QUOTATION

No-(146) , Sapel myaing 2street , 17 Quarter ,South Dagon Township ,Yangon ,Myanmar .
PH: 09975566253 , 09699985458, 09420008504
Jade.engineering@yahoo.com

Attention - NORSTAR
Project - Junction City Office Tower
REF - Office Expansion Date : 23/Jan/2024

Thank you for your invitation to quote for the project. We are pleased to submit herewith our quotation for the above mentioned
project for kind perusal and consideration.

S/NO Unit Price for Application of NORSTAR Office Expansion at JUNCTION Quantity Price
OFFICE TOWER
To provide required manpower, equipment and materials requirement Ls 49,543,000.00ks
NORSTAR Office Expansion at JUNCTION OFFICE TOWER
JADE’s scope of work will include:
• Site Engineer/ Supervisor + Safety Supervisor (with Tools and Equipment)
• Scaffolding and operator of polishing machine for smooth, before fixing carpet
• Aluminium Composite
• Section pump for dismantle Glass
• Overhead Cost + Transportation
• Paint + Silicone
• Consumables (Masking tape, Spray, chemical, soap, clothes, newpaper,
knife, etc )
• Requirement thing, Below we submit job items
MNE Ls 13,110,000.00Ks
Client’s scope of work will include:
•Storage Place for Tool & Equipment and one inspector.

Note: Duration would be extended subject to weather condition & unforeseen reasons. Details
of schedule & manpower will be discussed after confirmation of work scope & price. Any
additional work to be discussed on site.
You can choosing below job items of our quotation and after
confirmation of items, reply to us. After replying, we submit drawing and
details with prices to you.

Total Amount 62,653,000.00Ks


Dis %

Sub Total 62,653,000.00Ks


1) Work shall commence upon receiving Purchase Order.
2) Above quote is valid for Only 1 week. (Because of all material price change daily)
3) Payment terms: 50%after receiving PO,50% upon 100%completion of work and hand over
4) Job specification: Subjected to request as above.
If you have any Question about this QUO, Please contact PHYO 09699985458.
QUOTATION
No-(146) , Sapel myaing 2street , 17 Quarter ,South Dagon Township ,Yangon ,Myanmar .
PH: 09975566253 , 09699985458, 09420008504
Jade.engineering@yahoo.com

Attention - NORSTAR
Project - Junction City Office Tower
REF - Office Expansion Date : 23/Jan/2024

Thank you for your invitation to quote for the project. We are pleased to submit herewith our quotation for the above mentioned
project for kind perusal and consideration.

Item Description Quality Price


1. Junction City Office Tower, Room-06-06 1 Ls 5,000,000.00Ks

Interior painting work with (Primer Paint)


Size: (L)-215(ft)x (H)-11(ft) = 2365
2. 1 Ls 21,000,000.00Ks
Junction City Office Tower, Room-06-06

Size: (L)- 5791 (mm) x (W)-5080 (mm) x (H)-3400 (mm) - 2 rooms


Rock wool (or) Glass wool insulation, 12 mm clear tempered glass with floor
spring swing doors and partition boards and making 2 rooms for Managers. (
included of painting)
3. Junction City Hotel Tower, Room-06-06 1 Ls 2,600,000.00Ks

Size: 2300(mm)x2300(mm) and H 3400 mm - store room Rock wool (or) Glass
wool insulation, partition boards and Aluminium Frame with Composite Door
or pvc door

4. Demolition and Renovation of Length – 7925 mm partition wall enclosing 06-05 1 Ls 2,700,000.00Ks
and 06-06

5. Junction City Hotel Tower, Room-06-06 1 Ls 12,500,000.00ks


Floor Carpet – 225 Sq.m

6. Junction City Hotel Tower, Room-06-05 1 Ls 2,500,000.00Ks

Demolition and Renovation of partition wall and glass penel wirh door, ceiling,
painting
7. Cleaning and Waste Removal 1 Ls 1,800,000.00Ks
8. Management Free 5% 1,443,000.00Ks

TOTAL 49,543,000.00ks
QUOTATION
No-(146) , Sapel myaing 2street , 17 Quarter ,South Dagon Township ,Yangon ,Myanmar .
PH: 09975566253 , 09699985458, 09420008504
Jade.engineering@yahoo.com

Attention - NORSTAR
Project - Junction City Office Tower
REF - Office Expansion / MNE Date : 23/Jan/2024

Thank you for your invitation to quote for the project. We are pleased to submit herewith our quotation for the above mentioned
project for kind perusal and consideration.
MEP System Summary

No Particulars Amount (MMK) Remark

1 Electrical System Installation 10,710,000


2 Plumbing & Sanitary System
3 Fire Fighting System
4 ACMV System
5 Design & Approval for Electrical P.E 1,000,000
6 Design & Approval for Fire Fighting P.E 800,000
7 Transportation Cost 100,000
8 Testing & Commissioning Cost 500,000

Total = 13,110,000

Discount =

Contract Amount = 13,110,000