CLIENT: CONSULTANT: CONTRACTOR:

DAILY REPORT
Report No. J220/RC/DR/223

Project: Samana Miami-1 Date: 22-Feb-24

Client SAMANA SIA HOLDINGS LIMITED Weather : Sunny Cloudy Rainy


Consultant AREC ENGINEERING Temperature: Max: 29° Min: 20°
Main Contractor Reliant Contracting LLC Humidity: High Medium Low

Manpower Equipment
Office Staff No. Production Workers No. Type Qty Hours Worked
GENERAL Manager 1 Carpenter 41 Power Generator 1
PROJECT Manager 1 Steel Fixer 19 Bobcat 1
Site Engineer 2 Mason 6 Welding Machine -
Asst. Const. Manager - Labor/Helper 8 Tower Crane 1
Planning Engineer 1 Electrician 4 Bar bending Machine 1
MEP Coordinator 1 Painter 4 Vibrator 1
QA/QC Manager - Mechanic Compactor 1
Safety Officer. 1 Plumber 1 Boom Loader 1
Civil Forman 2 Crane Operator 1 Excavator -
Electrical Forman - Rigger 1 1 ton Roller -
Plumb. Forman - 6 ton Roller -
Driver 4 Shovel -
Sub-Contractors:
Office Boy/Cleaner 1
Security/Watchman 1
Store/Time Keeper 1
Secretary/Doc. Cont. 1
Safety Officer.Asst..
Surveyor 1
Surveyor Asst. 1
Trade Foreman -

Total 19 85 7 Total= 1106


Al Mayas Insulation. 0

Work Target for Today:


1. 5th to 6th Floor Columns Part-2 Curing Casting date: 21-02-2024 6th Floor
2. 5th to 6th Floor Columns Part-1 Curing Casting date: 15-02-2024 6th Floor
3. 5th to 6th Floor Core wall Part-2 Curing Casting date: 21-02-2024 6th Floor
4. 6th Floor Slab Part-1 Steel Fixing, PT & Trakhees Submission 6th Floor
5. 5th Floor Slab Part-2 Curing Casting date: 16-02-2024 5th Floor
6. 5th to 6th Floor Core wall Part-1 Curing Casting date: 15-02-2024 6th Floor
7. 1st Floor Swimming Pool Wall Steel Fixing & Shuttering 1st Floor
8. G-F Block work Shop area, security room & LV room G- Floor
9. G-F Plaster Preparation at Substation G- Floor
10. 1st Floor Block work Fixing & Curing 1st Floor
11. 2nd to 3rd Staircase-1 Steel Fixing 2nd Floor
12. 2nd to 3rd Floor Staircase-2 Curing 2nd Floor
13. Passenger Hoist Third Party Checking
14. Safety & Site Cleaning work in progress
Work Target for Next day:
1. 2nd to 3rd Floor Staircase-2 Curing Casting date: 21-02-2024 2nd Floor
2. 2nd to 3rd Floor Staircase-1 Casting 2nd Floor
3. 6th Floor Slab Part-1 Trakhees Approval & Casting 6th Floor
4. 5th to 6th Floor Columns Part-2 Curing Casting date: 21-02-2024 6th Floor
5
6. 5th Floor Slab Part-2 Curing Casting date: 16-02-2024 5th Floor
7. 1st Floor Swimming Pool Steel & Shutter Fixing 1st Floor
8. 5th to 6th Floor Core wall Part-2 Curing Casting date: 21-02-2024 6th Floor
9. 1st Floor Block work Fixing & Curing 1st Floor
10. 4th Floor Pouring Strip Casting 4th Floor
11. Hoist Fixing & Third Party Inspection for Hoist
12. Substation Plastering & Chequer Plate Fixing
13. Safety & Site Cleaning work
Material at Site
1. Plywood
2. Scaffolding
3. 3"x3" Timber
4. Blocks
5. Sikanjas.
6. Post Tension Cables
7. Reinforcement Steel
8. Cement
9. Tower crane sections.
Note:
Consultant Eng.: Cont. Engineer: Eng. Sameer Alzebdeh