C8 Plot 2 - Baseline Work Programme Rev00 (Detail) - Updated As of 31 January 2024 1 1
C8 Plot 2 - Baseline Work Programme Rev00 (Detail) - Updated As of 31 January 2024 1 1
KEDAI SERBANEKA, KEDAI MAKAN PANDU-LALU, KAWASAN LAPANG DAN TAMAN DI ATAS LOT PT87270, SEBAHAGIAN PLOT C8, DI PERSIARAN
KWASA UTAMA, SEKSYEN U4, KWASA DAMANSARA, 40160 SHAH ALAM, SELANGOR DARUL EHSAN UNTUK TETUAN KWASA UTAMA SDN BHD
(“PROJECT”)
PRECONSTRUCTION 448 09-May-23 08-Nov-24 09-May-23 A 08-Nov-24 75.65% 75.95% 0 08-Nov-24, PRECONSTRUCTION
MILESTONE DATES 448 09-May-23 08-Nov-24 09-May-23 A 08-Nov-24 0% 0% 0 08-Nov-24, MILESTONE DATES
100 Project Commencement 0 09-May-23 09-May-23 A 100% 100% Project Commencement
101 Project Completion / Handover 0 08-Nov-24 08-Nov-24* 0% 0% 0 Project Completion / Handover
PRELIMINARY WORKS 395 09-May-23 06-Sep-24 09-May-23 A 06-Sep-24 70.00% 74.22% 8 06-Sep-24, PRELIMINARY WORKS
102 Mobilization 14 09-May-23 25-May-23 09-May-23 A 25-May-23 A 100% 100% Mobilization
103 Joint Inspection with Consultant 7 09-May-23 17-May-23 09-May-23 A 17-May-23 A 100% 100% Joint Inspection with Consultant
104 OGL & Setting Out Pre Comp Survey 9 17-May-23 27-May-23 17-May-23 A 26-May-23 A 100% 100% OGL & Setting Out Pre Comp Survey
105 Appointment of Contractor 14 09-May-23 25-May-23 09-May-23 A 25-May-23 A 100% 100% Appointment of Contractor
112 Preliminaries 395 09-May-23 06-Sep-24 09-May-23 A 06-Sep-24 68.00% 73% 8 Preliminaries
LONG LEAD ITEM 343 23-Jun-23 16-May-24 15-Jun-23 A 01-Jun-24 79.11% 76.62% 44 01-Jun-24, LONG LEAD ITEM
ROOFING WORKS 289 01-Aug-23 04-Mar-24 01-Aug-23 A 02-Apr-24 88.15% 85.43% 11 02-Apr-24, ROOFING WORKS
ROOF STRUCTURE 269 01-Aug-23 23-Feb-24 01-Aug-23 A 15-Mar-24 91.24% 82.94% 0 15-Mar-24, ROOF STRUCTURE
SAMPLE SUBMISSION 77 01-Aug-23 04-Sep-23 01-Aug-23 A 22-Nov-23 A 100% 100% 22-Nov-23 A, SAMPLE SUBMISSION
110 Submission 21 01-Aug-23 25-Aug-23 01-Aug-23 A 24-Aug-23 A 100% 100% Submission
111 Approved 7 25-Aug-23 04-Sep-23 25-Aug-23 A 22-Nov-23 A 100% 100% Approved
SHOP DRAWINGS / METHOD STATEMENT SUBMISSION 40 04-Sep-23 31-Oct-23 01-Sep-23 A 08-Dec-23 A 100% 100% 08-Dec-23 A, SHOP DRAWINGS / METHOD STATEMENT SUBMISSION
113 Submission 40 04-Sep-23 23-Oct-23 01-Sep-23 A 23-Oct-23 A 100% 100% Submission
114 Approved 7 23-Oct-23 31-Oct-23 02-Oct-23 A 08-Dec-23 A 100% 100% Approved
FABRICATION 90 31-Oct-23 23-Feb-24 08-Dec-23 A 15-Mar-24 84.2% 69.23% 0 15-Mar-24, FABRICATION
116 Production Commencement 90 31-Oct-23 22-Feb-24 08-Dec-23 A 15-Mar-24 85.14% 70% 0 Production Commencement
