HAI LSHAM ROADWAY
EPUBLIC WORKS CONTRACTORS ——_ WOODSIDE DEPOT Tet 01323 saseze
@ SURFACING CONTRACTORS POLEGATE ROAD Fax 01323 e49408
HAILSHAM CONCRETE SUPPLIES 01323 441229
@ SMALL WORKS oIVisioN fast sussex wane pak
(GCONCRETE SUPPLIES N27 3PG ‘Webaite wer hatshameondays Souk
METHOD STATEMENT
& RISK ASSESMENT
ROBERTSBRIDGE COMMUNITY COLLEGE
PROJECT NUMBER ~ G14/46395
PROJECT MANAGER - Geoff FieldRISK ASSESSMENT & METHOD STATEMENT
Job Number G14/46395 21/7/2014
Contract’ Robertsbridge Community College, Knelle Road, Robertsbridge,
Site name N32 5EA.
Site Location
Work/Tasks to be
ortionie Construction of New Parking Bays & Concrete Hardstanding
(07753-850726
Contractors , Contact Mobile | geotf@hailshamroadways.co.
Project Manager | °° Field E.mail uk
Robertsbridge Community College
Knelle Road, Robertsbridge, TN32 5EA.
Contact Mobile
Contact Details | Tony Hougham rail ahougham @robertsbridge.org.uk
Dates/times the work will be carried out :~
Start Date 28/7/2014
Duration of works | 10 Days
Normal Working
oaral Between 8.00am - 6.00pm
Page 2 of 19RISK ASSESSMENTS
2) Generic Risk Assessments,
RISK ASSESSMENT & METHOD STATEMENT
Site Specitic Operations
~ See Appendix D
‘Whats he Rey] —WhatietraHaard | Whois atraak | Hazard] Prob | WSK | What Conor Wessures | Resaun | Restual | Residu
ect | Tea Neodtobe putinPusce | azard | "Prob | alse
ues | '@ tes | 3
a axe) ‘@ | ‘elo
Denne acne Tips aa ae Ta errs ocaaig ies | TF
pe a
Tiaingihe wana ern | TipsendTats | Wonbosaitapasis [2 | 2 | 7 | Erewoamreare pce | = TT
Deira as Ties Ta pares a T=
piace eet
a Tae Ta Enae raraT = TF
oo ‘scan te tend
Proanage a oa
Tanager | — Saar Ta 3 toga so] TF
SETA A Rak Rasa Tos GRAY
Ta ot Rasoaaar | — Bate oT anaes ie Fara ‘Operas Gieat oer
Geol Field BarriBoTs Foreman Bee attached lst5
[Nearmiss
PROBABILITY
Very likely to occur
Likely to occur
Unlikely to occur
RISK RATING SYSTEM
Find alternative method; if necessary involving CDM Coordinator and
Design Team.
If possible use alternative method. If not, implement further control
Measures Method Statement sections below must be completed.
Control measures needed.
No further action needed.
CMa edRISK ASSESSMENT & METHOD STATEMENT
COSHH assessment
Is a COSHH assessment required?
‘Summary of details below:-
‘Type of materials
[Manufacturer
‘Attached COSHH Sheet
Coated macadam
Tarmac
See Appendix 8
Bitumen Tack Coat
Colas
See Appendix B
Permit to work requi
ired?:~
Permit type:
Location on site Details when used
Hot Works
Confined space
‘Access
Planning only
Work on or near
electrical equipment
Additional Details
Page 5 of 19RISK ASSESSMENT & METHOD STATEMENT
Detail any personal protective equipment required (PPE):
PPE item INo| Type Details when used -
‘Safety Footwear Steel toecap with mid sole Alltimes on site
protection safety boots
Head Protection ‘Only helmets to BS 5240 or EN | Setety helmets will be worn by all our operatives at
397 less than 3 years old will be | all times, in specified locations
worn,
Hi-Vis Clothing Class ‘Al all times on site
Gloves, include Teather At all times on site
type
Weather Water Resistant When necessary
Protection
Eye Protection Glasses Atal times on site
Ear Protection Full ear defender When operating machinery
Full body safety | No
hares
Respiratory | No
Protection
FFP FFP2
Detail any safety equipment that will be required:-
Page 6 of 19RISK ASSESSMENT & METHOD STATEMENT
Noise assessment Is anoise assessment required? _| Yes | No
Full details below:
Type of Name of __] dB (A) ‘Area of use: _| Ear protection requirements and type:
machine machine | max. at
source
‘Compressor | Allas Copco 35 inthe open air Ear Defenders
Tandem vs | BOWAG co Tn the open ar | Ear defenders
roller
Spin Cutter | Stn co inthe open air_| Ear Defenders
Vibrating plate | WACKER co inthe open ar | Ear Defenders
Paving Machine | Marini co inthe open air Ear Defenders
Vibration assessment Is a vibration assessment required?
Full details below:
Type of Name of __] Vibration level] Exposure limit and control measure
machine machine m/sec?
