Purva Clermont-Dec22-1673427060
Purva Clermont-Dec22-1673427060
Tower A
TOWER MILESTONES
STATUS ACHIEVED
• Slab shuttering works • Basement 1 slab / plinth slab
above ground level in completed.
progress.
UPCOMING
MILESTONES
• Completion of podium slab casting.
PROGRESS TIMELINE
Construction Updates
Tower B
TOWER MILESTONES
STATUS ACHIEVED
• Plinth slab completed. • Plinth slab completed.
UPCOMING
MILESTONES
• Podium slab reinforcement works.
PROGRESS TIMELINE
Construction Updates
Tower C
TOWER MILESTONES
STATUS ACHIEVED
• Basement 1 base slab • B1 base slab completed.
casting completed.
UPCOMING
MILESTONES
• Completion of plinth slab work.
PROGRESS TIMELINE
Construction Updates
Tower D
TOWER MILESTONES
STATUS ACHIEVED
• Plinth shuttering works in • Completion of B1 base slab completed.
progress.
UPCOMING
MILESTONES
• Completion of plinth slab work.
PROGRESS TIMELINE
Construction Updates
Tower E
TOWER MILESTONES
STATUS ACHIEVED
• Excavation works in • Stressing works for shore piling
progress. completed.
UPCOMING
MILESTONES
• Completion of foundation work.
PROGRESS TIMELINE
December 22
Construction Updates
Site Office :
Purva Clermont
Off Sion - Panvel Expy, Chembur, Mumbai, Maharashtra – 400088
Regional Office :
Puravankara Limited. #130/1, Ulsoor Road,
Bengaluru - 560 042
Web : www.puravankara.com