P1
Procedure Site Inspection Plot No. 676-1061
Policy Health, Safety, and Environment Inspection report No. 10
Page 1 of 3
Observations:
Found Tele handler operation without
flagman
1. Tele handler operation without flagman
and while turning bucket goes on top of
nearby road.
2. Movement without flagman can result in
maneuvering and property damage. 27/10/2023
Need immediate
Action required: Ensure immediate
action close out
02 corrective actions are required as per HSE
evidence you can
Standards and legal requirements. submit till
mentioned date.
References
1. The Federal law No (8) Year 1980.
2. Ministerial Order No (32) Year 1982.
3. DMCOP, 2008 chapters–3 & 20
4. DDA HSE requirements.
6. DAMAC HSE requirements.
Page 2 of 3
Observations:
Generator roof with combustible material
1. Generator roofing provided with
wooden planks and exhausted smoke
directly hit on combustible material.
This can result in fire and explosion.
2. Ensure all combustible materials area
away from the Generator and fuel. 27/10/2023
Need immediate
Action required: Ensure immediate action close out
03
corrective action as per HSE standards and evidence you can
legal requirements. submit till
References mentioned date.
1. DMCOP, Chapters – 05.
2. UAE Fire & Life Safety Code.
3. Ministerial Order No. (32) For the year
1982.
4. UAE federal laws and regulations -
5. DDA HSE requirements.
6. Damac HSE Requirements.
Report Prepared
Mr. Anish Aravind Position: HSE Engineer
by: Date:
Report Issued to:
Mr. Ziad Ahmad Shehadi Position: Project Manager
Received by: Date:
Closeout actions
Position: Date:
by:
Page 3 of 3