Professional Documents
Culture Documents
PAPER 2 Test Content
PAPER 2 Test Content
- LUMP SUM
- ACTIVITY SCHEDULE
- BILL OF QUANTITIES
- COST REIMBURSABLE
- TARGET COST
- ALTERNATIVE STARTAGIES
- The parties
- Description of the works
- The agreed price
- The period of construction
FORMS OF SUB-CONTRACTS
Roles and relationships of the Subcontractor relate to the management of Risks between the employer, the
principal contractor, and the subcontractor. The risks will relate to the following:
Forms of Subcontractors
1. Direct Subcontractors
o The employer engages a direct contractor to carry out certain work alongside the main
contractor while the main building contractor is on the site.
o The main building contractor is not responsible of his performance.
o Any delay caused by the direct contractor may cause the contractor an extension of time.
o Should the direct contractor default, any additional costs incurred will be for the employer
2. Selected subcontractors
o A subcontractor which is selected Jointly by the main contractor and by the employer / agent.
o The main contractor is liable
o Not entitled to an extension of time
o Should the direct contractor default, any additional costs incurred will be for the main contractor
The Employer Warrants that the principle agent has = Full AUTHORITY AND OBLIGATION to ACT and BIND the
employer in terms of the agreement.
CLAUSE 12 = EXECUTION
On being given possession of the site, the contractor shall commence with the works within TEN Working days, and
proceed with: DUE DILIGENCE, REGULARITY, EXPEDITION, SKILL & APPROPREATE RESOURCES. To bring the works
to practical completion and to Final completion.
Practical Completion = State of completion that has been certified by the principal agent & the Works have been
completed free of PATENT defects (Other than Minor defects) and can be used for the intended purpose. the works
must be SAFE FOR USE
You are therefore obligated to Monitor the progress + Inform the Contractor of the outstanding work to be
completed to achieve PRACTICAL COMPLETION
Revision of date of practical completion: The contractor is entitleD to the REVISION of the date of practical
completion (granted by the principle agent) Either With or Without an adjustment to the contract value. (TIME AND
COST – The cost is directly related to the delay in the project and decided in the contract data)
The contractor may: Give notice to TERMINATE the agreement where the employer has failed to: or if the Principal
agent has FAILED TO ISSUE a PAYMENT CERTIFICATE by the due date (Specified in the contract data)
Compile a STATUS REPORT of the works, which includes marked up drawings and photographs that records the
completed and incomplete work on the date of termination. Your status report will be important to determine the
value of the FINAL ACCOUNT and could be relied on during the course of DISPUTE RESOLUTION
CLAUSE 30 = DISPUTE RESOLUTION
Both parties shall: REGARDLESS of whether a disagreement or a dispute exists between them Continue to perform
their OBLIGATIONS, in terms of the contract
DELAYS
- Delays to the contractor’s progress may be a result in time + and Cost + overruns + are a major source of Claims
and Disputes
- A delay in works progress in not necessarily the same as a delay in practical completion
o CRITICAL DELAY = Will have an adverse effect on the critical path of the contractor’s program.
o NON – CRITICAL DELAY = will not impact Practical completion.
o NON – JUSTIFIABLE DELAY = A delay caused by the contractor or any aspect that falls within the
contractor’s control, no additional time or compensation will be granted for such delays.
- Main advantage – It will not interfere with the PROGRESS of the works. Therefore, for the good of the project.