117 Delivery to Site 1 22-Feb-24 23-Feb-24 21-Feb-24 22-Feb-24 0% 0% 0 Delivery to Site
ROOF COVERING 225 10-Aug-23 04-Mar-24 18-Aug-23 A 02-Apr-24 85.42% 87.63% 11 02-Apr-24, ROOF COVERING
SAMPLE DRAWING 63 10-Aug-23 13-Sep-23 18-Aug-23 A 29-Aug-23 A 100% 100% 29-Aug-23 A, SAMPLE DRAWING
121 Submission 21 10-Aug-23 05-Sep-23 18-Aug-23 A 18-Aug-23 A 100% 100% Submission
122 Approved 7 05-Sep-23 13-Sep-23 21-Aug-23 A 29-Aug-23 A 100% 100% Approved
SHOP DRAWINGS / METHOD STATEMENT SUBMISSION 40 13-Sep-23 09-Nov-23 30-Sep-23 A 03-Jan-24 A 100% 100% 03-Jan-24 A, SHOP DRAWINGS / METHOD STATEMENT SUBMISSION
124 Submission 40 13-Sep-23 01-Nov-23 30-Sep-23 A 31-Oct-23 A 100% 100% Submission
125 Approved 7 01-Nov-23 09-Nov-23 26-Oct-23 A 03-Jan-24 A 100% 100% Approved
FABRICATION 90 09-Nov-23 04-Mar-24 04-Dec-23 A 02-Apr-24 75.56% 79.28% 11 02-Apr-24, FABRICATION
127 Production Commencement 90 09-Nov-23 02-Mar-24 04-Dec-23 A 02-Apr-24 76.25% 80% 11 Production Commencement
128 Delivery to Site 1 02-Mar-24 04-Mar-24 21-Feb-24 21-Feb-24 0% 0% 11 Delivery to Site
ARCHITECTURAL WORKS 223 04-Sep-23 16-May-24 01-Jul-23 A 01-Jun-24 59.03% 54.55% 36 01-Jun-24, ARCHITECTURAL WORKS
CURTAIN WALL GLASS 216 04-Sep-23 16-May-24 01-Sep-23 A 01-Jun-24 58.68% 60.98% 18 01-Jun-24, CURTAIN WALL GLASS
SAMPLE SUBMISSION 21 04-Sep-23 09-Oct-23 01-Sep-23 A 02-Dec-23 A 100% 100% 02-Dec-23 A, SAMPLE SUBMISSION
133 Submission 21 04-Sep-23 30-Sep-23 01-Sep-23 A 18-Sep-23 A 100% 100% Submission
134 Approved 7 30-Sep-23 09-Oct-23 19-Sep-23 A 02-Dec-23 A 100% 100% Approved
SHOP DRAWINGS / METHOD STATEMENT SUBMISSION 52 09-Oct-23 08-Dec-23 09-Oct-23 A 01-Feb-24 100% 99.82% 18 01-Feb-24, SHOP DRAWINGS / METHOD STATEMENT SUBMISSION
136 Submission 45 09-Oct-23 30-Nov-23 09-Oct-23 A 13-Dec-23 A 100% 100% Submission
137 Approved 7 30-Nov-23 08-Dec-23 21-Oct-23 A 01-Feb-24 100% 99% 18 Approved
FABRICATION 120 08-Dec-23 16-May-24 01-Jan-24 A 01-Jun-24 36.05% 39.67% 18 01-Jun-24, FABRICATION
139 Production Commencement 120 08-Dec-23 15-May-24 01-Jan-24 A 31-May-24 36.35% 40% 18 Production Commencement
140 Delivery to Site 1 15-May-24 16-May-24 31-May-24 01-Jun-24 0% 0% 18 Delivery to Site
TILES 190 25-Sep-23 05-Apr-24 15-Sep-23 A 05-Apr-24 65.89% 70.59% 78 05-Apr-24, TILES
PILING & FOUNDATION WORKS 189 23-May-23 21-Dec-23 23-May-23 A 21-Dec-23 A 100% 100% 21-Dec-23 A, PILING & FOUNDATION WORKS
PILING WORKS (41 nos) 12 23-May-23 24-Jun-23 23-May-23 A 23-Jun-23 A 100% 100% 23-Jun-23 A, PILING WORKS (41 nos)
