CLIENT: CONSULTANT: CONTRACTOR:

SAMANA SIA HOLDINGS LIMITED

DAILY REPORT
Report No. J220/RC/DR/156
Project: Construction of Proposed G+P+6 Residential
Building on plot no. JVC14WNEW003 - AL Brasha South Date: 05-Dec-23
Fourth, JVC, Dubai-UAE.
Client SAMANA SIA HOLDINGS LIMITED Weather : Sunny Cloudy Rainy
Consultant AREC ENGINEERING Temperature: Max: 28° Min: 22°
Main Contractor Reliant Contracting LLC Humidity: High Medium Low

Manpower Equipment
Office Staff No. Production Workers No. Type Sty Hours Worked
GENERAL Manager 1 Carpenter 38 Power Generator 1
PROJECT Manager 1 Steel Fixer 18 Bobcat -
Site. engr. 1 Mason 2 Welding Machine -
Asst. Const. Manager - Labor/Helper 5 Tower Crane 1
MEP MANAGER - Electrician 1 Barb ending Machine 2
MEP Coordinator 1 Painter - Vibratos 1
QA/QC Manager - Mechanic Compactor 1
Safety Officer. 1 Plumber - Boom Loader -
Civil Forman 1 Crane Operator 1 Excavator -
Electrical Forman - Rigger 1 ton Roller -
Plumb. Forman - 6 ton Roller -
Draft Man - Shovel -
Sub-Contractors:
Office Boy/Cleaner 1
Security/Watchman 1
Store/Time Keeper 1
Secretary/Doc. Cont. 1
Safety Officer.Asst.. 1
Surveyor -
Surveyor Asst. -
Trade Foreman -

Total 11 65 6 Total= 76
Al Mayas Insulation 0
1. 1st Floor Slab @ Grid A-F/01-05 ready for casting. 1st Floor
2. Columns Grid 5-13 & A-F curing 1st Floor
3. Podium slab @ Grid A-F/05-13 DE shuttering in progress. 1st Floor
4. Core Wall-2 at Podium to First Floor Curing Podium Floor
5. Staircase No.1 shuttering & steel fixing GF to podium Podium Floor
6. Swimming Pool Shuttering work in progress. Podium Floor
7. Last 8 nos. columns & Core Wall-2 DE shuttering & Curing 1st Floor
8. 1st Floor Slab @ Grid A-F/05-13 decking. 1st Floor
9. Ramp Curing 1st Floor
10. Shuttering Supply All areas
11. Material Shifting
12. Safety & Site Cleaning work in progress
13.MEP Fixing work in progress.
Work target for next day:
1. G.F to P.F Staircase Casting.
2. Swimming Pool Area Shuttering Work
3. Beams & columns shuttering @ A-F/05-13
Material at Site
1. Plywood
2. Scaffolding
3. 3"x3" Timber
4. Tie Rods.
5. Sikanjas.
6. Tower crane sections.
Note: