Professional Documents
Culture Documents
FINAL of Final BURSA
FINAL of Final BURSA
FINAL of Final BURSA
TABLE OF CONTENTS
EXECUTIVE SUMMARY ................................................................................................ 1
1.INTRODUCTION ........................................................................................................... 3
1.1.Objective .............................................................................................................. 3
1.1.1.Overall Objectives .................................................................................................. 4
1.2.Specific objective ................................................................................................. 4
2.BACK GROUND ............................................................................................................ 5
2.1.Location of the study .......................................................................................... 5
2.2.Climate and Topography ................................................................................... 6
3.METHODOLOGY .......................................................................................................... 6
4.SOCIAL - ECONOMIC STUDY ................................................................................... 7
4.1.Population ............................................................................................................ 7
4.2.Housing condition ............................................................................................... 7
4.3.Infrastructure and social services...................................................................... 7
4.4.Institutions ........................................................................................................... 7
4.5.Economic Activity ............................................................................................... 8
4.6.Mode of service and consumption pattern........................................................ 8
4.7.Income distribution pattern and area of participation ................................... 8
4.8.Affordability and Willingness to pay ................................................................ 9
Information collection approach ............................................................................. 9
Summarized survey for households of all categories ............................................... 10
Survey analysis results and Conclusions on the survey ............................................ 10
4.9. Sanitation and Hygiene condition.............................................................. 11
4.9.1. Latrine availability and utilization pattern ..................................................... 11
4.9.2. Solid waste management system .................................................................... 11
4.10. Overview of the project village .................................................................. 11
4.11. Existing Water Supply and Sanitation facilities condition ..................... 12
4.11.1. General ........................................................................................................... 12
4.11.2. Water source .................................................................................................. 12
4.11.3. Operation and maintenance ............................................................................ 12
4.11.4. Existing sanitation condition .......................................................................... 12
5. WATER RESOURCE STUDY ........................................................................... 12
6. POPULATION AND WATER DEMAND ......................................................... 13
6.1. Population .................................................................................................... 13
6.1.1. General ........................................................................................................... 13
6.1.2. Base population .............................................................................................. 13
6.1.3. Population projection ..................................................................................... 13
6.2. Present water consumption ........................................................................ 14
6.3. Present water demand ................................................................................ 14
6.4. Future Water demand ................................................................................ 14
6.4.1. Domestic water demand (DWD) .................................................................... 15
6.4.2. Climatic Grouping.......................................................................................... 16
6.4.3. Socio-Economic Adjustment Factor .............................................................. 17
List of Table
List of Figures
Figure 10.1 Organizational structures for Bursa Kebele .............................................................. 30
DN =Nominal Diameter
D.O.L=Direct online
GI = Galvanized Iron
km = kilo meter
m = meter
mm = millimetre
DN = NominalDiameter
PN = Nominal Pressure
EXECUTIVE SUMMARY
Main objective of this project is giving an immediate solution for the severe water supply and
sanitation system provision of Bursa kebele. A study and design of the system have been carried
out and presented in this report. The report includes the result of the study and design of the
water supply system in 14 chapters with its detail descriptions. In the introduction part it is tried
to see the necessity of safe water for life and the essentiality of designing water supply scheme.
In the Background; location, accessibility and climate of the area is described. The Kebele
explained to be found in East Belesa Woreda in North Gondar Zone.Bursa has education and
health institutions like; one elementary school and one health center and one veterinary-health
center. There is a problem of water supply both in quantity and quality. Under portion of the
population and water demand analysis all the population projection and water demand analysis
of the area is executed hereunder precisely.
Study of the present/base population and future/projected population is taken to be the first task
to know the water demand in designing any water supply project. The population data try to be
taken from the local administration and then to be counter checked with that of the CSA. Bursa
rural kebele growth rate is under Medium growth variant (rural) and Population projection is
then calculated based on the growth rate set by the CSA using geometrical progression in which
a constant percentage of growth assumed for a certain period of time. For this project a 15 years
design period (2020-2035) is considered since as a rural kebele. Hence the population is
projected from the base population 3143 to the final year population 4137 at the end of the
design period.
Demand projections were also made throughout the 15 year design periods. The major modes
and levels of services considered are public fountains (PF), and Yard connection (YC) respective
of living standard of the community. As per the demand calculation the maximum day demand
and peak hour demand at the end of the design period is designed to be 2.64l/s and 5.29 l/s
respectively. The water source for this project is deep borehole with 13l/s safe yield located 2km
far from Bursa Kebele centre, which is located in Nilygotte.
In the description of proposed schemes part all the recommended civil works and
electromechanical works are described in detail. The new proposed water supply structures for
the project include: 50m3 collection chamber at the same time serves as reservoir for three
gotenamed nily, tehuliye and graho,50m3Sandwich masonry Service reservoir, distribution pipe
networks, Booster Station, Generator house with operation room and public fountains. Water
from the borehole pumped to 50M3 collection Chamber and then pumped to 50m3 Service
Reservoir and then after it will be distributed by gravity action through distribution pipe network
system to the communities.
The pressure main line has a total length of about 4325m and distribution network pipe having a
total length of 8670m.
The environmental impact assessment is also discusses about the positive and negative impact
assessment with their mitigation measures in preconstruction, during construction, and under
operation and maintenance. The Total project cost for the total work is estimated to be
12,959,597.60 ETB.
1. INTRODUCTION
This report presents engineering part of the detailed design of different components of proposed
water supply system.
The report includes sections covering the following principal issues.
Objective
General background -
Population and water demand
Existing water supply system
Description of the proposed scheme
Design ofTransmission Main, Electro Mechanical , distribution main,
distribution systems including service reservoirs, layout & size of pipes and all
the works required to deliver the water from its source to the community
Preparation of appropriate drawings, bill of quantities and specifications for
each specified volume of work
Environmental Aspects.
Geotechnical information
Water tariff analysis
Manage mental and organizational setup
1.1. Objective
The provision of safe drinking water supply and sanitation facilities is a basic necessity of life
and a crucial input in achieving healthy population. All living things on the earth like human
beings, animals and plants make use of water for their survival. For example, human beings use
water for drinking, washing, sewer flushing, firefighting and the like purposes.
Therefore, Cities, Kebele, or Villages, necessary to carry out the necessary designing of water
supply scheme. This requires the knowledge to determine the total quantity of water required for
the various purposes and then finding out the source which satisfy the demand.
The objective of the project is to increase access to sustainable water supply and sanitation service
in particularly for Bursa rural Kebele. The project is designed to improve the living standard of
people living in the project area andits growing population through the provision of adequate and
safe water supply for the coming15 years.
2. BACK GROUND
3. METHODOLOGY
This report is prepared mainly based on the field assessment. During the preparation of detail
engineering design report, the following technical approaches are used and modified to suit into the
actual condition;
Studying the current population information of the kebele.
Conducting detailed surveying work
Assessing the water demand of the Kebele based on the current and projected
population
Reviewing surveying reports of the distribution and transmission lines, reservoirs sites.
Studying distribution of the water users by category, and setting the nodal demand.
Designing of each scheme components based on the basic related design criteria.
Preparation of working drawings for each scheme components.
Preparation of the cost estimates of the project by using the current market prices
The design time horizon of the system is selected to be15 years (up to the end of
2035GC.).
4.1. Population
Even though, the Central Statistics Agency (CSA) is recognized body in Ethiopia to determine
the official population figures and growth rates that should be taken for any development activity
throughout the country, kebele Administrator and concerned Woreda professionals also have
periodically counted population data. So as per the kebele administrator data the population for
bursa kebele is 3143.
4.4. Institutions
Therearepublic elementary school(Grade 1-8)located in the central part of BursaKebeleKebele.
Table 2.1 Number beneficiary of school in the kebele
NO. SCHOOL BENEFICIARY TOTALSTUDENT
1 BURSAKEBELE ELEMENTARY 931
4 GRAND TOTAL 931
Source: East Belesa Woreda educational office
There are twohealth post that provides medical services for BursaKebele and the nearby rural
villages as well.Quite a number ofhouseholds around 816 residents (60.04%) in the project area
have their own pit latrines constructed from locally available materials (wood and mud). There are
no shower facilities at all. In the other hand secondary data from the Kebele Office &baseleine
survey shows that 500 (8.6%) and 500 (8.6%) households in the kebele had both solid and liquid
waste disposal pits respectively at household level.And the sanitation coverage of bursa kebele is
52.73%, Therefore the ten most prevalent diseases in the area as reported by Keblehealth centre are
tabulated in the table below.