‘Compressor | Allas Copco tba “45minutes per person
Vibrating plate | WACKER tba “45minutes per person
Manual handling assessment
Full details of all items over 20 kgs as
Materia’ | Weight | Amount | Dimensions | Control measure
equipment
‘Additional Detai
No items in excess of 20kg to be lifted by individual operatives
Page 7 of 19RISK ASSESSMENT & METHOD STATEMENT
‘sequence of work ops
indix A for relevant drawit
‘SITE INDUCTION Ensure that a site induction is carried out with alll site personnel
prior to the works commencing
To ensure that all works are carried out in accordance with the
requirements of the attached risk assessments
Ensure that all risk assessments have been discussed and that
emergency and fire procedures are in place
Ensure that all site personnel are familiar with the safe use of
plant to be used
Ensure that site plant has been appropriately maintained and is fit
for use
GENERAL SITE Before commencement of works, ensure that the site is ‘walked’
APPRAISEL by the operatives to familiarise themselves with its terrain
Remove any obvious hazards and the like.
Carry out visual check for both overhead and underground
services
Cable Avoidance Tool is to be used prior to works to establish
locations of underground services
Check for lose and damaged branches and remove as required
Check ground conditions are suitable for safe working
THE WORKS Parking Bays Away From Tree Roots
To excavate area 290mm below required finish levels and dispose of all
arisings on site. To supply and lay new 255 x 125mm HB kerbs on
concrete bed and haunch. To supply and fit 2 no. new 900 x 450mm,
diameter plastic road gullies with 425 x 425mm cast iron gratings. To
connect to existing drainage with 10mm diameter plastic pipe. To
supply and lay 200mm depth of granular sub-base, 60mm depth of AC
20 dense binder 100/150 asphalt and 30mm depth of AC 10 close
surface 100/150 asphalt consolidated.
Parking Bays Above Tree Roots
To carefully excavate BY HAND DIGGING existing turf to an
approximate depth of 50mm and dispose of all arisings. To exacavate for
new kerbing BY HAND DIGGING and dispose of all arisings. To
supply and lay new 2600mmx120mmx200mm railway sleepers and
secure with new 600mmx50mmx50mm wooden pegs. To supply and
lay 200mm depth of Type 3 granular sub-base, 60mm depth of AC 20
open binder 100/150 asphalt and 30mm depth of AC 10 open surface
100/150 asphalt consolidated
Footpath Above Tree Roots
To carefully excavate BY HAND DIGGING existing turf to an
approximate depth of 50mm and dispose of all arisings on site. To
excavate for new kerbing BY HAND DIGGING and dispose of all
arisings on site. To supply and lay new 150x25mm tanalised timber
Page 8 of 19RISK ASSESSMENT & METHOD STATEMENT
‘edging board and secure with 600mmxS0mmx50mm wooden pegs. To
supply and lay 150mm depth of Type 3 granular sub-base, 45mm depth
of AC 20 open binder 100/150 asphalt and 20mm depth of AC 6 open
surface 100/150 asphalt consolidated.
Bike Shelter Base
NO EXCAVATION TO BE CARRIED OUT. To supply and lay
100mm depth of granular sub-base. To supply and fit shuttering. To
supply and lay polythene membrane, a single layer of A142 reinforcing
mesh and 150mm depth of C30 concrete.
7.2.1 To avoid damage to tree roots, existing ground levels should be retained
within the RPA. Intrusion into soll (other than for piling) within the RPA is,
generally not acceptable, and topsoil within it should be retained in situ.
However, limited manual excavation within the RPA might be acceptable,
Subject to justfication. Such excavation should be undertaken carefully, using
hand-held tools and preferably by compressed air soil displacement.
NOTE Due to the demands that manual excavation places on a development
project, and limitations arising from health and safety considerations, itis not
realistic to plan for excavation using hand-held tools where there is @ need for
trench shoring or grading the sides of the excavation to a stable angle of repose.
7.2.2 Roots, whilst exposed, should immediately be wrapped or covered to
prevent desiccation and to protect them from rapid temperature changes. Any
wrapping should be removed prior to backfiling, which should take place as
s00n as possible.
7.2.3 Roots smaller than 25 mm diameter may be pruned back, making a clean
ccut with a suitable sharp tool (e.g. bypass secateurs or handsaw), except
where
they occur in clumps. Roots occurring in clumps or of 25 mm diameter and
over
should be severed only following consultation with an arboriculturist, as such
roots might be essential to the tree’s health and stability.
7.2.4 Prior to backfilling, retained roots should be surrounded with topsoil or
‘encompassed sharp sand (builders’ sand should not be used because of its
high
salt content, which is toxic to tree roots), or other loose inert granular fill,
before soil or other suitable material is replaced. This material should be free of
contaminants and other foreign objects potentially injurious to tree roots.
