HSE-10 - HSE Site Observation Report

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

HEALTH, SAFETY, & ENVIRONMENT SITE OBSERVATION REPORT Procedure No.

P1
Procedure Site Inspection Plot No. 676-1061
Policy Health, Safety, and Environment Inspection report No. 10

Location: Dubai, UAE Date of Inspection: 23-10-2023


Project Name: 327 Villas at‘’Damac Hills’’
Responsible person Follow-up of the Required date
Item
Comments Photos (M/s. DECC) for closeout action by for action
No.
closeout & Action A&B closeout
Observations:
Smoking inside site close to Villa

1. Found three operatives of M/S. Prestige


smoking inside site premises which is
too close to Villa, any fire occurred in
site can result in property damage and
fatality.
2. Operatives not using mandatory
27/10/2023
personal protective equipment’s.
Need immediate
Action required: Ensure immediate action close out
01
corrective action as per HSE standards and evidence you can
submit till
legal requirements.
mentioned date.
References
1) UAE Fire & Life Safety Code of
Practice.
2) DMCOP, Chapters – 3 & 5.
3) Ministerial Order No. (32) For the year
1982.
4) UAE federal 24 0f 1999
5) DDA HSE requirements.
6) Damac HSE Requirements.

Page 1 of 3
Observations:
Found Tele handler operation without
flagman
1. Tele handler operation without flagman
and while turning bucket goes on top of
nearby road.
2. Movement without flagman can result in
maneuvering and property damage. 27/10/2023
Need immediate
Action required: Ensure immediate
action close out
02 corrective actions are required as per HSE
evidence you can
Standards and legal requirements. submit till
mentioned date.
References
1. The Federal law No (8) Year 1980.
2. Ministerial Order No (32) Year 1982.
3. DMCOP, 2008 chapters–3 & 20
4. DDA HSE requirements.
6. DAMAC HSE requirements.

Page 2 of 3
Observations:
Generator roof with combustible material
1. Generator roofing provided with
wooden planks and exhausted smoke
directly hit on combustible material.
This can result in fire and explosion.
2. Ensure all combustible materials area
away from the Generator and fuel. 27/10/2023
Need immediate
Action required: Ensure immediate action close out
03
corrective action as per HSE standards and evidence you can
legal requirements. submit till
References mentioned date.
1. DMCOP, Chapters – 05.
2. UAE Fire & Life Safety Code.
3. Ministerial Order No. (32) For the year
1982.
4. UAE federal laws and regulations -
5. DDA HSE requirements.
6. Damac HSE Requirements.

Report Prepared
Mr. Anish Aravind Position: HSE Engineer
by: Date:
Report Issued to:
Mr. Ziad Ahmad Shehadi Position: Project Manager
Received by: Date:
Closeout actions
Position: Date:
by:

Page 3 of 3