AHU & FCU Installation
Page 1 of S
I Rev. 0 0

BBCC Parcel 2

METHOD STATEMENT

A H U & FCU Installation

APPROVALS

PREPARED BY REVIEWED BY APPROVED BY

Signature: s t f Signature : Signature:


J
/ f ^

Name Name: Name:


Jason Beh

Designation: p r o ject Executive Designation: Designation :

Date: slh April 2019 Date : Date :

REVISIONS RECORD

REV. DATE ISSUED REVISION DESCRIPTION APPROVAL STATUS


Doc.No BBCC-SC>YL/MS/003/R0/Jason

l l i l OJiS YOKE! UHSdn.Ohd.


M E T H O D STATEMENT
Warn R
{ & 6) Effective date 8 t h A p r i l 2019
AHU & FCU Installation
Page 2of n Rev, 00

TABLE OF CONTENT

Items Description Pages

1 General 3

2 Objective & Scope of W o r k 3

3 Management Responsibilities 4-7

4 Plant, Machineries & Material 7

5 Materials & Technical Data 8

6 Procedure & Construction Methodology 9

7 Quality Control & Documentation 10-11

8 Safe W o r k Plan 11
Doc.No BBCC-SOYL/MS/003/R0/Jason

J B 1 ONQ YOKE i l H 5dn. Ohd.


M E T H O D STATEMENT
fflj| 36 r-ft 85 ti to •» S) Effective date 8 i h A p r i l 2019
AHU & FCU Installation
Page 3 o f 11 Rev. 0 0

1.0 GENERAL

This m e t h o d s t a t e m e n t covers on-site installation o f pipeworks f o r Bukit Bintang City

Centre (BBCC) at Jalan Pudu, Wilayah Persekutuan. This m e t h o d statement will describe

t h e installation o f pipeworks.

2.0 OBJECTIVE & SCOPE OF W O R K

The objective is t o o u t l i n e t h e w o r k m e t h o d o f p i p e w o r k installation. The w o r k shall b e

applied t o supply, deliver, install, testing and commissioning o f p i p e w o r k in accordance

t o approved shop d r a w i n g and specification.


Doc.No BBCC-SOYL/MS/003/R0/Jason

S g l ONS YOKE l ! N Sdn. Olid


M E T H O D STATEMENT
m m lii fji s f K s i Effective d a t e 8 t h A p r i l 2019
AHU & FCU Installation
Page 4 o f 11 Rev. 00

3.0 M A N A G E M E N T RESPONSIBILITIES

3.1 Project Organization Chart


Doc.No BBCC-SOYL/MS/003/R0/Jason
/%®M
S i i
V.".'
OKS YOKE UN 5dn. Bhd.
M E T H O D STATEMENT
p U B & fel K '/> is] Effective d a t e 8 t h April 2019
A H U & FCU Installation
Page 5 o f 11 Rev. 00

3.2 Project Personnel Job Description(s)

a) Project M a n a g e r

The Project M a n a g e r is responsible f o r t h e overall execution o f t h e f i e l d w o r k

surrounding a research initiative and t o ensure t h e project's success. She/he w o r k s

directly w i t h t h e client t o d e v e l o p t h e project schedule, define t h e research

instrument develop an analysis plan and coordinate all communications. The Project

M a n a g e r also oversees t h e planning, i m p l e m e n t a t i o n and tracking o f a specific

project, and t o ensure t h a t t h e w o r k d o n e is accordingly t o t h e r e q u i r e m e n t a n d

specifications.

b) Project Engineer

The Project Engineer is responsible f o r all construction matters related t o t h e w o r k

as established by contract and regulatory requirements. She/he reports t o t h e

Project M a n a g e r and responsible f o r t h e c o n t r o l o f effective undertaking a n d

c o m p l e t i o n o f all construction / installation activities w i t h t h e assistance o f Project

Coordinator. The Project Engineer works directly with main-contractor, sub­

c o n t r a c t o r s ) and a n y t h i r d party contractor involved in t h e project.


