The material report summarizes excavation and construction quantities for a road project along Seneca Drive between stations 23+000 to 23+965.988. It lists the area, incremental volume, and cumulative volume for different material types including ground removal, ground fill, highway layers, base, subbase, curb, and sidewalk at 20 station intervals along the alignment. The total ground removal volume was 634.11 cubic meters and the total ground fill volume placed was 6490.37 cubic meters.
The material report summarizes excavation and construction quantities for a road project along Seneca Drive between stations 23+000 to 23+965.988. It lists the area, incremental volume, and cumulative volume for different material types including ground removal, ground fill, highway layers, base, subbase, curb, and sidewalk at 20 station intervals along the alignment. The total ground removal volume was 634.11 cubic meters and the total ground fill volume placed was 6490.37 cubic meters.
The material report summarizes excavation and construction quantities for a road project along Seneca Drive between stations 23+000 to 23+965.988. It lists the area, incremental volume, and cumulative volume for different material types including ground removal, ground fill, highway layers, base, subbase, curb, and sidewalk at 20 station intervals along the alignment. The total ground removal volume was 634.11 cubic meters and the total ground fill volume placed was 6490.37 cubic meters.
The material report summarizes excavation and construction quantities for a road project along Seneca Drive between stations 23+000 to 23+965.988. It lists the area, incremental volume, and cumulative volume for different material types including ground removal, ground fill, highway layers, base, subbase, curb, and sidewalk at 20 station intervals along the alignment. The total ground removal volume was 634.11 cubic meters and the total ground fill volume placed was 6490.37 cubic meters.