insulating materials, when clean and assembly of the equipment.
dry, have very low leakage so that an alternating- Commonly used values for the anticipated max-
current resistance greater than 1Olo R is obtained imum switching surge S, are
with the usual three-electrode test arrangement. w 345 kV-S, 3.0 per unit or
=
If a resistance of l o 9 R or less is obtained, this less
From 345 kV to 500 kV-S, = 2.4 per unit or
Fig 6 less
General Circuit for Watt-LossTesting From 501 kV to 700 kV-S, = 2.0 per unit or
less

r TEST VOLTAGE 3.4.5.1.1 Aerial-Lift Equipment, Insulat-

i ing Tools and Other Similar Equipment.


(1) Nominal voltage criteria
(a) Test voltage = VnLc
(b) Maximum permissible current = 1 PA/
~VLG
(c) Test voltage applied for 3 min
(2) Double rated test
(a) Test voltage = 2 VnLG
where
S, V, < 2 V,, substitute 1.3 V, for 2 V,
(b) Maximum permissible current = 1PA/
kVLG
(c) Test voltage applied for 3 min

27
ANWIEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

(3) Withstand test Table 7


(a) Test voltage = S;V, Periodic (Routine) Test Values
(b) Test voltage applied momentarily
Condition Dielectric
NOTE: Corona-ring design should be made with regard to Wet Dry Current
boom configuration and for negative-polarity streamers.
Vn Vn I,
3.4.5.1.2 Conducting Protective (Shield- Device (kV/ft) (kV/ft) (FA) Reference
ing) Equipment Insulating hand lines
During the 3 min proof test, the dielectric
current surface should be monitored and Manila 0 75 l/kVLG
Synthetic 30 75 l/kVLG
recorded. The constant current on 4 in2 Chain 40 75 l/kVLG
(25 cm2) on surface should be I = 2 mA
Shielding Pulling-in lines
Dielectric (leakage) current = Manila 0 75 l/kVLG
(1 pA/1 R )/in2 [(l p A / l n )/6.5 cm2] Synthetic 15 75 l/kVLG
at an electric field of 25 kV/m Slings 30 75 l/kVLG
Thermal withstand of the material = 400 OF
(200 "C) on contact
3.4.5.2 Certification-Test Criteria. Certifi-
cation tests are used to demonstrate that the
final equipment assembly has performance char- (4) Switching impulse withstand voltage
acteristics that will enable the equipment to be (250/2500 ps)
used under design conditions. Certification tests Distribution voltages = 2 . 4 / a . VR peak
should not be destructive in nature and are con- Transmission voltages = 3 . 0 / 0 ' VR peak
(5) Shielding
sidered to be of limited frequency, that is, on
Dielectric (leakage) current =
initial purchase of equipment, after repairs, and
(1 pAI1 R)/in2 [ ( l pAI1 R)/6.5 cm2]
for future recertification. The same applies to
at an electric field of 25 kV/m
acceptance tests. For impulse and switching-surge
3.4.5.3 Periodic-TestCriteria. Periodic tests
tests, the magnitude of voltage used is given as
may be made to determine the condition of the
crest values.
Commonly used values for the anticipated max- equipment. Test intervals may be established on
criteria such as,elasped time, voltage level, number
imum switching surge S, are
of times used, condition of use or company user
Below 345 kV S, = 3.0 per unit or less policy, or a combination of these. Even when
From 345 kV to 500 kV S, = 2.4 per unit or less equipment passes a periodic electrical test, the
From 501 kV to 700 kV S, = 2.0 per unit or less user should still visually inspect or otherwise
check the equipment before use. For example,
NOTE: These factors may be reduced by factors within the even though a rubber glove is given a periodic
system.
electrical test, there is no assurance that the glove
3.4.5.2.1 Aerial-LiftEquipment", Insulat- has not been damaged in transportation from the
ing Tools, and Other Equipment. Test values test site to the work site, so a visual inspection
and conditions are the same as in 3.4.5.1.1. should always be made before use to check for
3.4.5.2.2 Insulating Protective Equipment. mechanical damage.
manufacturer's rating kV 3.4.5.3.1 Aerial-LiftEquipment, Energized-
3 min proof withstand voltage = 1.4/ Line Tools, and Other Similar Equipment.
fi - v , r m s (1) Test voltage = VLG(operating voltage)
Minimum critical flashover voltage = 1.6/ (2) Maximum permissible current = 1 pAI kVLL
fi -VRrms (3) Time of applied voltage = 3 min
Impulse withstand voltage (1.2/50 ps) (4) Check insulation for cracks, blisters, or
Distribution voltages = 2.8/fi * VRpeak other visual signs of deterioration
Transmission Voltages = 3 . 0 / n ' VR peak 3.4.5.3.2 Conducting Protective (Shield-
ing) Equipment
(1) Conductive clothing (suit, shoes, socks, and
gloves). Resistance, head to foot: R = 100 0,
l 1 Corona-ring design should be made with regard to boom maximum
configuration and for negative-polarity streamers. (2) Maximum resistance:R, = 1 O / l in (2.5 cm)
ANWIEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

3.4.6 Acceptance-Test Reference equipment and shows trends in the performance


3.4.6.1 Number of Tests. If no disruptive dis- of the material under tests.
charge occurs during any five consecutive 3.4.6.4 Electrical-Test References
impulses, the specimen should be considered as (1) Low frequency: ASTM D149-87 [9].
having met the test. If more than one of the ap- (2) Lightning impulse: ANSI/IEEE Std 4-1978
plied impulse waves cause a disruptive discharge, [41.
the test specimen should be considered as having (3) Water for wetting: IEC 265-1968 [27].
failed the test. If only one of the five applied Method of test, 7000 Win3 (17 800 R/cm3)
impulses causes a disruptive discharge, ten addi- k 15%at 77 OF (25 "C).
tional impulses should be applied. If no disruptive (4) Standard atmospheric conditions: tempera-
discharge occurs on any of the ten additional ture of 77 OF (22 "C) +
9 O F (5 "C); relative
impulses, the specimen should be considered as humidity of 35% minimum.
having met the test, otherwise the specimen has ( 5 ) Correction to standard conditions: light-
failed. ning and switching impulse; voltage, ANSI
3.4.6.2 Differences in Tool or Equipment C29.1-1982 [3].
Current. When the tool or equipment-current
values for two adjacent sections differ by more 3.4.6.5 Tools and Equipment. See Table 8
than 20% of the smaller value, the tool should be for types of tools and equipment.
rejected even if it meets other criteria. 3.4.6.6 Acceptance Tests Required. Accep-
3.4.6.3 Histograms. Histograms of initial tool tance tests for various tools, devices, and equip-
or equipment-current values for acceptance of ment should be as shown in Table 9.
tools or equipment may be established from pro- 3.4.6.7 Specific Test Guidance
duction or manufacturing limits. The basic pur- 3.4.6.7.1 Dielectric Tests. Dielectric tests
pose of these histograms is to indicate a trend for protective cover-up material should be con-
and to establish reference points of each tool ducted to evaluate the capability of meeting the
being tested. In the absence of historical infor- values indicated in 3.4.6.4 for such equipment.
mation or another equivalent basis, the tool or 3.4.6.7.2 Evaluation of Criteria. After
equipment-current values for fiberglass-reinforced considering the performance of line protection
plastic provided in Fig 5 are applicable. and other equipment in accordance with the tests
Plotting of histograms on graph paper give a listed in Tables 10 and 11 the performance char-
good graphic review of the testing of the tool or acteristics can be determined and assigned.