The willingness to pay will help to compare and recommend the minimum water tariff for the
water supply system after calculating the tariff from the technical requirement point of view when
the construction is completed if the collected information shows good willingness of the
community to cover at least operation and maintenance cost.
Therefore, the purpose of this survey is to make a willingness to pay assessment of the expected
beneficiaries of Bursa Kebele rural villages piped water supply system to cover at least the
operation and maintenance fund required for the sustainability of the scheme.
The average willingness to pay of the people for one cubic meter of water is 24.56 birr for house
hold consumption. The maximum tariff which is in use in the region by many motorized schemes
is 3.5 birr/cubic meter of water assuming to cover mainly operation and maintenance cost. This
implies if good financial management and tariff collection system established, the fee to be
collected from the people can cover even more than the operation and maintenance cost. Therefore,
financing of the bursa kebele water supply scheme is feasible at least from the point of view
covering 100% operation and maintenance cost to sustain the system.
The average monthly payments willing to be paid by the low & medium level living standard users
is 17.5% &4.55% of their monthly income respectively. And the average monthly payment willing
to be paid by the high living standard users is 4% of their monthly income respectively. The World
Bank recommendation regarding monthly payments willing to be paid for people having low
standard is 2% of their income and for people having living standards other than low is up to 4% of
their income. Therefore, we can say that the average amount of the household income that the
people are willing to pay for water is more than the minimum recommended percentage by the
World Bank it doesn’t mean that they will not pay for improved water in this particular case it
seems that the people are valuing water as a basis for their life and are willing to pay more for it
against to severity of problem. Draft paper such as cost effective design for World Bank water
supply and sanitation project support the idea “If the % spend for water 5% and more, it indicates
that people are willing to pay for improved water.”
Low & medium living standard people are paying for water 17.5 &4.55% of their monthly income
respectively while they are paying for electric power 5.33 & 1.25% of their monthly income and
16.25% & 4.86% for medical respectively. High living standard people are paying for water 4% of
their monthly income respectively while they are paying 1% of their monthly income for electric
and 5.85 % of their monthly income for medical treatment. Therefore, we can say that communities
of bursa Kebele rural village are taking water as a basic need for life and willing to pay more if
they get clean and potable water.
The final decision on the amount of water tariff to be set will be a compromise of this willingness
to pay survey result and the tariff required from the technical requirement point of view at least to
cover the operation and maintenances cost which will be clearly known when the construction of
the scheme is completed. And this survey is only to know the willingness and ability to pay of the
people from the improved water supply system which they are going to get.
4.11.1. General
During the survey and study of the team, most expresses strongly that they are suffering to use of
potable water at reasonable distance .There is no existing piped water supply system.
6.1. Population
6.1.1. General
Even though, the Central Statistics Agency (CSA) is recognized body in Ethiopia to determine
the official population figures and growth rates that should be taken for any development activity
throughout the country, Kebele Administrator and concerned Woredaprofessionals also have
periodically counted population data. So as per the kebele administrator data the population for
bursa kebele is 3143.
Growth rate
Table 7.2 projected annual growth rates,
Year Medium variant
5-year period Rural Urban
1995-2000 2.8 4.54
2000-2005 2.58 4.27
2005-2010 2.41 4.21
2010-2015 2.19 4.02
2015-2020 2.1 3.81
2020-2025 1.7 3.59
2025-2030 1.5 3.42
Source: Planning of Water Supply Minster of Water Resources (JICA), CSA 1999
Table 7.3 Population Projection (2018-2035)
Year 2018 2019 2020 2025 2030 2035
Growth rate (%) 2.1 2.1 2.1 1.7 1.5 1.5
The implementation of the project will result in change of the per capita water demand through
each mode of service. To estimate the projected percapita demand using the initial demand of
30l/c/d and 30 l/c/d for yard and public tap users respectively, the consultant assumed water
demand to grow at growth rates of 1% for public and 2% for yard per annum.
Table 7.5 Projected Average Per Capita domestic Water demand
Year
Demand Category 2020 2025 2030 2035
YTU 30 33.1 36.6 40.4
PTU 25.0 26.3 27.6 29.0
Based on the socio-economic survey carried out during study and the previous experiences, it is
reasonable to assume and adopt that about 80 and 20 percent of the population will public fountain
and yard connection users respectively at the end of the design period.
Source: Socio economic assumptions during the study on Bursa, may, 2010E.C)
Source: Design Guideline for Water Supply Projects, Oromo Water Works Design and Supervision
Enterprise (December, 2008)MOWR Design criteria guide line)
Hence, Bursaproject areahas an altitude between1500m-2300m amsl, which falls under group C.
Therefore an adjustment factor of 1 to refine the average per capita domestic water demand is
considered to make it on safe side.
Socio-economic activities have a role in determining the degree of development of the rural
kebele under study which in turn determines water consumption. Bursa Kebele, as compared to
other rural kebele in which most of the inhabitants are farmers withfew traders. In the view of this
and considering their development, it is classified under group C with appropriate adjustment
factor of 1.
Table 7.10 Socio-Economic factors
Gr groupDe description factor
A Kebeles enjoying high living standards and with very high potential
2.0
A for development
BB Kebeles having a very high potential for development but lower
1.5
living standard at present
CC Kebeles under normal Ethiopian conditions 1.0
Source: Planning of Water Supply Minster of Water Resources (JICA), CSA 1999
The following table presents summary of the results on population projection, percentage of
population served by different mode of services, Water demand determination and its growth in
the expected service year of the new system and the calculated adjusted average domestic
demand in liter per second for Bursa site study.
Table 7.11 Summary of Adjusted Domestic Demand
Year
Demand Category Unit 2020 2025 2030 2035
m3/day 85.19 99.76 116.36 138.85
Average Day Demand l/s 0.99 1.15 1.35 1.61
Climatic Adjustment factor 1 1 1 1
Socio Economic Adjustment
Factor 1 1 1 1
m3/day 85.19 99.76 116.36 138.85
Adujusted domestic demand l/s 0.99 1.15 1.35 1.61
remedial work is carried out. It is logical to presume an increase in water loss with time in
designing water supply system.
demand category. Previous studies and experiences clearly demonstrate that peak hour factor is
greater for a smaller population. According to water supply design criteria prepared by ministry
of water resource and tropics studies the proposed maximum day and peak hour factor are
summarized below
So the design average day demand is quantified as 2.03lit/sec reqaired to satisfy water demand
load at 2035.
7. DESIGN CRITERIA
A design period of 15years is considered for the design of the proposed scheme as it is rural
kebele water supply system. The proposed water supply structures forBursaproject are: Borehole,
service Reservoir, publicfountains, Collection chamber, booster station,Generatorhousewith
operation room, pressure and distribution mainsetc. Water from bore hole pumped to the50M3
collection chamber(As explained collection chamber also serves as reservoir for
nily&grahogotte&tehuleye) and Pumped to 50m3 sandwich masonryservice reservoirs and
eventuallywater distributed by gravityaction down to the users through distribution pipe
networks. The service reservoir and public taps should be constructed at the selected site and
fenced properly.
8.2. Treatment
In this water supply project as the source of the water supply is borehole the best method of
treatment will be chlorination done by manually put in the reservoir.
8.5. Reservoir
Capacity of reservoir for these project is by taking one third of the max day demand. We have got
228.34/3 m3 which is 76m3.So for the first syatem(lay & tach
ebara,shirobeten,gendaho,ginshia&dingaymidir) which is 68% by population of the whole project
we got 52m3 which is standard 50 m3. For the second system we need 26m3 for population uses
from the collection chamber and by taking 30min detention time we have found 10m3. So we have
got36m3 which is 50 m3 standard collection chqamber and also servs as reservoir for three
got(nily, tehuleye and graho)
Table: 9.2. Service reservoir location
No. Easting Northing Elevation capacity
50m3(coll.
1 397,442.77 1,364,380.38 1,922.15 & reservoir)
Shikur, Alemayehu & friends Wash Consulting Firm 22
Amhara Water, Irrigation and Energy Bureau Bursa Kebele Water Supply Final Design Report
8.6. Distributionsystem
The distribution network is designed in such a way that it safely and economically accommodates
the Peak hour demand of the design year 2035. The layout of the distribution network has been
prepared based on the existing population settlement pattern and topographic suitability. As per
the design criteria, the following guidelines are maintained in the analysis of the distribution
network.
During Peak hour flow velocity shall be between 0.3 and 2.0 m/s for non loop system.
During minimum consumption water shall not be stagnant in the distribution network
In the hydraulic simulation of the pipe network system, the demand at each node is calculated
based on the information gathered regarding the future development trend of the kebele and the
estimated population density.
