RISK ASSESSMENT MSP- Rev-00

Name of the jobsite: TCPL-Green Energy Source Private Limited, Jamshedpur. Date:
Name of the main activity: Brick Work HIRA No: 0
Assessment team:

Risk Assessment
Risk Matrix

Fatal 5 M M H H H

Impact Rating 
Hospitalization Case 4 L M M H H

Lost Time Case 3 L M M M H

Non-reportable Medical treatment


case 2 L L M M M

First Aid Treatment 1 L L L L M

1 2 3 4 5
Probability Rating 

Unlikely

Inevitable
Most Unlikely

Likely

Most Likely
Risk Level = Probability x
Impact Rating

Legend

Risk Level from 1 to 4 Low Risk

Risk Level from 5 to 12 Medium Risk

Risk Level from 15 to 25 High Risk

Page 1 of 4
RISK ASSESSMENT MSP- Rev-00
Name of the jobsite: TCPL-Green Energy Source Private Limited, Jamshedpur. Date:
Name of the main activity: Brick Work HIRA No: 0
Assessment team:

Brick work Activity:

Rating (P)

Risk Level
Rating (I)

Action by
Residual
Impact

(IxP)
Prob.
S.

Risk
Activity Hazard / Risk Risk Controls Required
No.

1 Shifting and 1. Slip, trip & fall 3 4 M  The work area shall be kept clean and free from obstacles, projected
staging of during sharp materials to prevent slip, trip & fall.
brick. material  Brick stack should not be done more the 1.2 mtr/4 feet.
handling.  As much as possible avoid head transportation of brick.
2. Fall of  Trained & Skilled persons shall be deployed.
material  Job specific PPEs shall be used during the job (Goggles / rubber gloves)
(Brick)  Work shall be done under proper Supervision.
3. Heat related  Rest shelter & drinking water shall be provided
illness.  Ensure PTW before start the work.

Site Engineer
 Proper arrangement for person to work & materials storing.

Low Risk
2 Lying of 1. Collapse of 4 3 M  Safe mean of approach shall be provided to work front.
bricks below soil.  Use gunny begs during plastering to avoid soil contamination
the Ground 2. Soil  Area housekeeping to be maintained.
level up to contamination  Loose materials shall not be stacked in the edge of excavated area.
1mtr. 3. Personal  Trained & Skilled persons shall be deployed.
injury.  Use rubber hand gloves for plastering purpose.
4. Heat related  Job specific PPEs shall be used during the job
illness.  Work shall be done under proper Supervision.
 Rest shelter & drinking water shall be provided
 Ensure workmen aware about MSDS of chemical

Page 2 of 4
RISK ASSESSMENT MSP- Rev-00
Name of the jobsite: TCPL-Green Energy Source Private Limited, Jamshedpur. Date:
Name of the main activity: Brick Work HIRA No: 0
Assessment team:

Rating (P)

Risk Level
Rating (I)

Action by
Residual
Impact

(IxP)
Prob.
S.

Risk
Activity Hazard / Risk Risk Controls Required
No.

3 Lying of 1. Fall from 5 2 M  Job specific working platform with fall protection measures shall be
bricks above height. ensured prior to engage the crew in height work.
the Ground 2. Collapse of  Use gunny begs during plastering to avoid soil contamination.
level up to 3 wall.  Verticality of wall to be maintained.
mtrs. 3. Soil  Trained & Skilled persons shall be deployed.
contamination  Thoroughly wash the exposed body with water.
4. Hazardous  Use rubber hand gloves for plastering purpose.
material  Job specific PPEs shall be used during the job
contact with  Work shall be done under proper Supervision.
skin/Contact  Rest shelter & drinking water shall be provided
with eyes.  Job specific TBT & Training shall be provided to the working person
5. Heat related
illness.

4 Curing of 1. Slip, trip & 3 3 M  Water logging/ slippery surface shall be avoided in work locations.
brickwork fall.  The work area shall be kept clean and free from obstacles, projected
2. Personal sharp materials.
injury.  Regular housekeeping to be maintained

Site Engineer
Low Risk
3. Heat related  Rest shelter & drinking water shall be provided
illness.  Follow permit system before start the job & Ensure proper illumination
during work.

Page 3 of 4
RISK ASSESSMENT MSP- Rev-00
Name of the jobsite: TCPL-Green Energy Source Private Limited, Jamshedpur. Date:
Name of the main activity: Brick Work HIRA No: 0
Assessment team:

Prepared by: Grant Enterprises Reviewed by: JLL Approved by: TGESPL/JLL

Page 4 of 4