Table €4
Types of Tools and Equipment
Device Reference Remarks

Aerial lifts ANSI A92.2-1979 [ l ] Latest revision


Rope CSA C225-76 [ 241 Latest revision
Gloves ASTM D120-87 [SI Latest revision
Sleeves ASTM D1051-87 [13] Latest revision
Blankets ASTM D1048-88a [ 101 Latest revision
Hose ASTM D1050-85 [I21 Latest revision
Hoods ASTM D1049-88 [ I l l Latest revision
Hard cover-up -
Hot sticks -
Conductive suits
Conductive footwear
Carts Cable cart suspended from
conductors
Stringing equipment ANSI/IEEE Std 524-1980 [SI
Synthetic chain - Includes that made from
polypropylene
Line guards ASTM F968-85 [21]
Couplers ASTM F968-85 [21]
Crossarm guards ASTM F968-85 [ 2 1 ]
Pole covers ASTM F968-85 [ 2 1]
Cutout covers ASTM F968-85 [ S l ]
Helicopters CFR, Section 29.1926/551 Used to lower and raise
and 1910.183, OSHA [23] workers to and from
structures

29
ANWIEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

Table 9
Acceptance Test References
Tool, Equipment, or Device Standard or Other Remarks

Cover-up equipment
Flexible material
Glove ASTM D120-87 [8] Latest revision
Insulator hoods ASTM D1049-88 [ 11] Latest revision
Line hose ASTM D1050-85 [ 121 Latest revision
Sleeves ASTM D1051-87 1131 Latest revision
Blankets ASTM D1078-86 (141 Latest revision

Rigid material ASTM F968-85 [ 2 1]


AI1

3.4.7 Guidance for Specific Devices made of one wrap of AWG No 18-AWG
3.4.7.1 Synthetic Rope No 24 bare copper wire and pigtailed.
Samples of rope from every lot (single (4) The wetting of the specimen should be
finished-production length) should be tested done in the following manner. A clean
by the manufacturer and each reel identi- nonmetallic tank or trough shall be rinsed
fied by lot. If the single finished-production with the same type of water to be used dur-
length is greater than 600 ft (180 m), the ing wetting [see 3.4.6.4 (4)]. The entire
tests should be conducted at both ends. rope specimen should be kept submerged
The rope specimen for testing should be at horizontally in the test water at a depth of
least 8 f t (250 cm) long so that when the 12 in (30 cm) for a period of 15 min to 20
rope is held in a vertical position there will min. The hold-down devices should be non-
be 5 ft (150 cm) of rope free from knots, metallic.
eyes, or splices. The ends should be heat- ( 5 ) The specimen should be drained within
sealed. When the specimen is handled, it 1 min after removal from the wetting tank
should always be outside the test length by hanging it in a vertical position with an
(see Fig 7). unrestrained weight of 10 Ib (4.5 kg) at-
NOTE: Rope is tested in a vertical position so that the tached. It should be allowed to drain at
effect of moisture inside it can be evaluated. atmospheric conditions as near standard
as practical with the rope-attachment point
The electrodes should be attached prior to
and weight-attachment point as shown
wetting the specimen (see Fig 7 for at-
in Fig 7. The specimen should be allowed to
tachment points). The electrode should be
dry for 15 min.
(6) The 60 Hz voltage should be applied imme-
Table 10 diately after the 15 min drying period and
Evaluation Criteria should be raised from 0 kV to 30 kV in not
less than 5 s but not more than 15 s. The
Performance Evaluation
Characteristics Technique voltage should be held at 30 kV for 30 s. The
current obtained over 24 in (60 cm) of the
Voltage 1. 60 Hz flashover test specimen should not exceed 1 mA
2. Switching-surge withstand
3. Lightning impulse from the time of initial application of volt-
age until the end of the test.
Current 60 Hz flashover voltage
tool or equipment current
-
3.4.8 Marking and Identification General
(1) All equipment should be marked with the
manufacturer’s name or logo, and date of
Table 11 manufacture, (month and year).
Periodic (Routine) Test Values (2) All markings and identification should be
permanent, that is, weather-resistant, not
Applied voltage 1.2 V,, LG susceptible to sunlight, fading, etc. They
Duration of voltage 3 min should be tested, as required, to ensure
Permissible maximum
tool or equipment current 1 pAIW they will remain legible for the intended
service life of the device. See Table 12.

30
ANWIEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

- ROPE-ATTACHM ENT PO INT


(BASKET. PARALLEL JAW, OR EQUIVALENT GRIP)
(NOT GROUNDED)

HIGH-VOLTAGE ELECTRODE
ATTACHMENT POINT

24 in (60cm)

60 in (150 crn)

ATTACHMENT POINT (GROUND)

10 Ib (4 5 kg)
WEIGHT

Fig 7
Typical Test Setup for
Dielectric Testing of Rope

Table 12 facturer’s tests. After the equipment is put into


Marking and Identification Guide service, periodic testing and in-service checking
ensures that the capability of the equipment
Equipment Information To Be Supplied remains adequate.
Gloves ASTM D120-87 [ 8 ] ,Section 5 The material for tools constructed of fiberglass
Blankets ASTM D1048-88a [lo], Section 5 reinforced plastic (frp) is tested by manufactur-
Hoods ASTM D1049-88 [ l l ] , Section 7 ers in accordance with ASTM F-711-83 [19].
Hose ASTM D1050-85 [12], Section 7
Sleeves ASTM D1051-87 [13], Section 5
Rigid or plastic cover-up 1. Manufacturer’s name or logo 4.2 Scope. This section covers field care in use
2. Date of manufacture handling and storage, periodic inspection and
(month and year)
checking, and maintenance and repair of tools
and devices.
4. In-Service Checking and Care
4.3 Field Care, Handling, and Storage
4.1 Introduction. Tools a n d devices used in 4.3.1 Insulating Tools. When not in use, insu-
energized-line maintenance are usually tested by lating tools should be stored where they will
the manufacturer for certification (see [ l ] ,[8], remain dry and clean and not be subjected to
[lo], [12], [13], [21], and [35]). Very often the abuse. Wood insulating tools should be adequately
user conducts electrical certification (acceptance) supported or hung vertically to prevent warping
testing of equipment and tools to verlfy the manu- a n d stored in a temperature- and humidity-

