RAB (RENCANA ANGGARAN BAHAN)

1. VOLUME LUBANG PINTU DAN JENDELA

- TINGGI PINTU X LEBAR PINTU X J.PINTU


= (2 m x 1,2 m) + (2 m x 0,92 m x 3 pintu ) +( 0,70 m x 2 m x 2 buah )
= 2,4 + 5,52 + 2,8 m
= 10,72 m2

- TINGGI JENDELA X LEBAR JENDELA X J.JENDELA

= (1,5 m x 0,52 m x 3 jendela)+(1,30 m x 0,52 x 6 jendela)

= 2,34 m +4,056 m

= 6,396 m2

Vol.total pintu dan jendela = 10,72m2 + 6,396 m2

= 17,116 m2

2. VOLUME PEK.DINDING DENGAN BATAKO – VOL.PINTU DAN JENDELA

- (Tinggi tembok x Panjang tembok - vol.pintu dan jendela)


= (2,60 m x 46,575 m)– 17,116 m2 )
= (121,095 m2 – 17,116 m2)
= 103,979 m2

KEBUTUHAN MATERIAL CAMPURAN 1 : 4


o Semen =5,750 x 103,979 = 15 zak
o Pasir =0,043 x 103,979 = 4 m3
o Batako =103,979/0,045 = 2310 buah bta

3. VOLUME TIANG
- Tinggi tiang x lebar tiang x tebal tiang x jumlah tiang
= 4 m x 0,20 m x 0,40 m x 17 tiang
= 5,44m 3

KEBUTUHAN MATERIAL CAMPURAN 1pc :2ps:3krl


o Semen =276 x 5,44/40 = 38 zak
o Pasir =828 x 5,44/1.400 = 3,9 m3
o Kerikil =1.012 x 5,44/1.350 = 4 m3
o Besi Ø12 =8 btg x 5m x17 tiang/12m = 57 btg
o Besi Ø8 =27 bh x1,12 m x 17 tiang/12m = 43 btg
4. VOLUME SLOFF 1 + 2
- Panjang sloof x lebar sloof x tebal Sloof
=( 61 m x 0,15 m x 0,20 m)+(11,5 x 0,15 x 0,20)
= 1,83 m3+0,345 m3
= 2,17 m3

KEBUTUHAN MATERIAL CAMPURAN 1pc :2ps:3krl


o Semen =276 x 2,17/40 = 15 zak
o Pasir =828 x 2,17/1.400 = 1,28 m3
o Kerikil =1.012 x 2,17/1.350 = 1,62 m3
o Besi Ø12 = 6 btg x 61m /12m = 31 btg
o Besi Ø8 = 61/0,15x0,70/12m = 24 btg

5. VOLUME RINGBALK 1 + 2
- Panjang sloof x lebar sloof x tebal Sloof
= 60,53 m x 0,15 m x 0,30 m + +(11,5 x 0,15 x 0,20)
= 2,72 m3+ 0,345 m3
= 3,06 m3

KEBUTUHAN MATERIAL CAMPURAN 1pc :2ps:3krl


o Semen =276 x 3,06/40 = 21 zak
o Pasir =828 x 3,06/1.400 = 1,80 m3
o Kerikil =1.012 x 3,06/1.350 = 2,29 m3
o Besi Ø12 =6 btg x 60,53 /12m = 31 btg
o Besi Ø8 = 60,53/0,15x0,90/12m = 31 btg

6. VOLUME PEKERJAAN RABAT LANTAI


- Panjang lantai x lebar lantai x tebal lantai
= (8,50 m x 7 m ) +(2m x 5m) x 0,07 m
= (59,5 m2 + 10 m2) x 0,07 m
= 69,5 m2 x 0,07 m
= 4,865 m3

KEBUTUHAN MATERIAL CAMPURAN 1 : 4


o Semen =326,000 x 4,865 = 15 zak
o Pasir =0,043 x 4,865 = 4 m3

7. VOLUME PEKERJAAN COR PLAT LANTAI II


- Panjang lantai x lebar lantai x tebal lantai
= (9,16 m x 9,65 m ) x 0,12 m
= 88,394 m2 x 0,12 m
= 10,60 m3
KEBUTUHAN MATERIAL CAMPURAN 1pc :2ps:3krl
o Semen =276 x 10,60 /40 = 73 zak
o Pasir =828 x 10,60 /1.400 = 6,26 m3
o Kerikil =1.012 x 10,60 /1.350 = 7,9 m3
o Bondek =9,16/5
o Besi Ø12 =61 btg x 9,65 /12m = 49 btg
o Besi Ø12 = 64 btg x 9,16/12m = 49 btg

Total Kebutuhan Material

 Semen = 177 zak


 Batu =-
 Pasir = 5,31 atau 6 ret
 Batako = 2310 bta
 Besi Ø12 = 217 btg
 Besi Ø8 = 98 btg
 Bondek = 20 lembar