Resource Management in MSP (Part 3)

___________________________________________________________________________
Exercise Description:

1. Create the following resource pool for “Pilot Residential Project”


RESOURCE NAME MAX AVAILABLE STD. RATE
UNITS
SHOVEL 2 Rs.1000/hr
CONCRETE MIXER 1 Rs.200/hr
NEEDLE VIBRATOR 3 Rs. 50/hr

2. Assign the above resources to activities:

Pilot Residential Project


Project Start
Mobilization and Sub-structure works
Site Mobilization
Layout
Construction Phase
Substructure
Excavation Shovel (2)
Foundations Concrete Mixer (1) Needle Vibrator (2)
G.Floor Works
Walls and Columns Concrete Mixer (1) Needle Vibrator (2)
Roof slab Concrete Mixer (1) Needle Vibrator (2)
Conduiting and water and sanitary
pipes
Fixing of wooden frames and plastering
Kitchen and toilet tiling
Flooring
Terrace Works
Parapet, Waterproofing etc.
Services
Terrace Finish
External Works
Outside plastering
External services and Boundary wall
Paths and Pavements
Boundary wall gates
Final Finishes
Doors and Windows fixing
Internal Painting (Initial Coats)
External Painting (Initial Coats)
Wood Polishing
Hardware, Sanitary, Plumbing, Electrical
fixtures fixing
Final coats (Internal and External
painting)
Project Closure
Defects Rectification and Handing over
Project finish

3. A lump sum provision of 10% of activity cost can be considered for petty tools & tackles to
be used in each activity.