31
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

controlled room. Insulating tools used for ener- the ground; this can be accomplished by paying
gized-line maintenance should not be laid on the the rope in and out of the container, or by having
ground because of possible contamination or wet- a tarpaulin or other type of ground cloth on
ting. They should be placed on clean, dry tarpau- which to put the rope. Rope used in energized line-
lin, moisture-proof blankets, on tool racks, or work should not be used for any other purpose.
leaned against dry supports. When transporting Handlines and slings should be stored by tying
insulating tools, ventilated containers should be them in hanks or coils and suspending them from
provided to prevent damage to the surfaces of the a rack where the air can circulate freely between
individual tools, or the tools should be mounted them. Rope should never be used wet when a vol-
on racks in trucks or trailers. These racks should tage is applied across it. Not only may a current
be well padded and so constructed that the tools pass through the rope but this current may cause
are held firmly in place. localized internal heating resulting in an almost
4.3.2 Insulting Aerial Equipment. When park- total loss of mechanical strength which is not eas-
ing aerial devices in buildings or maintenance ily detected visually.
garages where heat sources are present, care 4.3.4.2 Natural Fibers. Natural-fiber rope
should be taken to avoid damage to the insulated should be stored so as to remain clean, cool, and
portion of the arm from excessive heat. Fiberglass dry as deterioration is accelerated by hot, humid
portions can be damaged if their resins are ex- conditions. Care should also be taken so that the
posed to temperatures of 176 "F (80 "C) or more. rope does not come into contact with acids, caus-
The recommended maximum boom and bucket tics, or their vapors.
loads should not be exceeded. Natural-fiber rope used for conductor-pulling
When moving an aerial device, the boom should lines, when wet, should not be wound on a drum
be in the rest position, the buckets in the normal or reel and allowed to remain there for long peri-
storage place, and the boom tiedowns secured, ods of time. A minimum safety factor of 5 should
unless the device is specifically designed to be be applied to the mechanical strength of natural
moved with the boom elevated. fiber ropes.
When the unit is being moved, the boom hydrau- 4.3.4.3 Synthetic Fibers. Synthetic rope
lic system should be disengaged, the auxiliary should not be stored under tension as it has a
engine, if used, should be shut down, and in the tendency to become permanently elongated; this
case of hydraulically leveled buckets, the free- will reduce its breaking strength. It should also be
swing valve should be open. stored in a dark place as exposure to sunlight or
4.3.3 Insulating Cover-up Equipment. Cover- ultraviolet tends to lessen the mechanical strength
up equipment should be stored in a clean, dry and cause deterioration. A safety factor of between
condition. Tars and oils left in contact for long 5 to 9 should be applied to synthetic ropes, de-
periods can cause softening of plastics and rubber pending on the material and type of construction.
which, in turn, can reduce the dielectric strength The manufacturer should be consulted for the
of the materials; the equipment should preferably exact value.
be stored in canvas bags or draped with a plastic 4.3.5 Clothing
cloth to prevent dust and other contaminants 4.3.5.1 Conductive Clothing. Conductive
from building-up on the surfaces. Equipment clothing, including footwear, should be stored
should not be stored close to heating pipes or in separately in a location that is dry and dust-free
places where they might be exposed to the sun- to prevent contamination by grease, oil, dirt, or
light for prolonged periods of time. water. It should not be exposed to direct sunlight
Protective cover-up equipment should be trans- for long periods of time.
ported in canvas bags or other protective con- Other objects should not be stacked on the suits
tainers. Materials that might crack or distort of clothing because of possible damage to the fine
cover-up equipment should not be placed or piled interwoven material that forms the conductive
on top of these containers. portion of the suit and result in hot spots.
4.3.4 Insulating Rope Extreme care should be taken when storing the
4.3.4.1 General. Rope used in energized line- suits of clothing to ensure that they are clean and
work should be kept clean and dry. It should be that no sharp or rough objects, which could rip or
stored in clean, dry containers when not in use. tear the materials, are stored with the suits.
The use of a moisture absorbing agent such as Conductive suits and related equipment should
desiccant is suggested. When used for transmis- be transported in separate containers to prevent
sion, the rope should not be permitted to contact damage.

32
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

4.3.5.2 Insulating Clothing. Insulating cloth- When the insulating member of a tool shows
ing, such as rubber gloves, rubber sleeves, and signs of accumulated contamination, tracking,
overshoes should be stored in clean, dry locations. surface blisters, excessive abrasion, nicks, or deep
Care should be taken to prevent damage from scratches, the tool should be removed from ser-
rough objects. In addition, insulating equipment, vice, and cleaned or refinished as recommended
such as gloves, should not be dropped or allowed by the manufacturer, and retested. Moisture will
to ride down a handline. Rubber insulating gloves reduce the insulating properties of these tools.
should never be used without placing protector When tools have been exposed to excess mois-
gloves over them. A small puncture in the rubber ture, their moisture content can be measured
could render any insulating apparel useless. In with a commercially available moisture meter in
general, the same care should be given to insulat- accordance with the manufacturer’s recommen-
ing clothing as to conductive clothing. dations.
4.3.6 Conductor Carts. Care must be taken to Jack screws should be examined for excessive
ensure that the combined weight of the conduc- looseness (indicative of worn threads) and free-
tor cart, workers, and equipment does not allow dom from binding. Worn elements should be
the electrical clearance at midspan to be reduced replaced. Bolt and nut threads should be free of
below the electrical minimums indicated in Tables burrs, roughness, or other damage t h a t may
2, 3, 4, and 5. seriously erode mating threads, and all threads
4.3.7 Grounding and Bonding Devices. The should be lubricated only with dry lubricants.
effectiveness of these devices depends on the
integrity of the electrical-contact surfaces, the 4.4.2 Insulating Aerial Equipment
cable stranding, and the clamping mechanism. 4.4.2.1 Inspection Before Live Line-Work.
Care should be taken to prevent damage to the Before equipment is used for live line-work it
cable and the clamping mechanism. These devices should undergo a comprehensive, recorded, daily
should be stored separately to avoid kinking the inspection. Items to be checked or inspected daily,
cable. Contact surfaces and threads should always or both, should include, but not be limited to
be kept clean. Heavily oxidized or tarnished con- (1) Emergency power system, including battery
tact surfaces may present excessive contact resist- (2) Hoses and controls (hoses should not be
ance. Poor contact surfaces may jeopardize safety cut or damaged and controls should move
in the event of a line fault. freely)
( 3 ) Insulating section of boom, which must be
4.4 Periodic Inspection and Checking. Proce- wiped down and visually inspected
dures for periodic electrical testing of tools and (4) The engine should be started and the device
devices used in energized-line maintenance are operated through its normal operating cycle
given in Section 3. The acceptance in-service check with no one in the bucket. Any unusual
values for these devices are listed in Table 7. noise, malfunctions, oil leaks, erratic move-
4.4.1 Insulating Tools. Insulating tools should ment, or other occurence that is not nor-
be inspected for indications that show they may mal should be noted.
have been mechanically overstressed. Tools that 4.4.2.2 Periodic Inspection. Comprehensive
show evidence of being overstressed (such as, periodic inspections should be made and records
damaged, bent, worn, or cracked components) kept on file. Items t o be checked, serviced, and
should be removed from service and evaluated for repaired should include but are not limited to
repair. Feathered, elongated, or deformed rivet Vehicle and aerial device for lubrication as
ends, indicate that excessive mechanical loading specified by the manufacturer
has occurred and has weakened or sheared the Vehicle power take-off for mounting, con-
bond between the ferrules and the insulating pole. trols, linkage, and leaks
Hardware, bolts, and pins should be replaced Hydraulic pump for mounting, hose con-
only with high-strength, tempered-steel material, nection, leaks, and noise level
Grade 5, or the same as the original part. Nonde- Filters for cleanliness or replacement
structive testing should be performed on the mech- Hydraulic lines for leaks and general condi-
anical end-fittings and saddle clamps after a tool tion
has been subjected to possible overstressing or Mast and turret for cracks and excessive
vibrating loads for any extended periods of time motion in the bearings
(Magnaflux, Zyglo, and Xray may be used for Rotation motor and gear box for oil level,
checking ferrous and nonferrous parts). leaks, and drive mechanism
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