The hydraulic network diagram system for project area as shown on the layout drawing
including minimum demand (night time) and peak hour demand (day time) conditions were
carried out using the software called WaterCAD 6.5. Specific print outs of simulation results
covering minimum and peak hour consumption periods are attached in annex A and schematic
layouts showing the proposed pipe distribution network are presented in the drawing.
As per the analysis from the hydraulic calculation summary, the maximum pressure at minimum
demand is 89mH2O. And due to the nature of the topography and workable soil depth of site,
PE100, PN10 HDPE pipe type is proposed for the distribution system.
max.pressure mini. Pressure max.
no. Description head head at wp min.velocity velocity
1 During peak hour demand 84.58 11.36 0.3 0.84
During minimum day
2 demand 89.94 21.33 - -
Table 9. 3Summaries of Pipe Diameter and Length by adding 10 % contingency for each pipe
IT.NO Pipe Dia. Length(m)
material
1 HDPE 40mm 1588
2 HDPE 50mm 2817
3 HDPE 63mm 1626
4 HDPE 75mm 2109
5 HDPE 90mm 531
Total 8670
The public fountains are designed in such a way that users of various water fetching types like
Jeri can, and pot could easily be served. Moreover, these four faucet public fountains should be
constructed by Masonry with 1:3 mix mortars so it minimizes part of the project cost.
Hydraulic analysis
The hydraulic analysis of a water transmission system usually involves the use of the Hazen-
Williams equations to determine frictional head losses
hf =10.675*L*(Q^1.852)/((C^1.852) *(D^4.87))
1. Pump and generator analysis
Water must be pumped from the source to the destination higher elevation point (booster or service
reservoir) by using either centrifugal or submersible pump. Water pumping station have been
developed based on the following data
At duty point the mechanical and electrical efficiencies for the pump are ηm andηe 65% and
80%respectively
The pump and generator set will be work at the specific location masl, temperature and humidity
conditions
9.1. Introduction
Most water supply schemes in our region suffer from sustainability due to poor Management
system right from the commencement till the operation stage. To alleviate the problem, the Federal
and Regional Governments issued Policies and regulations to upgrade and improve the institutional
and technical capacity of those major actors in the sector. This section of the document is intended
to prepare Manage mental Models and Organizational structure for Bursa piped water supply
system to operate efficiently and sustainably.
Board
Manager& Accountant
As we can see in the above diagram, a person titled manger and accountant is accountable to the
Board and subordinated by other hired people with different experience and assignments. The
Woreda Water office shall follow and monitor the overall performance of the scheme instead of
taking over other routine activities like water point source rural schemes Woreda Water Office did.
The Woreda water Office with the assistance team shall give to employees a clear description of
tasks which they perform regularly. By doing so every employee will accomplished what is
expected from him/her and ensures sustainability.
The collection of money for operation and maintenance will be carried out by the Kebele water
committee formed in each fountain as per the tariff set based on the analysis done in the design
document.
9.4. Procurement
The procurement of spare parts, fuel& oil and other materials is the duty and responsibility of the
subordinate staffs that will be hired. Spare parts which will be easily damaged and frequently
changed have to be available at stock.
9.6. Audit
The Woreda water office team will send an auditor to monitor the proper collection, handling and
use of money and other property of the community annually or less can be audited under the
request of board.
A report consists of all works executed throughout the reporting period and encountered problems,
it can be prepared by the scheme manger. All community members shall involve in finding the
solutions to ensure ownership of the scheme.
The project also utilize local material purchased from the community.
The pipe line is tranmited through the boundary of agriculureal and houses,so, it disturb
the agriculture and activities of the public.
13. CONCLUSION
The Proposed Kebele Piped Water Supply Project is therefore, at right time and is expected to
bring an improvement in the public health status, economical productivity, sanitation conditions
and time & energy savings, particularly for women and children
Currently there is deficiency of adequate quantity and good quality of water supply system
at the project area. Therefore, It is the right time constructing the project to solve the
shortage of water, public health improvement, time and energy saving for women and
children.
Fortunately, the whole system layout is found accessible; reservoir, distribution lines and
pressure line are all accessible for construction. However, at rainy season, any civil works
may be difficult to construct in the Bursa environmental condition.
In order to optimize benefits and minimize the negative impacts of the proposed water supply
project, the following measures are recommended:
Provision of clean and adequate water to the public users should be supported by improving
the sanitation facility. Therefore, the community should be educated in keeping sanitation
and personal hygiene.
Close follow up and the issue of empowering communities to build, own and manage their
water systems must be clarified at the highest level.
Note: The points J1, J2,DL31, DL32 are points near to the reservoir.
Shikur, Alemayehu & friends Wash Consulting Firm 38
Amhara Water, Irrigation and Energy Bureau Bursa Kebele Water Supply Final Design Report
Pressure
Northing Elevation (m
No. Label Easting (m) (m) (m) H2O)
1 DL32 397,378.69 1,366,859.62 2,018.76 4.154
2 DL31 397,412.69 1,366,820.22 2,013.08 9.443
3 NWPGINSHIA 397,529.07 1,365,031.17 2,001.83 11.36
4 DL61 397,418.24 1,365,149.05 2,002.17 11.705
5 T.2 397,541.79 1,365,092.70 2,001.72 11.79
6 DL30 397,451.13 1,366,781.36 2,007.33 14.782
7 DL29 397,484.15 1,366,745.09 2,003.51 18.235
NWPDINGAY
8 MIDER 397,687.25 1,365,294.34 1,993.46 19.112
9 NWP4 397,281.00 1,365,168.46 1,994.59 19.643
10 J8 397,288.68 1,365,220.88 1,991.32 23.053
11 DL27 397,544.32 1,366,688.30 1,995.97 25.162
12 DL60 397,276.45 1,365,260.79 1,988.55 25.93
13 DL26 397,557.43 1,366,648.32 1,989.37 31.439
14 DL59 397,239.31 1,365,325.97 1,982.80 31.862
15 RL2 397,199.40 1,365,367.09 1,980.30 34.517
16 DL58 397,132.66 1,365,429.19 1,979.74 35.318
17 CHWP.1 397,563.39 1,366,598.16 1,984.27 36.131
18 SCHWP. 397,621.02 1,366,303.56 1,981.48 36.238
19 J3 397,583.62 1,366,609.87 1,984.03 36.432
20 HCWP.1 397,618.52 1,366,441.65 1,981.45 36.957
21 DL28 397,635.46 1,366,386.89 1,980.86 37.168
22 NWP1 397,657.35 1,366,380.00 1,980.70 37.203
23 J5 397,631.15 1,366,444.20 1,981.31 37.206
24 NWPG/WUHA 397,893.82 1,366,215.88 1,979.13 38.262
25 DL56 397,001.41 1,365,541.33 1,977.22 38.304
26 DL57 397,046.88 1,365,506.08 1,977.05 38.32
27 J-133 397,674.99 1,366,486.48 1,980.00 39.506
28 J6 397,701.83 1,366,492.42 1,979.77 39.604
29 DL24 397,669.87 1,366,508.61 1,980.01 39.631
30 DL55 396,953.61 1,365,566.25 1,975.96 39.704
31 J4 397,649.10 1,366,513.39 1,980.03 39.728
