Project: Construction of 4-Lane Access Controlled Greenfield Highway section on NH-163G

(Khammam–Vijayawada) from V. Venkatayapalem village at Design Ch. 220.480 Km to


Brahmanapalli(K) village at Design Ch. 250.400 Km (total length 29.920 Km) under other
Economic Corridor (NH(O)) programme on Hybrid Annuity Mode in the State of
Telangana (Package-I)

 Type of Pavement: Flexible (Bituminous)


 Total length of CW: 29.92 Kms
 Total Asphalt Material: 64,000 Cum
 Earthwork (excavation & filling qty): 35,00,000 Cum
 Length of Major bridges/ viaducts: 0.761 Kms
 Piling (if any) dia/number/ Running Mtr: 114 Nos.
 RE wall/ Retaining wall: 2,02,241 Sqm
 Any other critical/ major feature: 2 MJB Steel Girders structure (90m span each).
 Major Challenges: