PRINCIPAL OF OPERATION
Power is fed from the TSS at 50 kV and utilization is achieved at 25 kV by
providing Auto-Transformers of adequate capacity and by providing one
additional conductor feeder Wire. Provides +25 kV Voltage between OHE
and rail and -25 kV voltage between Rail/earth and the Feeder Wire.Spacing
& capacity of the AT’s depends upon system design capacity requirements
and tolerable limits of the inductive interference levels and normally varies
from 10 to 15 kms interval , The traction load is shared by both the adjacent
ATs in inverse proportion of respective distances i.e. the AT nearer to the
Locomotive will share more load than the other one.
TRACTION SUB-STATIONS
TSS WITH SCOTT CONNECTED TRANSFORMERS
Two numbers Scott connected transformers are installed, one of them
working as standby. The primary windings of the Scott connected
transformer are connected to three phases of the incoming 220/132 kV
transmission net work through the triple pole circuit breakers and isolators.
Three phase supply is received through duplicate bays. There are two
secondary windings in each of the Scott connected transformers referred as
Main(M) and Teaser(T) winding , each consisting of two winding.
Corresponding one outer terminal of each M & T winding of the two
transformers is terminated on common M and T buses connected to the
catenary and the other outer terminal terminated on other common bus
connected to the feeder The two inner terminals of M & T windings of each
transformer are connected to each other , which is solidly earthed and
connected to traction rails. As M & T voltages are 90 degree phase apart,
one side of TSS is fed from the M phase while other side from the T phase
with a neutral section provided in the OHE and Feeder. Due to two buses
structure, circuit breakers, interruptors and isolators on 2x25 kV side are
double poles are provided
This is another 2x25 kV TSS, with lesser loads. In this arrangement, 3 single-
phase transformers are connected to different pairs of 3 phases forming on
open delta connection on the primary side. Out of the 3 single-phase
transformers, one transformer feeds the OHE on one side of the TSS;
another transformer feeds the OHE on the other side of TSS and the third
remains as standby.
AUTO-TRANSFORMER
SECTIONING POST(SP)
At the SP, there are two bridging circuit breakers in a double line section
and two paralleling interruptors, one each on either side of dead zone. Four
auto transformers, two each on either side of the dead zone connected to
up & down lines are also installed at the SP.
Harmonic: Since the fault levels are much higher on the 25 kV & 220
/132Kv side, there are less harmonics on the system.