32 NWPMAEKEL 397,716.06 1,366,512.46 1,979.17 40.078
33 DL23 397,742.12 1,366,464.88 1,978.20 40.908
34 DL33 397,833.04 1,366,256.10 1,976.52 41.265
Pressure
Northing Elevation (m
No. Label Easting (m) (m) (m) H2O)
35 DL36 397,692.07 1,366,425.83 1,977.78 41.534
36 J-130 397,643.72 1,366,492.41 1,976.91 42.468
37 DL25 397,622.12 1,366,542.42 1,976.74 43.248
38 DL54 396,890.17 1,365,573.78 1,972.50 43.33
39 DL35 397,702.46 1,366,399.99 1,975.30 43.928
40 DL34 397,715.10 1,366,363.99 1,974.30 44.814
41 DL21 397,789.33 1,366,370.28 1,973.14 45.391
42 NWP TACH EBARA 396,837.30 1,365,560.14 1,969.14 46.39
43 DL22 397,770.85 1,366,411.67 1,971.89 46.881
44 DL20 397,781.69 1,366,297.90 1,967.48 50.646
45 DL52 396,919.60 1,365,590.83 1,960.78 55.195
46 DL49 397,135.37 1,365,618.64 1,960.81 55.923
47 DL50 397,067.91 1,365,621.58 1,960.11 56.474
48 DL47 397,274.62 1,365,654.02 1,958.42 58.606
49 DL51 397,024.20 1,365,624.89 1,957.23 59.261
50 DL48 397,206.07 1,365,650.19 1,957.42 59.462
51 DL17 397,724.62 1,366,130.25 1,958.95 59.518
52 DL18 397,752.29 1,366,211.06 1,958.88 59.758
53 DL19 397,766.76 1,366,260.58 1,958.73 60.011
54 DL46 397,295.65 1,365,658.73 1,955.58 61.483
55 DL16 397,699.43 1,366,090.83 1,954.30 64.062
56 DL45 397,328.22 1,365,668.64 1,952.87 64.256
57 DL44 397,355.22 1,365,675.14 1,950.35 66.828
58 DL43 397,385.68 1,365,671.18 1,949.35 67.891
59 DL15 397,658.34 1,366,027.34 1,946.54 71.647
60 DL42 397,432.16 1,365,696.68 1,938.74 78.585
61 DL37 397,638.32 1,365,973.28 1,939.15 78.91
62 J2 397,636.45 1,365,955.12 1,938.21 79.803
63 DL41 397,459.77 1,365,760.03 1,937.56 79.911
64 DL38 397,586.58 1,365,878.52 1,936.97 80.855
65 DL40 397,477.27 1,365,793.13 1,933.08 84.457
66 DL39 397,532.08 1,365,840.42 1,933.10 84.579
67 J1 397,468.09 1,364,328.16 1,915.87 6.303
68 J12 397,486.87 1,364,332.57 1,914.58 7.523
69 DL83 397,566.44 1,364,280.46 1,911.02 10.709
70 DL84 397,613.65 1,364,244.19 1,906.47 15.021
71 NWP GRAHO 397,648.31 1,364,203.56 1,905.66 15.619
Pressure
Northing Elevation (m
No. Label Easting (m) (m) (m) H2O)
72 DL13 397,440.27 1,364,224.22 1,904.04 17.824
73 GL4 397,457.31 1,364,260.59 1,902.86 19.106
74 GR3 397,448.04 1,364,249.33 1,901.12 20.811
75 DL12 397,449.99 1,364,148.78 1,899.00 22.654
76 NWPNILY2 396,666.64 1,363,014.35 1,888.35 24.898
77 DL76 396,756.23 1,362,941.29 1,885.95 27.741
78 DL71 396,763.68 1,362,844.99 1,885.09 28.708
79 DL72 396,768.41 1,362,835.01 1,884.85 29.044
80 DL74 396,730.87 1,362,775.32 1,884.52 29.159
81 J10 396,801.40 1,362,906.00 1,883.95 29.957
82 DL70 396,811.53 1,362,899.00 1,883.81 30.198
83 DL73 396,743.71 1,362,778.83 1,883.51 30.288
84 DL75 396,734.87 1,362,752.78 1,882.83 30.801
85 NWPNILY 396,945.13 1,362,966.87 1,881.70 32.21
86 J9 396,881.25 1,362,995.51 1,881.90 32.282
87 DL69 396,874.67 1,363,004.12 1,881.42 32.748
88 GL3 397,474.95 1,364,007.64 1,887.59 33.654
89 DL67 396,907.73 1,363,032.48 1,880.55 33.734
90 DL66 396,900.77 1,363,042.87 1,880.46 33.81
91 DL4 397,244.27 1,363,368.17 1,883.12 34.139
92 DL65 396,948.39 1,363,106.87 1,880.09 34.361
93 DL64 396,958.42 1,363,104.83 1,879.72 34.751
94 DL2 397,088.76 1,363,329.26 1,880.90 35.073
95 DL11 397,485.32 1,363,944.97 1,885.82 35.254
96 NWP TEHULEYE 398,238.02 1,363,075.57 1,880.80 35.653
97 DL3 397,180.64 1,363,348.17 1,880.67 36.046
98 DL7 397,433.33 1,363,528.94 1,882.43 36.529
99 DL1 397,045.56 1,363,292.84 1,878.85 36.661
100 DL6 397,395.82 1,363,487.78 1,882.11 36.705
101 DL8 397,467.19 1,363,587.27 1,882.41 36.718
102 DL63 397,009.49 1,363,202.23 1,877.81 36.894
103 DL62 397,016.68 1,363,200.31 1,877.75 36.967
104 J-49 397,886.17 1,363,378.28 1,880.50 37.391
105 DL5 397,295.60 1,363,407.77 1,880.36 37.412
106 DL9 397,519.32 1,363,632.55 1,881.85 37.458
107 J-48 397,799.01 1,363,495.18 1,880.36 37.983
108 BRL1 397,034.49 1,363,250.60 1,876.71 38.452
Pressure
Northing Elevation (m
No. Label Easting (m) (m) (m) H2O)
109 GL1 397,348.19 1,363,440.68 1,879.25 39.017
110 DL10 397,515.28 1,363,732.20 1,880.83 39.1
111 GR1 397,340.03 1,363,436.57 1,878.99 39.201
112 GL2 397,496.79 1,363,901.88 1,881.44 39.507
113 GR2 397,496.98 1,363,890.37 1,880.90 40.016
114 BRR1 397,035.61 1,363,230.16 1,874.55 40.443
SUMMARY OF BOQ
1 General item
Fabricated and erect metallic project sign
boards for project identification including
1.1 printing of titles as per engineers instruction Ls 2
Prepare and provide as built drawings of all
works constructed under this contract as per
the specification and to the satisfaction of
1.2 engineer and client Ls 1
Mobilization of man power ,equipment
,machinery and all required materials to the
1.3 site No. 1
1.4 Demobilization Ls 1
Provide survey control points and setting out
work including with report of addition and
1.5 omission of pipe line other related activities Ls 1
Establishment of contractors and engineers
site office as shown in the detail
drawing(covering a land area of about 70m2
with CIS G-28 wall,8mm thick chip wood
internally and roof for insulation and CIS G-
28 roof and equluptes poles including office
furniture(tweleve chair and four medium
table) electricity &hand over to the kebele
1.6 water committee after project completion. Ls 1
Sub Total
Total
Unit
S.No. Description Unit QTY Price Total Price
Part I Trench Excavation and Back Filling
1 Trench excavation
1.1 Depth up to 0.9m*0.6m normal soil m3 1141.82
a .Ditto item 1.1 But with soft rock 3
1.2 m 913.46
a .Ditto item 1.1 But with Hard rock 3
1.3 m 228.36
1.4 c. Ditto item 1.1 But with back fill native soil m3 1141.82
d.Ditto item 1.1 But with Back fill with select
1.5 material m3 1141.82
2 Structural works
Unit
S.No. Description Unit QTY Price Total Price
3.3.5 OD 110ninty degree bendPN 10 No. 1.00
3.3.6 OD 110 degree bendPN 10 No. 1.00
OD 110 flanged adapter pn 10 with Back
3.3.7 ringing No. 1.00
Pipe line testing and commissioning For the
whole Rising main work including transporting
water and dispose of used water including
4 disinfection Ls. 1.00
Sub Total
Total
BOQ 3: DISTRIBUTIONLINE
Total
No ACTIVITY Unit Qty
Rate Amount
& Bulging out
3 Masonry work
Construction of 20 x 20 cm thick Masonry Wall on
3.1 both side of the Concrete - Core embedded with m3 20.6
cement Sand mortar of mix 1 : 3
Floor finish 30 mm thick trawl and smooth finish with
3.2 m2 18.1
1:3 cement Sand mortar screed
Semi Dressed Stone Pavement around the Reservoir
3.3 m2 36
1.0 m wide cemented with in 1:3 mix cement mortar
Construction of Semi-Circular 30 cm diameter
3.4 m 38
Drainage Ditch as per drawing
1.4mx1.4m masonry Valve chamber construction as
shown in the drawing including 80cmX80cm metal
3.5 LS 2
sheet for manhole cover with thickness 4mm with all
accessory.
3.6 Reservoir man hole cover as per standard dimension No. 1
4 Mislaneous& Finishing
Supply & install all necessary pipes & fittings with all
necessary accessories, gate valves, Float Valves as per
4.1 LS 1
the Design Drawings for In-let, Out-let, Vent pipe
Drain,& Over-flow system of the reservoir
A Inlet pipes and fittings with PN 10
DN 80GS pipe formed into the required pieces for
4.1.1 suitable connections including unions, nipples & m 12
sockets
4.1.2 GS 90 deg bend DN 80 PN 10 no 2
4.1.3 DN 80 internally threaded gate valve PN 10 no 1
4.1.4 OD 90 TO 3" Female Adapter no 1
Medium Class Outlet GI pipes & PN10 Fittings with
B
accessories
DN 80GS pipe formed into the required pieces for
4.1.6 suitable connections including unions, nipples & m 12
sockets.