225 Mobilization of Piling Machine & MLT Test 7 23-May-23 31-May-23 23-May-23 A 30-May-23 A 100% 100% Mobilization of Piling Machine & MLT Test
ZONE A (30 nos) 4 31-May-23 15-Jun-23 31-May-23 A 14-Jun-23 A 100% 100% 14-Jun-23 A, ZONE A (30 nos)
227 GL A-B/14 (6 nos) 2 31-May-23 02-Jun-23 31-May-23 A 01-Jun-23 A 100% 100% GL A-B/14 (6 nos)
229 GL B-B1/14 (9 nos) 4 02-Jun-23 07-Jun-23 02-Jun-23 A 06-Jun-23 A 100% 100% GL B-B1/14 (9 nos)
231 GL C/5 (4 nos) 2 07-Jun-23 09-Jun-23 07-Jun-23 A 08-Jun-23 A 100% 100% GL C/5 (4 nos)
233 GL C/4 (3 nos) 1 09-Jun-23 10-Jun-23 09-Jun-23 A 09-Jun-23 A 100% 100% GL C/4 (3 nos)
235 GL C-D/4-5 Lift Pit (8 nos) 4 10-Jun-23 15-Jun-23 10-Jun-23 A 14-Jun-23 A 100% 100% GL C-D/4-5 Lift Pit (8 nos)
ZONE B (11 nos) 4 15-Jun-23 24-Jun-23 15-Jun-23 A 23-Jun-23 A 100% 100% 23-Jun-23 A, ZONE B (11 nos)
238 GL D/4 (2 nos) 1 15-Jun-23 16-Jun-23 15-Jun-23 A 15-Jun-23 A 100% 100% GL D/4 (2 nos)
240 GL F3a/3-4 (9 nos) 4 16-Jun-23 21-Jun-23 16-Jun-23 A 20-Jun-23 A 100% 100% GL F3a/3-4 (9 nos)
241 PDA Test 3 21-Jun-23 24-Jun-23 21-Jun-23 A 23-Jun-23 A 100% 100% PDA Test
FOUNDATION WORKS 189 24-Jun-23 21-Dec-23 24-Jun-23 A 21-Dec-23 A 100% 100% 21-Dec-23 A, FOUNDATION WORKS
ZONE A 178 08-Jul-23 01-Nov-23 06-Jul-23 A 21-Dec-23 A 100% 100% 21-Dec-23 A, ZONE A
RAFT FOUNDATION & STUMPS 16 08-Jul-23 29-Sep-23 06-Jul-23 A 02-Sep-23 A 100% 100% 02-Sep-23 A, RAFT FOUNDATION & STUMPS
RAFT FOUNDATION 9 08-Jul-23 26-Aug-23 06-Jul-23 A 25-Aug-23 A 100% 100% 25-Aug-23 A, RAFT FOUNDATION
GL A-B1/11-8 (LG2) 5 08-Jul-23 01-Aug-23 08-Jul-23 A 25-Aug-23 A 100% 100% 25-Aug-23 A, GL A-B1/11-8 (LG2)
247 Excavation/Leveling 2 08-Jul-23 11-Jul-23 08-Jul-23 A 11-Jul-23 A 100% 100% Excavation/Leveling
248 Lean Con & Anti Termite To RF 2 11-Jul-23 13-Jul-23 11-Jul-23 A 15-Jul-23 A 100% 100% Lean Con & Anti Termite To RF
249 Formwork to RF 5 13-Jul-23 20-Jul-23 17-Jul-23 A 01-Aug-23 A 100% 100% Formwork to RF
250 Reinforcement to RF 4 21-Jul-23 26-Jul-23 02-Aug-23 A 21-Aug-23 A 100% 100% Reinforcement to RF
251 Casting To RF 5 26-Jul-23 01-Aug-23 22-Aug-23 A 25-Aug-23 A 100% 100% Casting To RF
GL B-D/1a-2a (LG1) 9 01-Aug-23 26-Aug-23 06-Jul-23 A 22-Jul-23 A 100% 100% 22-Jul-23 A, GL B-D/1a-2a (LG1)
253 Excavation/Leveling 6 01-Aug-23 08-Aug-23 06-Jul-23 A 11-Jul-23 A 100% 100% Excavation/Leveling
254 Lean Con & Anti Termite To RF 4 08-Aug-23 12-Aug-23 12-Jul-23 A 15-Jul-23 A 100% 100% Lean Con & Anti Termite To RF
255 Formwork to RF 5 12-Aug-23 18-Aug-23 17-Jul-23 A 19-Jul-23 A 100% 100% Formwork to RF
256 Reinforcement to RF 4 19-Aug-23 24-Aug-23 19-Jul-23 A 21-Jul-23 A 100% 100% Reinforcement to RF