Doc.No BBCC-SOYL/MS/OOS/RO/Jason

Jill oris YOKE UN Sdn. ( M


M E T H O D STATEMENT
II!! ® sa M
5 & hi Effective d a t e 8 l h April 2019
AHU & FCU Installation

Page 6 o f 11 Rev. 00

b) Project C o o r d i n a t o r ( Q A / QC Personnel)

The Project Coordinator, in t h e area o f inspection and testing activities, reports t o

t h e Project Engineer in relation t o t h e activities. The Project C o o r d i n a t o r is

responsible f o r t h e receipt issue, distribution, recording, transmission, filling a n d

archiving o f all d o c u m e n t a t i o n as p e r d o c u m e n t c o n t r o l procedures.

c) The Project C o o r d i n a t o r is involved b u t n o t limited in t h e area as:-

i) Maintenance o f drawings and d o c u m e n t s registers

ii) Ensuring information, instructions, requisition o r works report is in p r o p e r

circulation.

iii) To record and collect instruction / i n f o r m a t i o n f r o m t h e Consulting Engineer

/ A r c h i t e c t and prepare d r a f t copies o f shop d r a w i n g / a s - b u i l t drawings f o r

Drafting Division t o incorporate f o r submission o f approval.

d) Site Supervisor(s)

The Project Foreman is responsible t o m o n i t o r t h e site progress closely and ensure

t h e w o r k d o n e safely, hence t o ensure t h e workers are c o m p l y i n g w i t h t h e health

and safety regulation, d a y - t o - d a y basis. She/he is also responsible t o handle site

daily, inspection and progress r e p o r t t o t h e Project M a n a g e r and Project Engineer.


Doc.No BBCC-SOYL/MS/OOS/RO/Jason

i l l OHaYOKnitJSdfi. O M
M E T H O D STATEMENT
• I a <ki H & h]
P Effective date 8 t h April 2019
A H U & FCU Installation
Page 7of I I Rev. 00

e) Foreman

The Foreman is t o report t o t h e Project C o o r d i n a t o r f o r site activities, and t o ensure

ail t h e installation works are according t o t h e requirement and specification. The

Foreman works closely w i t h t h e Site Supervisor.

4.0 PLANT, MACHINERIES & MATERIAL

Machineries, Equipment & Tools

Item Description(s)

Rollers To mobilize t h e units f r o m o n e place t o another.

T o use as t e m p o r a r y staging f o r s u p p o r t workers and material


Scaffolding
d u r i n g installation.

Drill H a m m e r s To drill holes f o r d r o p - i n a n c h o r installation.

Spanner / Screwdriver T o t i g h t e n t h e screw.


Doc.No BBCC-SOYL/MS/OOS/RO/Jason

M m OMG YOKE i.lfj Sdn. Obd


M E T H O D STATEMENT
|||j| s f& m ti pa»ro Effective date 8 t h A p r i l 2019
AHU & FCU Installation
Page 8 o f 11 Rev. 00

5.0 MATERIALS TECHNICAL D A T A

Piease refer t o t h e a t t a c h m e n t f o r t h e schedule o f e q u i p m e n t selection.


Doc.No BBCC-SOYL/MS/003/R0/Jason

i l l OHG YOKE UN Sdn. Bhd. M E T H O D STATEMENT


I j g l Sri W
!fiti -Fi E « r} Effective d a t e 8 t h April 2019
AHU & FCU Installation
Page 9 o f 11 Rev. 00

6.0 PROCEDURE & CONSTRUCTION METHODOLOGY

Please refer t o t h e attachmen t f o r t h e r e c o m m e n d e d installation instruction f r o m t h e

manufacturer.
Doc.No BBCC-SOYL/MS/OOS/RO/Jason

| | | | Of/a YOKE UN Sdn. OhcJ.


M E T H O D STATEMENT
I * .IS (ft ft ft m « fij Effective d a t e 8 t h A p r i l 2019
A H U & FCU Installation
Page 10 o f 11 Rev. 00

7.0 QUALITY CONTROL & D O C U M E N T A T I O N

7.1 Coordination

Logistic and c o o r d i n a t i o n w i t h o t h e r contractors are d o n e :

a. Daiiy M & E c o o r d i n a t i o n meetings chaired b y t h e Main Contractor and a t t e n d e d

b y all subcontractors.

b. D a y - t o - d a y matters requiring subcontractors' c o o p e r a t i o n are resolved a m o n g

Main Contractor, Project Engineer and representatives o f o t h e r contractors.