Page 9 of 19RISK ASSESSMENT & METHOD STATEMENT
Resources
Number of operatives anticipated to be
on site to carry out the work safely:-
Plant, equipment to be used
Inspection/certification requirements ~ See appendix C
Van
Tandem roller
Wacker plate
3T Excavator
3T Dumper
16T Grab Lorry
Materials to be used
255mm x 125mm HB Kerbs
150mm x 50mm BN Kerbs
€20 Concrete
Type 1 Granular Sub Base
Type 3 Granular Sub Base
AC 20 dense binder 100/150
AC 20 OPEN binder 100/150
AC 10 close surface 100/150
AC 10 OPEN surface 100/150
Page 10 of 19RISK ASSESSMENT & METHOD STATEMENT
Details of access and egress to work areas:-
All access to site to be gained from KnelleRoad.
‘Arrangements for delivery, stacking, storing and movement on site of planv/
materials:-
Delivery
Materials delivered and retained on trucks until required
Stacking & Storage
Stored on delivery vehicles
Movement of plant/Materials
On specified Haul routes and
Under supervision of a banksman
Protection needed for any site visitors:-
Yes_| No
‘Other employees: Client Personnel
Hi
PPE Required
Hi Vis. Hi Vis. Hi Vis.
Hard Hat Hard Hat Hard Hat
Ear Defenders. Ear Defenders Ear Defenders
Gloves Gloves Gloves
Safety Glasses Safety Glasses Safety Glasses
Safety Boots Safety Boots Safety Boots
Dust Masks
Dust Masks Dust Masks
Page 11 of 19RISK ASSESSMENT & METHOD STATEMENT
Signage: Ts site specific signage required?
Full details below:
Information —
Detail of work at height None X
‘Specific detailed description of safe working at heights/prevention of falls:-
Hierarchy for managing and selecting equipment for work at height.
ment __| Details of use, also give reasons
Equipment Tobe | aya [Not | why equipment is not used.
used Suitable
7 | MEWPS x
Scissor lifts, cherry pickers
ete.
2_ | Scaffolding/ Fixed Guardrails x
3. | Stepladders x
@_| Ladders x
5 | Safety Hamess /Safety x
Lines.
Detail of work at depths not exceeding 5m None X
‘Specific detailed description of safe working at depths not exceeding 5m:-
Hierarchy for managing and selecting equipment for work at depth.
‘Selected Equipment Details of use, also give reasons
Equipment Tobe] nya | NOt why equipment is not used.
used Suitable
Safety Hamess / Safely x
Lines.
Gas Detection x
Ladders
Page 12 of 19RISK ASSESSMENT & METHOD STATEMENT
Environmental controls details
Ensure that any fauna and natural wildlife is not unnecessarily disturbed by the works
Description of clearance of waste from site including waste transfer procedures:-
Excavated materials to be loaded on to tipper and taken to a licenced waste facility
Site Welfare
Toilet and hand washing facility are available on site
Description of emergency/rescue and fire procedures.
Ensure that any formal Fire Procedures explained at site induction are adhered to-
For out of hours emergency contact:-
First name Surname Contact Number.
Geoff Field (07753-850726
Who will be the on-site First Aider:-
First name Surname Training course/date
Nick Honeysett duly 2013
Page 13 of 19RISK ASSESSMENT & METHOD STATEMENT
Nearest Accident and Emergency Hospital
‘CONQUEST HOSPITAL
‘The Ridge, St Leonards on Sea, Hastings, TN37 7RD.
01424-755255
‘Competent person/supervisionfraining/procedures:-
Duties of supervisor/foreman (name if known at this stage)
To act as Company Foreman/representative to carry out works as instructed and
specified
‘Surname Training/ level of competence
Honeysett Foreman
Name and contact details of Health and Safety Officer/Manager or Consultant
(Must include qualifications/ membership of professional H&S body)
Name Contact details Qualifications/membership
of professional H&S body
Bryan Sheldon 0845-2268393 MIOSH, MIIRSM
Page 14 of 19RISK ASSESSMENT & METHOD STATEMENT
Names of all operatives involved in this operation:-
NB. To be completed by all operatives involved in the works after Site
Supervisor has explained the contents.
First Name Surname Job title Signature Date
Nick Honeysett Foreman 21/7/2014
David Dann Skilled Operative 21/7/2014
Dave Seymour Skilled Operative 21/7/2014
Name of competent person/s who prepared this method statement:-
Name Job title Signature Date
Geoff Field Managing 15/7/2014
Director
Page 15 of 19RISK ASSESSMENT & METHOD STATEMENT
APPENDIX A
Site Drawings
Technical Information
Page 16 of 19RISK ASSESSMENT & METHOD STATEMENT
APPENDIX B
COSHH Details — (Carried in Foreman Pack)
Page 17 of 19RISK ASSESSMENT & METHOD STATEMENT
APPENDIX C
Plant Inspection / Certification
Page 18 of 19RISK ASSESSMENT & METHOD STATEMENT
APPENDIX D
Generic Risk Assessments — (Carried in Foreman
Pack)
Page 19 of 19