(8) Manifold block or rotary connections for be checked prior to use to make certain the
leaks wheels, drive mechanisms, safety slings, and bond-
(9) Bucket controls for free movement and ing traveler wheel are in good condition.
self-centering 4.4.7 Grounding and Bonding Devices. These
(10) Oil reservoir for oil level devices should be inspected for strand breakage,
(11) Outriggers for mounting, welds, and proper especially around the areas where the ferrule is
functioning of holding valves crimped to the cable, tightness of the cable termi-
(12) Pivot points for lubrication, proper hose nal to the clamp body, and condition of the
routing, wear, and hose condition threads for smooth operation and clean surfaces.
(13) Bucket-leveling system to make sure the
bucket levels properly 4.5 Maintenance and Repair of Tools and
(14) Boom-lift cables for wear, broken strands, Equipment
and proper adjustment 4.5.1 Insulating Tools. Repair to insulating-
(15) Booms for cracks, alignment, and general tool fittings by welding or reshaping should not be
condition of the insulating sections done because damage by impact or overstressing
(16) Boom cylinders for leaks and properly func- may have weakened the member elsewhere. Weld-
tioning holding valves ing may also damage heat treatment of the part.
(17) Bucket and bucket liners for bruises, cuts, Damaged tools should therefore be removed from
and cracks service.
(18j Emergency systems for proper operation 4.5.1.1 Fiberglass-Reinforced Plastic (frp)
(19) D ring attachment for security Tools. Insulating tools of fiberglass-reinforced
(20) Throttle control for proper cycling and sys- plastic should be wiped with a clean cloth or
tem settings paper towel before use and as soon as they
4.4.3 Insulating Cover-upEquipment. Cover- become noticeably contaminated. Cleaning with a
up equipment should be inspected for dents, strong detergent solution followed by thorough
tears, cracks, punctures, burns, tracking, distor- rinsing or a cleaning recommended by the manu-
tion, soft spots, loose or broken appendages, con- facturer is usually sufficient. However, if this does
tamination, and dampness. Cover-up equipment not remove all foreign matter, tools may be washed
that is damaged, as distinguished from being with a suitable solvent. After cleaning, the tools
soiled or damp, should not be used but set aside should be wiped with a finish restorer recom-
for electrical tests and possible repairs. mended by the manufacturer.
Equipment that is damp should be thoroughly Fiberglass-reinforced-plasticinsulating tools
wiped with a clean cloth both inside and outside should be repaired only by competent personnel.
before use. Where wiping internally by hand is Light spots are caused by impact blows and may
impossible because of space a clean cloth should or may not have a noticeable effect on the strength
be thrust through to swab internal surfaces. Cov- or electrical properties of the tools. If there is no
ers that are soiled with dust or mud should be surface roughness, there is no need for repair.
wiped with a moist rag and dried. Small surface ruptures can be seen with the
4.4.4 Insulating Rope. Ropes used for ener- naked eye and should be repaired by competent
gized line-work should be frequently inspected for personnel by removing the damaged fibers, clean-
deterioration, wear, broken strands, and condi- ing the void, and following the manufacturer’s
tion of eyes and splices. Inspection should include recommended procedure for repair.
examination of the inner strands. If there is any indication that the outer layer of
4.4.5 Clothing-Conductingor Insulating. All material has separated, leaving a void beneath
conductive clothing should be visually inspected (this void can accumulate moisture or, under
before and after use, checking for rips, punctures, electrical stress, become ionized), the tools should
or any damage that may prevent complete shield- be removed from service and refinished as recom-
ing. A defect in the conductive clothing or its mended by the manufacturer. Numerous light
bonding apparatus should be a reason for remov- spots may show excessive abuse and, coupled
ing it from service and instituting immediate with surface contamination, may reduce flashover
repairs and testing. or contribute to insulation degradation.
Particular care should be given to removing dirt 4.5.1.2 Wood Tools. Although the surface of
or gravel, which may be embedded in conductive the tool may appear to be perfectly dry and the
shoes. finish in excellent condition, the wood may have
4.4.6 Conductor Carts. Conductor carts should absorbed excessive moisture from the air if the
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

tool has been exposed to high humidity. There- conductive clothing. Clothing should be washed
fore, extra precautions should be taken during with a mild detergent and thoroughly rinsed in
wet seasons of the year. Treatment in a drying clean water. The only repairs that should be per-
cabinet is recommended if leakage is encoun- mitted are conductive patches with conductive
tered. In these cases, tools should be dried at 90 OF thread or glue, and all repaired sections should be
(32 "C) for approximately 48 h and subsequently tested before reuse. Only conductive rubber should
subjected to a dielectric or power-factor test. be used for repairing conductive boots.
Prompt touching-up is recommended where the 4.5.5.2 Insulating Clothing. Repairs to insu-
finish is worn or damaged to prevent dirt or mois- lating clothing are not recommended.
ture from entering and becoming absorbed by the 4.5.6 Conductor Carts. Damaged or fatigued
wood fibers where it might form dangerous con- members should be replaced and bonding circuits
ductive paths. periodically checked for continuity.
When general refinishing is required, wood tools
should be thoroughly dried to 6%or 7%moisture
content. After the old varnish and foreign mate- 5. Work Methods
rial have been scraped off, the surface should be
rendered smooth with flint paper and finished 5.1 Introduction. This section covers work meth-
with two or three coats of varnish, sanding lightly ods based on accepted clearances and techniques
between coats. used by electrical utilities in work on energized
Damage to the finish should be repaired accord- lines. It should in no way be considered as a train-
ing to the manufacturer's recommendations. ing outline or be used by untrained personnel as
Repairs and refinish should be done by compe- instructions for doing work on or in the vicinity of
tent personnel and followed by a dielectric or energized lines.
power-factor test.
4.5.2 Insulating Aerial Equipment. All repair 5.2 Scope. This section covers detailed methods
work should be performed by or under the super- and proper use of equipment for the various con-
vision of competent workers. ditions under which live-line maintenance can be
A detailed record should be kept of all mainte- performed.
nance and repairs performed on the aerial device. 5.2.1 Categories of Energized-Line Mainte-
Replacement parts should be as specified by nance
the manufacturer or as approved by the user. 5.2.1.1 Workers at Ground Potential. The
After major repair work has been performed on workers are located on the structure supporting
the insulated portion of the aerial device, a certi- the conductor or on other work platforms and
fication or periodic test should be made before remain essentially at ground potential using insu-
the device is returned to service. lating tools and equipment.
A thorough inspection of the device should be 5.2.1.2 Workers at Intermediate Potential.
made if the recommended maximum load of the The workers are isolated from grounded objects
bucket or boom has been exceeded. by insulating means, such as an aerial man lift or
4.5.3 Insulating Cover-upEquipment. Repairs an insulating ladder or platform, and work with
to cover-up equipment having cracks, tears, or insulating tools and equipment.
holes are not recommended. The only parts that 5.2.1.3 Workers at Line Potential. Workers
might be repaired are appendages, damaged or are bonded to the energized device on which work
loose, that have no effect on the dielectric strength is to be performed and are insulated from
of the equipment. grounded objects and other energized devices
For instance, a loose rope loop might be rece- that are at a different potential. This is commonly
mented using the manufacturer's recommended known as the barehand technique.
repair kit or the scissors bar, or its mounting
hardware might be replaced or reattached to the 5.3 Insulating and Working Clearances
bottom lip of the line guard. (1) Working clearances should be obtained by
4.5.4 Insulating Rope. Damaged sections adding to the minimum insulation distance
should be removed and spliced following the (Table 2) an additional distance to provide
manufacturer's recommendations. for inadvertent movements of the worker.
4.5.5 Clothing The amount of this increase should be the
4.5.5.1 Conductive Clothing. Body residues prerogative of the owner of the facilities on
and other impurities will cause deterioration of which work is being performed.
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

