SUPPLY SALES
PROCESS
(ZDPC TYPE) NON PGI

SAMADHAN VIDE
VIKRAN ENGINEERING & EXIM PVT LTD
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Contents
SUPPLY SALES PROCESS.................................................................................................................................... 0
1) INTRODUCTION ................................................................................................................................................. 2
2) CREATE SALE ORDER (SO- SUPPLY TYPE – ZDOR)...................................................................................... 3
3) Error analysis................................................................................................................................................... 11
4) BILLING.................................................................................................................................................................... 18

Figure 1 Sale order creation screen .................................................................................................................................. 3


Figure 2 Copy from screen ................................................................................................................................................ 4
Figure 3 Item selection screen .......................................................................................................................................... 5
Figure 4 Mandatory filed screen ....................................................................................................................................... 6
Figure 5 Check Tax Screen................................................................................................................................................. 7
Figure 6 Update Tax Screen .............................................................................................................................................. 7
Figure 7 Incompletion log check screen............................................................................................................................ 9
Figure 10 error - quantity already consumed ................................................................................................................. 11
Figure 11 Copy control not defined ................................................................................................................................ 13
Figure 12 error - check distribution channel................................................................................................................... 15
Figure 13 validity of contract for information ................................................................................................................ 16

Page 1 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

1) INTRODUCTION

The sales order is a contractual agreement between a sales organization and a


sold-to party about delivering products or providing a service for defined prices, quantities
and times. In sales order processing, the system implements various functions:

Pre-requisite
For creating sales order following points user need to ensure:
1) Contract is uploaded
2) HSN Code is applied to an Item
3) Sold-to-party, Shift-to-party, Bill-to-party & Payer Addressee are updated
4) Child items and their quantities are available in store.

This Document will help user to understand the supply billing where there is No PGI. In
this type of SO only ZTAQ item categories will be allowed. Other than ZTAQ Categories will not
be copied in the SO.

Page 2 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

2) CREATE SALE ORDER (SO- SUPPLY TYPE – ZDOR)


T-Code: VA01
Follow the steps
Enter Oder Type > Distribution Channel > Division & Click on Create with Reference.

Figure 1 Sale order creation screen

In the above screenshot we have given example of PD Business. However, if user wants to
create SO for different business channels change distribution channels as per bellow table
DISTRIBUTION CHANNEL NUMBER DISTRIBUTION CHANNEL BUSINESS NAME
10 Power Distribution Business

20 EHV Business

30 Railway Business
40 Water Business

Page 3 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

After click on Create with Ref. then click on Contract and Enter the Contract & Select
item selection.

Figure 2 Copy from screen

Page 4 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Select All Item > Enter Quantity > And Copy

Figure 3 Item selection screen

Enter Customer Reference > Cust. Ref. Date and Click on Header.

Page 5 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Figure 4 Mandatory filed screen

Page 6 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Please check tax is applied or not. If applied, no need to update.

Figure 5 Check Tax Screen

If tax not applied then refer screen shot 2 for update tax.

Figure 6 Update Tax Screen

Page 7 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Select G for tax

Page 8 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Figure 7 Incompletion log check screen

Page 9 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Click on save

Page 10 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

3) Error analysis
There are 3 no. of error which can be seen while creating the sales order for ZDOR type.

1) The reference has already been completely copied or rejected


This error refers to the quantity is already being consume this reference to the subject contacts
to remove this error user needs to update the contract.

Figure 8 error - quantity already consumed

Page 11 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

2) Error have occurred.


Enter Cust. Reference & Date for seen this error.
in this error the item categories are not allowed for sale document type ZDOR.

Page 12 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Figure 9 Copy control not defined

Page 13 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

• The reference is incomplete

Page 14 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

3) Distribution channels deviate from each other. 10 and/or 20 (reference)


In the below screen distribution channel & Reference document are not same.

Figure 10 error - check distribution channel

Page 15 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Figure 11 validity of contract for information

Page 16 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Page 17 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

4) BILLING
T-Code: VF01

Page 18 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

CLICK ON ENTER

Page 19 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

Page 20 of 21
PROJECT EVOLVE
SAP S/4 HANA SD VIK_SAP_SD_SO_02
VER - 00
SUPPLY SALES PROCESS
DATE – 25/2/2023
VIKRAN ENGINEERING & EXIM PVT LTD (ZDPC Non PGI)

CHECK AMOUNT & TAX

Page 21 of 21