7.2 Shop Drawing & Material A p p r o v a l

The subcontractors responsible f o r t h e installation o f air-conditioning a n d mechanical

ventilation services will s u b m i t shop drawings accompanied b y full technical details

and literature t o g e t h e r w i t h samples o f f i t t i n g s and materials f o r inspection a n d

approval b y t h e Project Engineer.

7.3 Delivery o f Material t o Site

A n y material delivered t o site, t h e Q A / Q C shall be informed and inspected by

consultant's site staffs and shall be p r o v e d w i t h delivery o r d e r (DO). All e q u i p m e n t

and materials will be handled in such a m a n n e r as n o t t o d a m a g e t h e i t e m and hence

its performance. Damaged, dented, o r rejected material shall be r e m o v e d f r o m site

immediately.
Doc.No BBCC-SOYL/MS/OG3/RO/Jason

Jgfffil OHG YOKE UH Sdn. Olid.


M E T H O D STATEMENT
|||| <£ 6j) S f-R ft H3 Effective d a t e 8 t h A p r i l 2019
AHU & FCU Installation
Page 1 of 11 Rev. 00

7.4 Inspection Checklist

Please refer t o t h e A p p e n d i x f o r t h e inspection checklist.

8.0 SAFE W O R K PLAN

Please refer t o t h e attachm e n t f o r t h e Job Safety Analysis Worksheet.

i
JOB SAFETY ANALYSIS WORKSHEET

Title of Job Operation : Installation o f A H U / F C U Installation

Plant/Department/Unit : Air Conditioning & Mechanical Ventilation System

Area / Equipment : General Area

Date

All workers shall wear minimum persona! protective equipment as stipulated in the HSE Manuals and Procedures. If the job involves special
task and/or hazardous chemical, additional personal protective equipment shall be worn as stipulated in the above said HSE manual and
accordinq to matrix for Additional PPE Requirements.

Recommended Safe Job


Sequence of Basic Job Steps Potential Accidents of Hazards
Procedure
Installation ofAHU/FCU Installation
1. Room & Pathway Cle a r a n ce : Falling from height - minor Permit to Work obtain from HSE Dept.
- Work area is permitted for access Personal i n j u r y - m i n o r Adequate ventilation and lighting
- Adequate ventilation and lighting for Manual H a n d l i n g - m i n o r provided.
work area Tools and equipment is in good condition
- Tools and equipment are available for and inspected before work commence.
the work. Unloading machineries must be in good
- Mobile crane(s)/machineries are condition and inspected before delivered
available for the work. to site.
- Proper access and egress is available Enclosed Work Permit obtained a n d
approved by HSE Dept.

2. Unloading A r e a : Manual Handling - High Permit to Work obtain from W C T C and


- External road surface/condition must Personal injury - Major Internal PTW obtain from HSE Dept.
be able to withstand the weight o f the Falling from height - Major Work supervision/attention b y supervisors
units itselves or heavy transportation, at all time.
e.g. mobile crane, transportation etc.
- Work area is permitted for access
- Proper access and egress is available

3. To measure and install hanger a n d Manual Handling - Low Permit to Work obtain from W C T C and
supports. Personal injury - minor/major Internal P T W obtain from HSE Dept.
Falling from height - minor/major Adequate ventilation and lighting
provided.
Work supervision by supervisor at all
time.
4. Demobilization from working area. Falling from height - minor/major Use proper PPE and tools.
Personal injury - minor/major Housekeeping.
Manual Handling - L o w Risk
To be filled out by Approving Authority and Receiving Authority Before Starting The Work,
•••: Name Department Position Initial
Approving
Authority

Chaired By:
Reviewed By:
Receiving
Authority
Work Leader
Working Team
Names
Working Team
Names
Working Team
Names