When a person is at an intermediate poten- 5.4.2 Precautions when Working at Ground


tial, whether to perform work isolated from Potential
energized parts or when approaching such (1) I t is important to determine correct loca-
parts, the distance between the worker and tions on structures for placement of tem-
ground, plus the distance between the porary rigging loads.
worker and the energized device, should (2) Care should be exercised to ensure that
never be less than the minimum insulation tools properly engage conductors or hard-
distance (see Table 2). ware, or both, before transferring a mecha-
While withstand values of dry surface insu- nical load to the tool.
lation and of air gaps are essentially the (3) Sticks should not be overloaded.
same for dc stresses as for ac stresses hav- 5.4.3 Precautions when Working at Interme-
ing the same peak voltage to ground, small diate Potential
amounts of moisture and dirt on surface (1) When passing conductive objects to the
insulation have a much greater degrading worker a t intermediate potential, care
effect for dc stresses compared to ac and should be taken not to decrease the min-
consequently the insulation distance for imum insulating distance to ground.
tools and ladders used on dc systems will (2) To avoid shocks, the worker should bond to
be determined on the basis of permissible any conductive object being passed to him.
steady-state stress similar to the perma- ( 3 ) When returning to a metal structure from
nent insulation on the line: an insulating ladder or similar support
platform, the worker should drain t h e
5.4 Precautions when Working Energized Lines charge off his/h& body by first contacting
5.4.1 General Precautions the structure with a small metal tool or
Energized-line maintenance should not be object held tightly in his/her hand.
started when lightning is visible or thunder 5.4.4 Precautions when Working at Line
is audible at the work location. Potential
When possible, reclosing should be made (1) The worker should be insulated fro,m
inoperative whenever energized-line mair- ground or objects at a potential other than
tenance work is in progress on conductors. that of the device he/she is working on.
On distribution lines, the nature of the (2) The worker should be adequately shielded
work being performed usually determines from the electric field.
the action to be taken. ( 3 ) Bonding should be such that the worker is
All equipment should be inspected for at the potential of the device on which
defects before use. he/she is working.
Protective glasses or other face protection (4) All objects passed to the worker ought to
should be worn if the work requires it. be brought t o his/her potential before
The nominal voltage of the circuit should he/she touches them.
be checked before starting work to ensure (5) When working with bundled conductors,
that proper clearances are maintained. the worker should bear in mind that a
Care should be taken to maintain proper heavy fault current will slam the subcon-
clearances when using conductive mate- ductors together with violent force.
rial, including noninsulating ropes or slings, (6) When working in close proximity to other
in the vicinity of energized devices. conductors or objects, the worker should
When required to verify the insulating- cover these with protective cover-up equip-
clearance distance, insulating measuring ment or move them to avoid inadvertent
tools should be used. contact with other potentials or ground by
Insulating tools should be inspected for the worker or the equipment he/she is
indications of damage before and after using.
each job.
When a n energized conductor is being 5.5 Requirements when Working Energized
moved, checks should be made to avoid Lines
flashover contact with trees o r other 5.5.1 General Requirements
objects located in the adjacent spans. (1) Personnel doing energized line-work should
Persons not involved in the work operation have satisfactorily completed a formal
should be kept clear of the work site. training course of instruction and practice

36
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

for each applicable category of insulating of all grounded and energized parts in the
device to be used. Records should be main- vicinity of the proposed work. Safe clear-
tained that include training and work expe- ances for personnel and their supporting
rience in the categories of work he/she is insulating devices (considering movements
expected to perform. In addition, person- during the work) should be determined in
nel performing barehand work should be advance and strictly observed.
examined periodically to determine the 5.5.2 Requirements when Working at Ground
adequacy of the worker’s knowledge of Potential
rules and procedures, his ability to esti- When working from steel structures at volt-
mate clearance distances visually while in ages above 230 kV phase-to-phase, workers
elevated working positions, and his ability should be protected by conductive foot-
t o safely use t h e barehand technique, wear or shielding to avoid static shocks.
including the control and positioning of The condition of conductors, tie wires, and
supporting insulating devices. insulators should be carefully checked for
Whenever workers are exposed to electric signs of burns or other weaknesses. When
fields, shielding should be provided as such defects are found, extra special care
required. should be taken while doing the work.
A well-developed set of formal, written 5.5.3 Requirements when Working at Inter-
work rules should be provided for safe mediate Potential. The integrity of any insulat-
implementation of energized-line mainte- ing device used to support the worker should be
nance. All personnel should be familiar ensured.
with these rules. 5.5.4 Requirements when Working at Line
Procedures should be continuously exam- Potential
ined and updated to take advantage of new For work o n circuits energized above
equipment and work methods. 230 kV phase-to-phase, the worker should
Frequent, well-developed on-the-job or tail- wear conductive clothing.
gate discussions of the aspect of each Before beginning work, workers should
energized line-work program or job by the bond his/her conductive clothing to the
working personnel are necessary. Commu- energized device on which helshe is to
nication by all participants should con- work.
stantly be encouraged, both during the When the insulation clearance is decreased
discussions and during the progress of the below the minimum value indicated in
work program. Every effort should be made Tables 2 or 3, protective gaps should be
to provide logical, understandable answers installed, preferably at structures adjacent
or reasons for all questions, or both, and all to the work location on adjacent structures.
proposals should be readily received and 5.5.5 Requirements for Gloving
discussed, with immediate action initiated 5.5.5.1 General. Rubber and synthetic gloves
on any approved actions. A high degree of and sleeves are available for use on voltages
intra-crew discussion and participation through 36 kV. Few, if any utilities do not glove
d e m o n s t r a t e s a highly t r a i n e d , well- through 7.5 kV. Some do not glove above that level
adjusted, energized-line crew. but use live-line tools. All voltage references are
The leader of the crew should be present phase to phase.
for every job and should personally direct 5.5.5.2 General Requirements
all energized line-work. An awareness of (1) Rubber gloves (with or without sleeves)
the capabilities and the physical and men- should be worn before entering a hazard-
tal condition of each member of the crew is ous area and removed only after leaving
necessary. No crew member should be the hazardous area.
allowed to work during periods, either (2) Energized or neutral conductors, ground
temporary or sustained, when one is sus- wires, messengers, guy wires, etc, in prox-
pected to be in a physical or mental state imity should be covered with approved
that could contribute to an unsafe opera- protective equipment. This equipment
tion of the crew or equipment. The leader should be installed and removed from
of the crew should be responsible for seeing below, when practicable, and in Such a
t h a t detailed plans are worked out in manner and sequence as to provide maxi-
advance and for determining the location mum protection. Protective covering should