GS 90 deg bend DN 80 PN 10 no 2
4.1.7 DN 80 internally threaded water meter PN 10 no 1
4.1.8 DN 80 internally threaded gate valve PN 10 no 1
4.1.9 OD 90 TO 3" Female Adapter no 1
Medium class Over flow and Drainage pipes & PN 10
C
Fittings
4.1.10 DN 80 internally threaded 90 degree bend no 2
4.1.11 DN 80 internally threaded tee PN 10 no 1
Shikur, Alemayehu & friends Wash Consulting Firm 55
Amhara Water, Irrigation and Energy Bureau Bursa Kebele Water Supply Final Design Report
Total
No ACTIVITY Unit Qty
Rate Amount
4.1.12 DN 80 internally threaded gate valve PN 10 no 1
4.1.13 Medium class Vent pipes & PN 10 Fittings
4.1.14 DN 2.5” vent pipe no 1
4.1.15 DN 2.5” GS tee no 1
4.1.16 DN 2.5” GS nipples no 1
4.1.17 DN 2.5” GS elbow no 1
Supply and install both External & Internal Ladder
made of Class B, G S Pipe of 1 ½” Length 3.0 m
4.2 No 2
having extra 1.0 m high handle at the top for External
Ladder
Install and fix quality water meter DN 80 mm at the
4.3 outlet of the reservoir with appropriate fittings and No 1
Gate Valve.
Plastering the whole inner wall face and exposed faces
4.4 of concrete works with three coats of cement sand m2 94
mortar of mix 1 : 2
4.6 Pointing the whole External face of the masonry wall
m2 56.5
with cement mortar mix 1 : 2
5 FENCE WORK
Supply and erect fence of 40mm*30mm*3mm angle
iron stands c/c spaced at 100cm to a height of 2m
above ground level with 6 lines of barbed wire
5.1 200mm and 400mm spacing the bottom 4 and upper 2 m 80
lines, respectively with cross diagonal & to a depth of
50cm embedded in concrete foundation of
200mm*200mm.
Construct 1500mmx3000mm size gate with metal
frame and rectangular hollow tube 80mmRHS
5.2 No 1
including 2mm sheet metal having three coats of
antirust painting including hinges and lock.
Total for one 50m3 reservoir
Total
No ACTIVITY Unit Qty
Rate Amount
1 Earth Work
Site clearing & grubbing up to a average depth of 20
1.1 m2 43
cm.
Foundation excavation to a depth of 75 cm below
1.2 m3 32.2
ground level
Filling and compacting foundation base with selected
1.3 m3 6.43
materials for 20 cms
Placing 40 cm thick basaltic stone or equivalent hard
1.4 m3 20.4
core well-rolled consolidated and blinded with gravel
Back filling around a foundation with approved
1.5 selected materials from site well rammed in layer of m3 22.1
20 cm
Cart away surplus excavated materials from the site to
1.6 m3 40.8
a distance of 100 m
2 concrete work
Casting 50 mm thick Lean concrete over hard-core
2.1 with Grade C-15 concrete with minimum cement m2 30.2
150kg/m3
Casting 25 cm thick Base slab in Grade C-25
2.2 reinforced concrete with minimum cement 360kg/m3 m3 7.55
mix 1:2:4
Casting 20 cm thick Roof cover slab with Grade C-25
2.3 m3 6.8
reinforced concrete of minimum cement 360kg/m3
Construction of friction key with Grade C-25
2.4 m3 0.83
reinforced concrete simultaneously with base slab
Construction of 10 cm thick reinforced concrete Grade
2.5 C-25 filled between masonry wall reinforced with m3 5.2
Hexagonal Mesh-Wire of size 3/4
Casting 20cm thick concrete Ring beam of Grade C-
2.6 m3 1.7
25 with minimum cement 360kg/m3
supply, cut, bend and fix in position reinforcement
2.7
bars
a/ ø 6mm kg 66.1
b/ ø 8mm kg 126
c/ ø10mm kg 325
d/ ø 12mm kg 578
Supply and fix3/4 Hexagonal Mesh Wire for hoop
2.8 m2 55
stress
Sub total
2.9 Fixing of good quality wooden or metal form work m2 54
Total
No ACTIVITY Unit Qty
Rate Amount
firmly with strong strutting & tight to avoid Bleeding
& Bulging out
3 Masonry work
Construction of 20 x 20 cm thick Masonry Wall on
3.1 both side of the Concrete - Core embedded with m3 20.6
cement Sand mortar of mix 1 : 3
Floor finish 30 mm thick trawl and smooth finish with
3.2 m2 18.1
1:3 cement Sand mortar screed
Semi Dressed Stone Pavement around the Reservoir
3.3 m2 36
1.0 m wide cemented with in 1:3 mix cement mortar
Construction of Semi-Circular 30 cm diameter
3.4 m 38
Drainage Ditch as per drawing
1.4mx1.4m masonry Valve chamber construction as
shown in the drawing including 80cmX80cm metal
3.5 LS 2
sheet for manhole cover with thickness 4mm with all
accessory.
3.6 Reservoir man hole cover as per standard dimension No. 1
4 Mislaneous& Finishing
Supply & install all necessary pipes & fittings with all
necessary accessories, gate valves, Float Valves as per
4.1 LS 1
the Design Drawings for In-let, Out-let, Vent pipe
Drain,& Over-flow system of the reservoir
A Inlet pipes and fittings with PN 10
DN 80GS pipe formed into the required pieces for
4.1.1 suitable connections including unions, nipples & m 12
sockets
4.1.2 GS 90 deg bend DN 80 PN 10 no 2
4.1.3 DN 80 internally threaded gate valve PN 10 no 1
4.1.4 OD 90 TO 3" Female Adapter no 1
Medium Class Outlet GI pipes & PN10 Fittings with
B
accessories
DN 80GS pipe formed into the required pieces for
4.1.6 suitable connections including unions, nipples & m 12
sockets.
GS 90 deg bend DN 80 PN 10 no 2
4.1.7 DN 80 internally threaded water meter PN 10 no 1
4.1.8 DN 80 internally threaded gate valve PN 10 no 1
4.1.9 OD 90 TO 3" Female Adapter no 1
Medium class Over flow and Drainage pipes & PN 10
C
Fittings
4.1.10 DN 80 internally threaded 90 degree bend no 2
Total
No ACTIVITY Unit Qty
Rate Amount
4.1.11 DN 80 internally threaded tee PN 10 no 1
4.1.12 DN 80 internally threaded gate valve PN 10 no 1
4.1.13 Medium class Vent pipes & PN 10 Fittings
4.1.14 DN 2.5” vent pipe no 1
4.1.15 DN 2.5” GS tee no 1
4.1.16 DN 2.5” GS nipples no 1
4.1.17 DN 2.5” GS elbow no 1
Supply and install both External & Internal Ladder
made of Class B, G S Pipe of 1 ½” Length 3.0 m
4.2 No 2
having extra 1.0 m high handle at the top for External
Ladder
Install and fix quality water meter DN 80 mm at the
4.3 outlet of the reservoir with appropriate fittings and No 1
Gate Valve.
Plastering the whole inner wall face and exposed faces
4.4 of concrete works with three coats of cement sand m2 94
mortar of mix 1 : 2
4.6 Pointing the whole External face of the masonry wall
m2 56.5
with cement mortar mix 1 : 2
5 FENCE WORK
Supply and erect fence of 40mm*30mm*3mm angle
iron stands c/c spaced at 100cm to a height of 2m
above ground level with 6 lines of barbed wire
5.1 200mm and 400mm spacing the bottom 4 and upper 2 m 80
lines, respectively with cross diagonal & to a depth of
50cm embedded in concrete foundation of
200mm*200mm.
Construct 1500mmx3000mm size gate with metal
frame and rectangular hollow tube 80mmRHS
5.2 No 1
including 2mm sheet metal having three coats of
antirust painting including hinges and lock.
