Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

December 2022

Tower A

TOWER MILESTONES
STATUS ACHIEVED
• Slab shuttering works • Basement 1 slab / plinth slab
above ground level in completed.
progress.

UPCOMING
MILESTONES
• Completion of podium slab casting.

Actual site photograph

PROGRESS TIMELINE

September 22 October 22 November 22 December 22

Construction Updates
Tower B

TOWER MILESTONES
STATUS ACHIEVED
• Plinth slab completed. • Plinth slab completed.

UPCOMING
MILESTONES
• Podium slab reinforcement works.

Actual site photograph

PROGRESS TIMELINE

September 22 October 22 November 22 December 22

Construction Updates
Tower C

TOWER MILESTONES
STATUS ACHIEVED
• Basement 1 base slab • B1 base slab completed.
casting completed.

UPCOMING
MILESTONES
• Completion of plinth slab work.

Actual site photograph

PROGRESS TIMELINE

September 22 October 22 November 22 December 22

Construction Updates
Tower D

TOWER MILESTONES
STATUS ACHIEVED
• Plinth shuttering works in • Completion of B1 base slab completed.
progress.

UPCOMING
MILESTONES
• Completion of plinth slab work.

Actual site photograph

PROGRESS TIMELINE

September 22 October 22 November 22 December 22

Construction Updates
Tower E

TOWER MILESTONES
STATUS ACHIEVED
• Excavation works in • Stressing works for shore piling
progress. completed.

UPCOMING
MILESTONES
• Completion of foundation work.

Actual site photograph

PROGRESS TIMELINE

December 22

Construction Updates
Site Office :
Purva Clermont
Off Sion - Panvel Expy, Chembur, Mumbai, Maharashtra – 400088

Regional Office :
Puravankara Limited. #130/1, Ulsoor Road,
Bengaluru - 560 042

Email : crm@puravankara.com (Subject line – Project name/ unit number)

Call Us : +91 - 80-67724001 / 1 860 208 0000

Web : www.puravankara.com

Maha RERA Registration Number :


(P51800028571), (P51800028427), (P51800028428)
(P51800028494), (P51800028492)

You might also like