37
ANWIEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

be applied to the nearest and lowest con- 5.5.5.8 Working 26 500 V- 36 000 V
ductor first and removed in reverse order. (1) Insulated aerial lift equipment is univer-
(3) Special care is exercised when working in sally accepted as necessary for gloving at
proximity to fuses, lightning arrestors, etc. this voltage level. Sleeves are optional. Insu-
Procedures may require that fuses be lated basket liners are often used.
bypassed for the duration of the work. (2) Work in damp or foggy weather is restricted -
(4) Protective equipment is normally removed often limited by the boom leakage current
at the end of the work day. or the atmospheric humidity.
5.5.5.3 Field Inspection ( 3 ) Frequently, a combination of gloves and
(1) Rubber gloves and sleeves should be in- live-line tools is used because of construc-
spected at least daily, while in use, for tion, clearances, congestion, etc.
cracks, bruises, and other damage or (4) Lower voltage class gloves are not permit-
defects. Gloves should be given a roll and ted at the job site or are collected and
air test at the beginning of the work period stored a t a specific location before work as
and at any time their condition is suspect. this voltage is started.
(2) All other rubber protective equipment ( 5 ) The chassis of the aerial lift should be
should be given a visual inspection before grounded to the system neutral, if practi-
being used. cable, otherwise, to a temporary ground
5.5.5.4 Care and Storage source.
(1) Rubber gloves should never be stored or
worn inside out nor worn without glove 5.6 Insulating Equipment Used in Energized
protectors. Gloves should be stored in their Line-Work
natural shape. Sleeves and blankets should 5.6.1 Insulating Aerial Equipment. Any vehicle-
not be folded or creased. They should be mounted device that isolates the worker from
stored flat or in an approved roll-up. ground potential at the vehicle and lower boom
(2) All rubber protective equipment should be supporting structure and is used to position the
protected from mechanical damage and worker for contact with, or work on, energized
exposure to harmful chemicals, heat, ozone, lines and apparatus. This category covers aerial
oil, grease, etc. Harsh chemicals, oil, grease, ladders, articulating boom platforms, extensible
etc, should be removed as soon as practi- boom platforms, and vertical towers. The device
cable by wiping or by using a mild deter- should be rated and certified by the manufacturer.
gent. Thorough rinsing is important to 5.6.2 Insulating Ladder. A single or multiple-
prevent damage. section ladder used for personnel support during
5.5.5.5 Working 600V- 7500V. At this volt- energized line-work. This ladder may be structure-
age level, it is uncommon to use supplemental mounted, base-supported, or cable-supported by
insulation such as platforms or aerial lifts. With a crane or similar device.
the use of proper protective equipment (line hose, 5.6.3 Insulating Platform. An aerial device
blankets, etc), this voltage level is normally worked designed to elevate a platform in a vertical axis
directly off the supporting structure. either by means of insulating arms operating in a
5.5.5.6 Working 7500 V- 17 000 V. Usually scissors action or by means of an insulating tele-
some additional insulation is required such as scoping boom.
platforms, ladders, or insulated aerial lifts. Instal- 5.6.4 Insulating Tower Boom. An insulating
lation of line hose, blankets, and other protective tower boom is used in conjunction with support
equipment can be performed from the structure platforms such as a bosun’s chair, basket or
without additional insulation because contact with bucket, or tree trimmer’s saddle, to position the
the energized conductor is not necessary. Sleeves worker.
are sometimes used.
5.5.5.7 Working 17 000 V-26 500 V. The 5.7 NoninsulatingEquipment Used in Energized
same practices usually apply to this level as at the Line-Work
7500 V--17000 V level except that line hose, 5.7.1 Conductor Cart. A cart suspended from
blankets, etc, are installed with live-line tools or the conductor can be used as a work platform for
with the benefit of additional insulation such as operations, such as removing insulator strings or
platforms, and insulated lifts. Aerial lifts are often inspecting dampers, spacers, or the conductor
preferred at this level. itself.
ANWIEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

5.7.2 Helicopter. Helicopters can be used to excess of the manufacturer’s rating. To


lower and raise workers and tools to and from protect the fiberglass parts, none of the
structures carrying energized lines and to place parts of the bucket, platform, or upper arm
lineman in position for live contact. should be used as a fulcrum for prying or
lifting.
5.8 Insulating Devices Used in Energized Line- (7) The fiberglass material of which aerial lift
Work buckets are made should not be considered
5.8.1 Insulating Tools. Insulating tools made as providing any insulating properties.
of either wood or fiberglass-reinforced plastic are (8) Bond cables should use break-away clamps
used for work on energized devices while the or have a break-away section that allows
worker is at ground potential or at an interme- for separation from the energized conduc-
diate potential. tor in an emergency situation.
5.8.2 Insulating Rope. Insulating rope is used (9) When it is necessary to move from an aerial
in rigging support platforms for positioning per- device or ladder to a structure or to a con-
sonnel, controlling conductors, and raising or ductor, the worker must not be safetied off
lowering tools and equipment whenever work is to both devices at the same time.
being done on or in the vicinity of energized lines 5.9.1.2 General Requirements
or devices. It can be used alone or in series with (1) One person capable of operating the over-
an insulating pole. Insulating chain can be used in riding controls on the truck should be near
place of insulating rope when high humidity levels the aerial lift when workers are in the
are likely to be encountered. buckets or on the platform.
5.8.3 Protective Cover-up. Protective cover-up (2) Before workers are sent aloft, the insulat-
equipment is used at the lower voltages to insu- ing member of aerial lifts should be electri-
late energized lines and devices from the worker. cally tested by making contact with the line
to be worked on. This electrical check should
5.9 Methods for Positioning Personnel be made each time the aerial lift is relo-
5.9.1 Aerial Lift Equipment Performing Bare- cated. The maximum arm current should
hand Procedures not exceed 1 pA/kV phase-to-phase voltage.
5.9.1.1 General Precautions (3) Bond cables should remain firmly attached
(1) Before the boom of an aerial lift is elevated, to the energized device throughout the
t h e outriggers on t h e truck should be work operation.
extended, and if required, the aerial lift (4) Insulating members of aerial lifts should be
should be adequately grounded. kept clean and dry.
(2) The aerial lift should be operated to check 5.9.1.3 Minimum Clearance
that all controls are operating normally. (1) The clearance between any grounded part
(3) Workers should thoroughly clean the soles of t h e truck a n d t h e insulating boom
of conductive footwear before entering the assembly should not be less than those
bucket of an aerial lift device or mounting a specified in Tables 2 and 3. This includes
support platform. The floor of the equip- the clearance between live and grounded
ment should also be inspected for dirt or parts of the aerial lift device.
other material that might prevent good (2) The clearance between any part of a per-
contact between the floor and the conduc- son, a conducting tool, or a platform com-
tive footwear. bination not at earth potential and a live
(4) When working aloft, the worker should be conductor should not be less than the
secured to the aerial lift with his/her safety clearance given in Table 4 corresponding to
belt and both legs should be inside the a switching surge factor of fi.S for the
bucket or platform at all times, with one if appropriate voltage. Where this cannot be
not both feet on the bottom of the bucket achieved for any one conductor the clear-
or platform liner. ance between person, tool, or platform
(5) When an aerial lift is in contact with or combination to any other live conductor
near energized devices, workers on the that is at a different potential from the first
ground should avoid making contact with it. must be maintained. Where the two live
(6) The bucket or platform and upper insulat- conductors are on different circuits at dif-
ing boom should not be overstressed by ferent system voltages the clearance shall
attempting to llft or support weights in be calculated on the basis of voltage to be