Total for one 50m3 reservoir
Unit Total
Item Description Unit Quantity price amount
1 Earth work
Clearing and removal of top soil to
1.1 average depth of 25cm m2 15.84
Excavation in ordinary soil to a depth
1.2 not greater than 1m m3 9.50
Cart away the excavated material not
1.3 less than 1000m m3 30.12
Back fill and compacted with selected
1.4 soil 20cm layer by layer m3 13.50
1.5 25 cm thick hard core fill m2 6.6
2 Masonry Work
Stone masonry with cement mortar 1:3
2.1 ratio with pointing m2 11.8575
One meter width semi dressed stone
2.2 pavement (1:3) ratio mix m2 16
stone masonrytrapezoidal drainage
2.3 ditch mix(1:3) m 13.6
3 Concrete works
3.1 5cm thick C-5 lean m2 4.00
C-25 concrete column, gradebeam,
3.2 Intermediate beam & top tie beam
3.2.1 floor slab m3 1.24
3.2.2 grade beam m3 0.50
3.2.3 in elvn column m3 0.40
3.2.4 in suspended beams m3 0.50
3.2.5 for lintel m3 0.10
sub total
4 sawn zigba form work
4.1 2 side grade beam m2 7.00
4.2 in elvn column m2 3.00
4.3 in suspended beams m2 3.40
5 Reinforcement
5.1 ø06mm bar kg 12.00
5.2 ø08mm bar kg 30.70
5.3 ø12mm bar kg 137.10
sub total
6 Supply and construct HCB walling
Shikur, Alemayehu & friends Wash Consulting Firm 60
Amhara Water, Irrigation and Energy Bureau Bursa Kebele Water Supply Final Design Report
Unit Total
Item Description Unit Quantity price amount
6.1 class "C" 20cm thick HCB wall m2 26
sub total
6.2 Roofing
fabrication & installation of eucalyptus
truss, upper and lower cords(10cm
upper and lower rafters 6cm verticals
6.2.1 and diagonals) Ls 1
6.2.2 5*7cm Purlinwood at 90 cm spacing m 18.4
Gauge 32 corrugated iron sheet Roof
6.2.3 cover m2 10.08
6.2.4 Facia Board 20 cm wide m 6.00
gauge 32 galvanized iron guttersheet
6.2.5 corrugated iron m 4.60
DITTO 6.2.5 but 10*15cm down pipe
6.2.6 fixed to wall m 4.00
sub total
7 Door and window
Metal window size 1200x700mm Sheet
metal thickness 2 mm with all
7.1 accessory including lock pcs 1
Metal door size 2100x700mm with
7.2 2mm thick sheet metal pcs 1
supply and install lumps and flush
mounted socket with all necessary
7.3 accessory Ls 1
G.TOTAL No. 2
Unit
No. Descriptions Unit Quantity Amount
Rates
1 Earth Work
Clearing and removal of top soil to an average
1.1 m2 35
depth of 20cm
Bulk excavation for foundation to a depth not
1.2 m3 13.69
exceeding 500mm
Cart away surplus excavated material to a
1.3 m3 20.69
distance not exceeding 1000m
Supply and place 250mm thick basaltic hardcore
1.4 m2 10
blinded with crushed aggregate
Supply and install Trapezoidal drainage ditch
1.5 pipes DN 300mm for surface drainage around M 23.2
water point stand
Subtotal
2 CONCRETE WORK
100mm thick C-20 mass concrete in water point
2.1 m2 10.24
base and on the surface of the hard core
100mm thick concrete class C-20 in manhole
2.2 m2 3
floor and cover
2.3 Ditto, but in water point pillar and seating floor m2 2.89
Subtotal
3 REINFORCEMENT WORK
Supply, cut and fix mild steel reinforcement bars
3.1 of dia.8mm and 10mm for manhole cover, as Kg 8
shown in the drawing
Subtotal
4 FORMWORK
4.1 For water point base m2 0.68
2
4.2 For water point pillar, cover slab and seating floor m 2.32
Sub Total
5 MASONARY WORK
Hard Basaltic or equivalent stone masonry water
5.1 m3 2.85
point wall grouted and filled with 1:3 mortar
400mm thick Basaltic stone or equivalent
5.2 m3 0.58
manhole walls grouted in 1:3 mortar
Sub Total
6 FINISHING WORK
Unit
No. Descriptions Unit Quantity Amount
Rates
Three coats of plastering to internal walls of
6.1 m2 2.52
manhole, using 1:3 mortar
Pointing stone masonry wall of water point with
6.2 m2 8.04
rich mortar
30mm thick sand and cement floor screed 1:3
6.3 m2 22.5
mix ratio
Sub Total
7 PIPES AND ACCESSORIES ALL TRADED
7.1 For four Faucet
7.1.1 G.S pipe 1'' of class 'B' Type m 12
7.1.2 Elbow 90 deg. dia. 1" Pcs 4
7.1.3 Reducer dia. 1"x3/4" Pcs 4
7.1.4 Tee dia. 1” Pcs 3
7.1.5 Faucet dia.3/4" Pcs 4
7.1.6 Water Meter dia. 1" Pcs 1
7.1.7 Gate Valve dia. 1" Pcs 1
7.1.8 socket dia.1" Pcs 4
7.1.9 Nipples dia 1" Pcs 4
7.1.10 Union dia 1" Pcs 2
Subtotal
7.2 For one Faucet (2 in NO.)
7.2.1 G.S pipe 1'' of class 'B' Type m 12
7.2.2 Elbow 90 deg. dia. 1" Pcs 4
7.2.3 Reducer dia. 1"x3/4" Pcs 2
7.2.4 Tee dia. 1” Pcs 3
7.2.5 Faucet dia.3/4" Pcs 1
7.2.6 Water Meter dia. 1" Pcs 1
7.2.7 Gate Valve dia. 1" Pcs 1
7.2.8 socket dia.1" Pcs 4
7.2.9 Nipples Dia 1" Pcs 4
7.2.10 Union Dia 1" Pcs 2
Subtotal
8 FENCE WORK
Supply and erect fence of 40mm*30mm*3mm
angle iron stands c/c spaced at 100cm to a height
8.1 of 2m above ground level with 6 lines of barbed m 26
wire 200mm and 400mm spacing the bottom 4
and upper 2 lines, respectively with cross
Unit
No. Descriptions Unit Quantity Amount
Rates
diagonal & to a depth of 50cm embedded in
concrete foundation of 200mm*200mm.
Item U.
No. Description Unit Qty Price Amount
Apply pointing to all external masonry wall with
3.2 cement mortar ratio (1:3) m2 9
Sub total
4 Pipe and fitting work
4.1 supplying and installing Gs pipes
4.1.1 DN 40mm GI m 12
4.2 supplying and installing fittings for 4 faucets
Item U.
No. Description Unit Qty Price Amount
6 Fence work
Supply and erect fencing of galvanized wire
mesh 80mm GI pipe posts @ 2000mm spacing,
2600mm high (2100mm above OGL) and struts
are to be embedded in concrete C-25 to a depth
of 500 mm as detailed on the drawings including
6.1 earth work and all associated works. m 31
Supply and erect 1850900mm gate of RHS
frame and 2mm thick metal sheet, complete with
6.2 hinges and lock No. 1
Sub total
Total for one school fountain
Unit Total
Item Description Unit Quantity price amount
1 Earth work
Clearing and removal of top soil to average depth
1.1 of 25cm m2 16.34
Excavation in ordinary soil to a depth not greater
1.2 than 800mm m3 52.10
Cart away the excavated material not less than
1.3 500m m3 52.10
Back fill and compacted with selected soil 20cm
1.4 layer by layer m3 13.00
Sub Total
2 Masonry Work
2.1 Stone masonry with cement mortar 1:3 ratio m3 24
2.2 25cm thick hard -core filling m2 56
sub total
3 Concrete works
3.1 2cm thick cement screed m2 56
15cm thick C-20 mass concrete above the hard
3.2 core m3 8.40
C-25 concrete Generator seat, column,
3.4 gradebeam,Intermidate beam & top tie beam
3.4.1 generator seat(25cm) m3 1.40
3.4.3 column m3 2.97
3.4.4 grade beam m3 2.25
3.4.5 top tie beam m3 2.80
3.4.6 for lintel m3 0.60
sub total
4 Reinforcement
4.1 ø14mm bar for column and generator seat kg 143.73
4.2 ø12mm bar for column and generator seat kg 142.21
4.3 ø10mm bar for top tie beam and grade beam kg 75.00
4.4 ø08mm bar stirrups for column & grade beam kg 56.49
4.5 ø06mm bar for stirrups kg 49.00
sub total
5 Supply and construct HCB walling
5.1 class "B" 20cm thick HCB wall m2 120
5.2 class "B" 15cm thick HCB wall m2 15.4
Unit Total
Item Description Unit Quantity price amount
5.3 Plastering of internal HCB wall m2 120
5.4 Plastering of external HCB wall(1:3) ratio m2 130
Rendering to stone H.C.B wall in cement mortar
5.5 (1:3) mix. m2 130.00
Unit Total
Item Description Unit Quantity price amount
Supply and erect fence of 6 lines of Wire mesh
and 400mm spacing, with cross diagonal on angle
iron poles 5cmx4cm*3mm,spaced at 1m interval
and bracers at the corners, embedded in 100mm
concrete around the pole to depth of 500 mm and
11.1 including gate ml 90
Supply and erect 2000mmx2000mm gate with
metal frame and rectangular hollow tube 80mm
RHS Pole including 2mm thick sheet metal door
having three coats of antirust painting including
11.2 hinges and lock. No. 1
supply and install lumps and flush mounted socket
12 with all necessaryaccessory Ls 1
SUB TOTAL
TOTAL
5.4
c. In column lintel and tie beam m3 38.64
3.2 Class C-25 RC for 2 Generator seats m3 1.281
3.3 provide cut, bend and fix in position reinforced
steel bar. All according to structural drawing.
