DPR Mechanical 19-12-23
DPR Mechanical 19-12-23
Directed
Area / PM / and
S.No Tag# Activities Performed Status Job Performed By Start Time End Time PTW # Remarks
Location CM Instructed
By
1 Oxidation G-21 Testing of New G-21 Impeller Completed Touseef+Najam 9:00 AM 1:00 PM
In-progress
2 Oxidation - Pre-fabrication of Cooling water line Rizwan+Afzal 9:00 AM 5:00 PM
(30% Done)
3 Distillation C-31 Incinerator inlet duct body pinhole leakage Completed Arshad+Muhammad Khan 9:00 AM 1:00 PM
4 Distillation - Maintenance of Steam Traps (10 done today) Complete Shahid+Irshad 9:00 AM 5:00 PM
5 Utility - Daily Condition Monitoring Instrument Air Compressor Completed Najam 9:00 AM 10:00 AM
7 Plant Site - House Keeping at Plant Site Completed Shehzad 9:00 AM 5:00 PM
In-progress Adnan
8 Plant Site - Refilling of Digged hole against leakage of HDPE Fire Fighting Line Outsource Labor (1 person) 9:00 AM 5:00 PM
(75% Done) Mushtaq
Achievements
Problems/Challenges
Skill Devolopment/Trainings