39
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

withstood being the sum of the products of (4) The ladder should be checked electrically
the S and Vvalues, that is, the clearance each time the base is relocated when bare-
corresponds to hand work is being performed.
5.9.2.2.3 Minimum Clearance. A clearance
81 VILG s
+ 2 v2LG of 8 f t should be added to the mimimum insula-
5.9.2 Insulating Ladder tion distance indicated in Tables 2 and 3 to allow
5.9.2.1 Structure-Mounted Ladder for Bare- for the length of ladder occupied by the person. In
hand Work addition, allowance should be made for inadver-
5.9.2.1.1 General Precautions tant movement.
The end of the ladder should be firmly 5.9.2.3 Cable-Supported Ladder for Live
secured to the structure. Line-Work
The ladder should not be secured to a 5.9.2.3.1 General Precautions
defective component or to a device that The lifting device should be of adequate
will be taken apart or moved. capacity to handle the ladder load without
Before the worker mounts the ladder, the any risk of an operating deficiency.
leader of the crew should first assure him- It should be adequately supported and
self that all rigging has been checked. secured to ensure safe operation at all
5.9.2.1.2 General Requirements expected angles and positions.
Before a worker mounts t h e ladder, it The equipment should be closely inspected
should be tested electrically by making by the supervisor and operator following
contact with the line to be worked on to setup, and any noted or suspected defi-
check the dielectric current. ciencies should be corrected.
The ladder should be moved to a safe de- Insulating link sticks should be used
energized position prior to allowing the between the cable and the ladder when-
worker to mount or dismount. ever possible to facilitate the dielectric-
Controlling the movement of the ladder current testing and to improve the insulating
should be done with insulating tools, or quality of the setup.
nonconductive rope or chain, or both. 5.9.2.3.2 General Requirements
Except when mounting or dismounting from The equipment being used as the lift device
the ladder, the worker should maintain his should have both power raise and power
safety strap around the ladder. lowering facilities. Brake-type lowering
5.9.2.1.3 Minimum Clearance should not be used.
The minimum insulation distance specified When workers are on the ladder, all move-
in Tables 2 and 3, plus an additional dis- ments of the lifting device should be directed
tance for inadvertant movement, should be or controlled from aloft.
maintained between the worker and any One person capable of operating all con-
grounded part. trols should be near the lifting device when
5.9.2.2 Base-Supported Ladder for Live workers are on the ladder to warn other
Line-Work persons not to walk under the work area
5.9.2.2.1 General Precautions and to keep them clear from the lifting
The equipment being used as a fixed base device when the ladder is elevated.
support should provide a sturdy, safe prop Link sticks or ladders should be solidly at-
for the length of ladder and weight to be tached to the lifting cable; open-load hooks
supported. should not be used.
Personnel should stay clear of the ladder 5.9.2.3.3 Minimum Clearance. Noninsulat-
and base while the ladder is being moved ing portions of the equipment should not be
into position. closer to energized devices than the distances
5.9.2.2.2 General Requirements indicated in Tables 2 and 3. Depending on the
The equipment being used as a fixed base work location, additional distances may be speci-
support for the ladder should be grounded. fied by the person in charge to ensure that min-
Insulating sticks should be used to move imum distances are not violated.
the ladder to the energized device. 5.9.3 Insulating Platforms for Barehand Work
Before the worker mounts the ladder, the 5.9.3.1 General Precautions
dielectric-current value should be checked ( 1 ) Before the platform is elevated, the out-
when barehand work is being performed. riggers on the unit should be extended and

40
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

adjusted to stabilize and level the unit. imum phase-to-ground clearance from an
The body of the unit should be properly energized conductor.
grounded when required. Grounding through 5.9.4 Insulating Tower Boom for Live Line-
the outriggers is not sufficient. Work
Before moving the insulating platform into 5.9.4.1 General Precautions
the work position, all controls both a t (1) The tower boom should be erected a t an
ground level and on the support platform appropriate location on the structure to
should be checked. facilitate moving the worker or equipment
For scissors-type platforms with hydraulic to the desired location.
lines to the controls at the support plat- (2) The specific support platform to be used
form level, all arms supporting the plat- should be properly attached to the tower
form should be raised to their maximum boom and all component parts should have
height and left in the raised position for an adequate factor of safety for the load to
5 min. be carried.
Workers in the vicinity of a support plat- 5.9.4.2 Minimum Clearance
form, in contact with or near energized (1) The minimum insulation distance specified
lines, should avoid making contact with the in Tables 2 and 3 plus additional distance
support platform. for inadvertent movement should be main-
Bond cables should use break-away clamps t a j n e d between t h e worker a n d a n y
or have a break-away section that allows grounded part.
for separation from the energized conduc- (2) No portion of a person or tools should be
tor in an emergency situation. less than t h e minimum phase-to-phase
clearance from another energized conduc-
5.9.3.2 General Requirements
tor.
(1) One person capable of operating the over-
5.9.5 Conductor Cart
riding controls should be near the unit
5.9.5.1 General Precautions
when workers are on the support platform.
(1) A worker using a conductor cart should
(2) Before workers are sent aloft, the insulat-
not make contact with the cart during its
ing members of the platform should be
installation on the conductor until it is at
electrically tested by making contact with
the same potential as he/she is. This can be
the line to be worked on. When the dielec-
done either by allowing the cart to be
tric arm current is being measured, all base
pulled against the conductor to which the
arms of a scissors-type platform should be
worker is bonded or by the worker reach-
bonded together at the metering point.
ing out and hooking it with his bonding
(3) Bonding cables used to connect the plat-
wand.
form to the energized device should remain
(2) A nonconductive-rope tag line should be
firmly a t t a c h e d throughout t h e work
tied to the cart to control its motion during
operation.
hoisting.
(4) Insulating members of support platforms (3) After the trolley wheels are on the conduc-
should be clean.
tor, safety slings should be installed across
5.9.3.3 Minimum Clearance the wheel attachment to prevent the cart
The distance between the top of the insu- from dropping if a wheel should jump off
lating platform and grounded parts should the conductor.
not be less than those indicated in Tables 2 (4) When transferring from an insulating lad-
and 3. der to a cart attached to the conductor,
No portion of the insulating section of the the worker should make sure that his/her
equipment should be permitted to contact safety strap, which is fastened to the ladder,
a grounded part or a conductor having a and his/her conductive clothing bond are
different potential. of sufficient length to permit his/her trans-
No portion of a person, tool, or the plat- fer from the ladder to the cart.
form should be less than the minimum (5) When the cart is being mounted on bundled
phase-to-phase clearance from energized conductors, the rigid side of the cart sup-
conductors. port should be mounted on the conductor
No portion of the grounded section of the away from the worker on the insulating
equipment should be less than the min- ladder, and the hinged side of the cart