Price shall include tying wires.
a. Diameter 12 mm deformed bar kg 767.43
b. Diameter 10mm deformed bar kg 125.09
c. Diameter 6mm deformed bar kg 21.45078
3.4 supply and fix in position sawn formwork
a. For grade beams, column, lintel and tie beam m2 75.6
Subtotal
8 FENCE WORK
8.1 Supply and erect fancing of galvanized wire m 100.00
mesh and RHS gate as detailed, include for all
intermidatestraining.Gate and 80mm gi pipe
posts @2000mm spacing.2600 mm height (2100
mm above OGL) and struts are to be embeded in
concrete C-25 to a depth of 500mm as detailed
on the drawings
8.2 Supply and erect 4000mm x 1500 mm gate of 80 No 1.00
mm GS pipe poles frame and metal sheet,coplete
with hinges and lock (2mm thick)
Subtotal
Carried to Summary
BOQ:-10. ELECTROMECHANICAL
1.2 26kw control panel board with level sensors with Auto pcs 1
transformer, impedance type, soft starter or equivalent
starting type
1.3 copper wire size 1x1.5sqmm with copper electrodes mtr 400
1.4 vulcanizing kit with chemical epoxy/heat shrink Set 1
1.5 copper power cable from control panel board to motor mtr 148
size 3*25sqmm,flat type cable
1.6 copper power cable from generator to MTS 3x25sqmm mtr 9
1.7 copper power cable from EEPCO to MTS 3x25sqmm mtr 10
1.8 copper power cable from MTS to control panel board mtr 5
3x25sqmm
1.9 Metal body Cable tray, cable tie, cable supports & cable Set 1
lags etc. as required within the system.
1.1 3" medium class GS pipe clamp pair 2
2 Installationof standby diesel generator
2.1 Installation diesel generator set, continuous rating, as per set 1
the technical specification, engine & alternator pre-
installed on a common rigid frame, switchgear panel,
day tank incorporated into the frame, exhaust piping
system, including manufacturer working, service
&maintenance manual, spare part catalogue(fuel and oil
filter, air cleaner, belt, electrical and mechanical toolkit,
etc) and all accessories required for installation with
prime power =70kva, three phase, 400V, 50hz, 1500
RPM.
2.2 Earthling materials, including 25sqmm earthling copper Set 1
cable, 25sqmm, 1.2m length of copper rods, tape
bonding straps etc. as necessary for the earthling
requirements
1.2 26kw control panel board with level sensors with Auto pcs 1
transformer, impedance type, soft starter or equivalent
starting type
1.3 copper wire size 1x1.5sqmm with copper electrodes mtr 400
1.4 vulcanizing kit with chemical epoxy/heat shrink Set 1
1.5 copper power cable from control panel board to motor mtr 148
size 3*25sqmm,flat type cable
1.6 copper power cable from generator to MTS 3x25sqmm mtr 9
1.7 copper power cable from EEPCO to MTS 3x25sqmm mtr 10
1.8 copper power cable from MTS to control panel board mtr 5
3x25sqmm
1.9 Metal body Cable tray, cable tie, cable supports & cable Set 1
lags etc. as required within the system.
1.1 3" medium class GS pipe clamp pair 2
2 Supply of standby diesel generator
2.1 Supply diesel generator set, continuous rating, as per the set 1
technical specification, engine & alternator pre-installed
on a common rigid frame, switchgear panel, day tank
incorporated into the frame, exhaust piping system,
including manufacturer working, service &maintenance
manual, spare part catalogue(fuel and oil filter, air
cleaner, belt, electrical and mechanical toolkit, etc) and
all accessories required for installation with prime power
=70kva, three phase, 400V, 50hz, 1500 RPM.
Rising main
Elevation
IT.NO. Label Easting (m) Northing (m) (m)
1 RM1 397,028.09 1,363,167.03 1,876.64
2 BRR 397,035.61 1,363,230.16 1,874.55
3 BRL 397,034.49 1,363,250.60 1,876.71
4 RM2 397,050.74 1,363,289.58 1,878.20
5 RM3 397,089.89 1,363,323.90 1,880.26
6 RM4 397,187.67 1,363,341.50 1,880.41
7 RM5 397,248.23 1,363,363.28 1,880.95
8 RM6 397,297.56 1,363,405.70 1,880.24
9 GR1 397,340.03 1,363,436.57 1,878.99
10 GL1 397,348.19 1,363,440.68 1,879.25
11 RM7 397,400.45 1,363,481.62 1,881.54
12 RM8 397,436.89 1,363,524.78 1,881.83
13 RM9 397,472.13 1,363,579.31 1,881.78
14 RM10 397,520.81 1,363,630.12 1,880.90
15 RM11 397,518.25 1,363,732.04 1,880.70
16 GR2 397,496.98 1,363,890.37 1,880.90
17 GL2 397,496.79 1,363,901.88 1,881.44
18 RM12 397,489.85 1,363,943.68 1,885.48
19 GL3 397,474.95 1,364,007.64 1,887.59
20 RM13 397,463.78 1,364,046.30 1,890.37
21 RM15 397,453.69 1,364,147.38 1,898.38
22 RM16 397,444.87 1,364,224.67 1,902.57
Elevation
IT.NO. Label Easting (m) Northing (m) (m)
23 GR3 397,448.04 1,364,249.33 1,901.12
24 GL4 397,457.31 1,364,260.59 1,902.86
25 RM17 397,469.06 1,364,293.88 1,910.08
26 RM18 397,472.25 1,364,327.45 1,915.51
27 GM1 397,459.82 1,364,393.66 1,919.27
28 GM2 397,479.73 1,364,449.41 1,917.34
29 GM3 397,477.93 1,364,471.37 1,916.55
30 GM4 397,463.95 1,364,533.38 1,913.18
31 GM5 397,453.64 1,364,576.95 1,910.72
32 GM6 397,439.03 1,364,633.59 1,906.37
33 GM7 397,429.28 1,364,683.66 1,903.02
34 GM8 397,426.81 1,364,722.24 1,899.32
35 GM9 397,419.45 1,364,733.72 1,898.43
36 RR1 397,439.42 1,364,784.18 1,895.66
37 RL1 397,447.85 1,364,817.39 1,894.81
38 GM10 397,453.70 1,364,857.48 1,898.94
39 GM11 397,467.90 1,364,948.20 1,902.71
40 GM12 397,491.43 1,364,995.14 1,904.18
41 GM13 397,521.21 1,365,047.43 1,905.01
42 GM14 397,548.04 1,365,084.97 1,906.05
43 RM19 397,575.51 1,365,134.81 1,906.55
44 RM20 397,617.24 1,365,217.98 1,907.72
45 RM21 397,633.94 1,365,259.07 1,909.85
46 RM22 397,629.21 1,365,406.85 1,914.84
47 RM23 397,628.03 1,365,526.74 1,920.94
48 RM24 397,642.58 1,365,554.88 1,921.88
49 RM25 397,636.74 1,365,606.10 1,922.56
50 GR4 397,641.53 1,365,646.18 1,922.58
51 GL5 397,642.36 1,365,663.80 1,922.15
52 RM26 397,648.57 1,365,752.22 1,927.72
53 RM27 397,640.58 1,365,856.96 1,931.99
54 RM28 397,660.64 1,366,025.95 1,944.93
55 RM29 397,701.21 1,366,088.94 1,952.63
56 RM30 397,726.83 1,366,128.79 1,957.64
57 RM31 397,758.33 1,366,207.13 1,955.88
58 RM32 397,771.16 1,366,252.77 1,956.80
59 RM33 397,785.45 1,366,294.80 1,965.82
60 RM34 397,797.22 1,366,370.65 1,972.37
Elevation
IT.NO. Label Easting (m) Northing (m) (m)
61 RM35 397,777.85 1,366,412.44 1,971.31
62 RM36 397,753.24 1,366,459.65 1,977.25
63 RM37 397,716.47 1,366,485.76 1,978.87
64 RM38 397,628.01 1,366,545.41 1,976.54
65 RM39 397,587.82 1,366,611.14 1,983.85
66 RM40 397,561.52 1,366,651.41 1,989.52
67 RM41 397,548.77 1,366,688.80 1,995.86
68 RM42 397,488.84 1,366,748.78 2,003.36
69 RM43 397,466.98 1,366,772.93 2,006.07
70 RM44 397,416.07 1,366,822.10 2,013.10
71 RM45 397,387.94 1,366,860.33 2,018.12
1. General
o Submersible pump directly coupled to wet submersible motor for pumping ground water
from deep wells.
o Max. external diameter of pump including motor over the cable should be less than the
diameter of the well casing at least by 2’’
2. Motor
o Submersible wet type motor adequate power
o RPM-2900
o Starting can be for pumps having the capacity from 7.5 up to 50kw Auto Transformer.