41
ANSI/IEEE
Std 516-1987 IEEE GUIDE FOR MAINTENANCE

I
support then mounted on the conductor This includes mobile work equipment, such as
near the worker. aerial lifts used as work platforms, radial boom
5.9.5.2 General Requirements derricks, aerial ladders, and live-line insulator
(1) Appropriate bonding and shielding should washing equipment. Step-and-touch potentials are
be observed. also considered.
(2) For carts propelled by internal-combustion
engines, care should be exercised in han- 6.3 Approach Distance
dling fuel. 6.3.1 Absolute Limit of Approach
5.9.5.3 Minimum Clearance (1) The absolute limit of approach is th,eshort-
(1) Care should be exercised during installa- est permissible distance between energized
tion of the cart on the conductor so that electrical apparatus and the position of the
the minimum distances indicated in Tables worker's body or tools and the materials
2 and 3 are not violated. he/she may be handling.
(2) The weight of the cart and the worker (2) The distances indicated in Table 4 do not
should be such that when installed on the allow for accidental or unplanned move-
conductor they do not alter the sag of the ments and should be used only to establish
conductor to the extent that they violate minimum distances. They must never be
the distances indicated in Tables 4 and 5. encroached upon unless protection is pro-
5.9.6 Helicopters vided in the form of approved protective
5.9.6.1 General Requirements. When per- devices.
forming barehand live-line techniques with a
6.3.2 Working Limit of Approach. The work-
helicopter:
ing limit of approach is the shortest permissible
(1) The pilot and the worker shall be checked
distance between live electrical apparatus and
out on the particular job to be done
the closest part of the worker's body or any con-
(2) All applicable work clearances shall be
ducting tool or material that he/she may be han-
discussed
(3) Constant communications between pilot
dling, taking into consideration an allowance for
inadvertent mouement. This distance could vary
and worker should be provided
(4) The pilot and worker should be dressed in depending on the work operation.
equivalent conductive clothing
(5) The pilot, in consultation with the worker, 6.4 Determination of Working Clearance
shall be responsible for all decisions regard- 6.4.1 General Precautions
ing safe flying conditions (1) The following factors are among those that
(6) A regulatory approved work platform shall should be considered when establishing the
be provided for the worker working clearance for a particular work
(7) Pull-away bonding clamps should be used operation:
(8) The worker shall be fastened to the helic- (a) The potential hazards of the work;
opter or work platform, or both, by an electrical, mechanical, or physical, or
approved safety harness and lanyard both
(b) The skills and knowledge of the worker
doing the work
6. Work in the Vicinity of (c) The possible use of protective cover-
Energized Lines and Devices up equipment
(d) The fact that the live equipment may
6.1 Introduction. This section concerns itself with be the energized conductor or device
suggesting ways to provide protection for workers itself, any hardware attached to it, any
during energized-line maintenance or while work- conducting tool or material touching
ing in the vicinity of other energized lines. it, or the metal component at the end
of an energized-line tool.
6.2 Scope. This section determines the minimum (2) Extreme care shall be taken to ensure the
safe working clearances for grounded bodies or safety of all workers.
equipment operating and moving in the vicinity of (3) When conductive shoes or boots are worn
energized lines or energized components, or both, while working in the vicinity of switchgear,
in station yards while performing work on ener- circuit breakers, intrument transformers,
gized circuits or devices. and arresters to eliminate the annoying

42
ANSI/IEEE
METHODS ON ENERGIZED POWER-LINES Std 516-1987

although harmless discharging of the body 100 7

capacitive charge to the grounded struc- 90 ..


tures, extreme care should be taken by the g
worker not to make contact with a source
of low-voltage potential.
6.4.2 General Requirements
(1) The working clearance should be obtained
by adding to the distances indicated in
Table 2 a distance to cover accidental or
unplanned movement of the worker’s body
or tools and material he/she may be
handling.
(2) At no time should the distance between a
grounded body or tool be less than the dis-
tances shown in Table 2.
(3) Conductive clothing should be worn by 2 4 6 8 10 12 14 16

workers at ground level and on any DISTANCE FROM ROD ( f t )


grounded structure of an extra-high-voltage
(ehv) switchyard or transformer station
Fig 8
whenever field strengths are sufficient to
require them. Typical Voltage-Gradient Distribution Curve

6.5 Step and Touch Potentials


6.5.1 Introduction. When a ground fault

4
occurs on a transmission line, the potential rise of TOUCH
the transmission-linetower with respect to ground
may present a hazard through excessive touch or
step potentials. The degree of the hazard depends
upon the magnitude of the fault current and the
time of exposure. While the probability of a line-
to-ground fault has increased only very little in
recent years, the magnitude of fault current has
in many cases increased appreciably with the
result that the hazard from step and touch poten-
tials should no longer be considered as negligible.
6.5.2 Voltage-Gradient Distribution
(1) The dissipation of the voltage or voltage Fig 9
drop from the ground electrode is called Step and Touch Potential
the ground potential gradient or simply the
voltage gradient. The voltage drops are
known as ground potentials.
Figure 8 is a typical voltage-gradient dis- 6.5.3 Protection of the Worker from Ground
tribution curve and shows that the voltage Potential Gradients
decreases rapidly with the distance from (1) The use of a metal mat connected to the
the electrode and that most of the voltage electrode will protect a worker standing on
is concentrated near the electrode. The it from any step or touch potential. How-
graph assumes soil of uniform texture. ever, if the worker is standing with one foot
(2) Step and touch potentials are illustrated in on the conducting mat and one foot on the
Fig 9. ground, he/she will be exposed to a step
Transferred voltages may occur on any potential, at least equivalent to the touch
metal component connected to station potential, as illustrated in Fig 10.
grounds in the event of a fault to ground, (2) Workers on the ground should minimize
including station fences, cable sheaths, their contact with structures in the per-
pipes, and rails. formance of the work operation.

43
ANWIEEE
Std 516-1987

6.6.2 General Requirements


(1) If it becomes necessary to make contact
STEP /i -' with attachments or load during minor
controlled adjustments of the boom or
winch so as to connect, disconnect, or align
the attachment or load, care should be
taken to make sure that safe methods for
controlling loads are employed. In addition
(a) Appropriate safe working clearances
must exist between the boom, attach-
ments and load, and the energized
conductors or devices.
(b) The minor controlled adjustments of
the boom or winch must not encroach
Fig 10 on the appropriate, safe workmg clear-
Protection of the Worker from ance, and the boom, attachments, and
Ground-PotentialGradients load must be protected from the ener-
gized conductors or devices.
(2) When it is necessary to operate the con-
trols at ground or vehicle level, the opera-
tor should protect himseWherselfby one of
the following methods:
6.6 Vehicles in the Vicinity of Energized Lines (a) By standing on an operator's metal
and Devices platform installed for this specific
6.6.1 General Precautions purpose
(1) Vehicles equipped with any type of aerial (b) By standing on the deck of the vehicle
equipment working in the vicinity of ener- (c) By standing on a portable conductive
gized conductors or apparatus should be mat electrically attached to the vehicle
grounded or isolated. (d) By standing on an insulated platform
(2) Persons standing on the ground should not 6.6.4 Insulator Cleaning. Cleaning contami-
be in contact with a vehicle while the boom nated insulators on energized lines can be done by
or aerial device is being moved in the vicin- using various methods [30]. See IEEE Std
ity of energized conductors or apparatus. 957-1987 [29].

44

You might also like