3. Pump
o Multistage, centrifugal radial type or centrifugal mixed flow type
o Impellers, diffusers, shaft and pump body should be made of stainless steel
o Screwed connection for riser pipes up to four inch and flange connection for riser pipes above
four inches.
o The pump size in diameter includes the pump, cable and cable guard.
4. Clamp
The clamps should have at least 2’’ extra length from the permanent surface casing diameter on
both sides accordingly
For wells with 12’’ production casing permanent surface casing is 14’’
For wells with 10’’ production casing permanent surface casing is 12’’
For wells with 8’’ production casing permanent surface casing is 10’’
The thickness & strength of the clamp should be designed to carry the load/ weight of the pump
& the riser pipe column full of water
o Short-circuit protected with a fuse disconnection switch ahead of the contactor or circuit
breaker, usually a molded type ease ahead of contactor.
o Systems with over current protection relay which is adjustable time and load.
o Ammeter for three phase current measurement and ammeter selection switch
o Indicator lamps for pump running and power on indicator. (green and yellow) red for faulty
o Phase failure relay. (Including under & over voltage protection relay)
6. Power cable
o Four core submersible cable flat type to minimize the pump size
o Cable diameter to be such that the voltage drop at the maximum depth setting is not more
than 2.5% at an ambient temperature of 30.0C
o Cable connected with motor should be with water proof joint to the motor cables.
7. Additional Equipment
o 3 vulcanized electrodes for water level monitoring system to prevent pump from running dry.
o Eight roll with 1.5*1 mm2 control cable for electrodes equal length with power cable for both
submersible and booster pumps(4 roll with the same color where as others different from this
color)
o Cable clamp per 3 meter length for total power cable length (total head) two pairs of pipe
clamp at bore hole mouth with bolts and nuts for the specified pipe diameters on the BOQ
o One or two, according to a number of cable core, jointing kit with quick drying epoxy resin
compound.
8. Technical Information
o The technical information should include but not limited to
o Complete pump performance at duty point and at different heads and discharge.
o Pump HP or KW
o Type of impeller
o Control panel box full details (wiring diagram and spare list)
o Impeller vane thickness, number of vane, vane angle at inlet and outlet of typical stage.
1. Generating sets
General
- Generator set steel base skid mounted with anti-vibration
- Continuous rating output at a power factor of 0.8 and continuous duty cycle at a
maximum permissible temperature.
- Radial or axial ventilated and provided with eye-bolt for lifting
- Insulation resistance between output terminals and earth should be greater than 5MΩ
- Control and main circuits should be protected from over voltage and short circuit
Engine-to includes but not limited to
- AC voltmeter, ammeter, frequency meter, fuel gauge, hour meter, temperature indicator
e.t.c
- Selection switch for both voltmeter and ammeter
Supply of spare parts
Engine
Generally Generator
This specification shall be taken as standard, for an internal combustion engine as prime mover
diesel generating sets
1.2 Engine (Fundamental)
The engine shall be capable of operating at its rated speed loaded to its rated capacity on hazardous
working environment, at ambient air temperature and relative air humidity variations specified in
art.1-2 without evidence of ever loading the capacity of the engine.
1.3 Horse Power
The required minimum Brake Horse BHP, as per ISO standard power specified for the respective
equipment in sec. 2 shall be delivered by the engine at the flywheel at its rated speed at standard
reference at condition with all required accessories.
The rating of the engine bid upon should be specified in accessories with ISO standard power. If
other standards are taken the following points should be specified clearly.
o Standard accessories
A certified engine data showing, at least, net horse power, (continuous, intermittent and maximum)
torque performance curves, specific fuel consumption curve at 2536 meters elevation shall be
submitted with appropriate data from the company.
1.4 Cooling System (Water Cooled or Air Cooled)
1.4.1 Water Cooled
Shikur, Alemayehu & friends Wash Consulting Firm 98
Amhara Water, Irrigation and Energy Bureau Bursa Kebele Water Supply Final Design Report
The cooling system unless otherwise specified in sec. 2 shall be of the closed, pressurized, pump
forced type. The radiator and water passages in the cylinder block shall be of ample capacity to
permit continuous full Load operation of the engine without boiling of the coolant at atmospheric
air temperature up to 750c.
The radiator shall be heavy duty construction, properly mounted to withstand shocks and strain
likely to be encountered in operation under the conditions of operation described under art.1-2.
The cooling system shall incorporate and efficient thermostat to effect prompts warming of the
proper engine temperature.
1.4.2 Air Cooled
If air cooled the air blower capacity and the cooling fin arrangement shall be sufficient to permit
continuous full load operation of the engine without overheating the engine at atmospheric air
temperature of about 570c.
Velocity of cooling air should be sufficiently high to prevent formation of dust deposits which
could impair the cooling efficiency. The finish shall have adequate area for prompt and efficient
cooling.
Full details regarding the type, capacity of the radiator/blower and the cooling system shall be
submitted with the bid.
1.5 Lubrication System;
The lubrication system shall be powered by a mechanically driven gear type positive displacement
pump of ample capacity to operate at any desired ambient air temperature and altitude.
The system shall be equipped with suitable Engine oil pump, dual centrifugal and full flow-filters
and suitably arranged oil passages in the cylinder block.
Full details regarding the type, capacity of the pump, the pump and filters and the lubrication
system shall be submitted with the bid.
1.6 Fuel System;
The fuel system shall include a mechanically driven fuel pump with all necessary regulator and
controlling attachments.
The system shall incorporate easily accessible, interchangeable and readily removable injectors,
fitters of adequate capacity and construction heavy duty oil bath or dry type air cleaner or adequate
capacity for the size and type of engine bid upon.
Manufacturer’s standard fuel tank shall be acceptable, unless otherwise stated and shall be located
so as not to be affected by heat from the engine, exhaust pipe, or muffler.
Complete specification data relating to the diesel engine fuel injection system shall be submitted by
bidder.
The system shall incorporate easily accessible, interchangeable and readily removable injectors,
filters of adequate capacity and construction heavy duty oil bath or dry type air cleaner or adequate
capacity for the size and type of engine bid upon.
Manufacturer’s standard fuel tank shall be acceptable, unless otherwise stated and shall be located
so as not to be affected by heat from the engine, exhaust pipe, or muffler,
Complete specification data relating to the diesel engine fuel injection system shall be submitted by
bidder.
1.7. Electrical System;
The engine shall be provided with a complete electrical charging, starting, electrical switch,
preheating switch, preheating switch and at least two keys.
The engine shall start satisfactorily at temperatures as low as 00c. The generator or alternator shall
be the manufacturer’s standard production model and shall be adequate to provide service under
normal operation conditions.
1.8 Tests on Completion
On delivery to Site, the Plant will be visually inspected, and any Plant with obvious defects will be
rejected.
The Contractor’s main Bid shall comply fully with the Specification.
The Contractor is however at liberty to include alternative items of Plant, which do not completely
comply with the requirements of the Specification provided that he submits manufacturer’s
detailed descriptions of alternatives and draws attention to any aspect of each component which
does not fully comply with the requirements of this Specification. These detailed descriptions,
including any departure from the requirements of the Specification may, after approval by the
Employer, be included among the Contract documents and each item shall be in accordance with
the description of it. Approval of a manufacturer’s description shall not include approval of any
departure from the requirements of the Specification unless the departure is specifically approved
by the Employer in writing. The Employer however, may not necessarily accept any alternative put
forward.