RFQ SPBU-778

Dear Sir,

Please note that the quote Supply, Deliver and Installation of wooden door and metal door in addition,
labor transportation, food and accommodation shall be included in your price . Please Consider the
following notes :

Material: Single and Double leaf solid wooden door with hardwood veneer.and metal door

Finish : hardwood veneer finish with powder coated galvanize steel frame and metal sheet on powder
coated galvanize steel frame.

Thermal Insulation : shall be included

PVC CAP and Rubber Silencer shall be included

All materials shall be subject to consultant approval and client acceptance.

the Accepted payment terms as following :

1)10% advance payment 2) 100% progress payment 50% after delivery will be
paid after 30 days and 50% after installation will be paid after 30 days 3) 10%
retention 5% after Initial HO of building and 5% after final HO of building

Please note that there is an alternative line option available on system. you may need to use if you need
to present your exact description.

This video for pricing online


https://drive.google.com/file/d/18pKMrh4gTbCJw1N06Rpd6xW0b3anCe
GK/view

and this video for all aspects, like, invoicing, payments, deliveries etc
https://sites.google.com/el-seif.com.sa/elseif-supplier-portal/home

if you do not have user name and password, you can write an email to c.somera@EL-SEIF.COM.SA to reset
your user name and password.

thanks

Proprietary and Confidential 16-Apr-2019 7:00 PM


1
RFQ SPBU-778

Proprietary and Confidential 16-Apr-2019 7:00 PM


2
RFQ SPBU-778

Submit your response to the following contact.


Company EL SEIF GROUP
Buyer SHAKER MOHAMMED AYESH
Location El Seif Engineering Contracting CompanyRIYADHSAUDI ARABIA
Phone 966-114549191
Fax
E-mail s.ayesh@el-seif.com.sa

When submitting your response, include the following information.


Your Company Name
Company Site (Optional)
Address
Contact Details
Response Valid Until
(Optional)

This document has important legal consequences. The information contained in this document is proprietary of EL
SEIF GROUP. It shall not be used, reproduced, or disclosed to others without the express and written consent of EL
SEIF GROUP.

Proprietary and Confidential 16-Apr-2019 7:00 PM


3
RFQ SPBU-778

Table of Contents

1 Overview.......................................................................................................................................................................5
1.1 General Information..............................................................................................................................................5
1.2 Schedule................................................................................................................................................................5
1.3 Negotiation Controls.............................................................................................................................................5
1.4 Response Rules.....................................................................................................................................................5
1.5 Terms....................................................................................................................................................................5
2 Requirements................................................................................................................................................................6
3 Lines..............................................................................................................................................................................7
3.1 Line Information...................................................................................................................................................7
3.2 Line Details...........................................................................................................................................................9
3.2.1 Line 1..............................................................................................................................................................9
3.2.2 Line 2............................................................................................................................................................10
3.2.3 Line 3............................................................................................................................................................10
3.2.4 Line 4............................................................................................................................................................10
3.2.5 Line 5............................................................................................................................................................10
3.2.6 Line 6............................................................................................................................................................11
3.2.7 Line 7............................................................................................................................................................11
3.2.8 Line 8............................................................................................................................................................11
4 Appendix: Alternate Lines..........................................................................................................................................13
4.1 Instructions for Alternate Lines..........................................................................................................................13
4.2 Alternate Lines Template...................................................................................................................................13

Proprietary and Confidential 16-Apr-2019 7:00 PM


4
RFQ SPBU-778

1 Overview
1.1 General Information
Title Supply, Delivery And Installation of Metal & Wooden Door For POL Store
Synopsis Shop Drawing Shall Be Submitted For Approval Prior To Manufacturing.
-The Dimensions Shown In Attached Signed Door Schedule Are To Be Followed.
-The Drawing To Be Used For Information Only.
-Pre- Approved Sub-Contractor.

Note : Providing Accommodation To Subcontractor Will Be ESECs Responsibility.

Buyer SHAKER MOHAMMED Outcome Subcontract Order


AYESH
E-Mail s.ayesh@el-seif.com.sa

1.2 Schedule
Preview Date Open Date 16-Apr-2019 7:00 PM
Close Date 16-Apr-2019 11:40 AM Award Date
Time Zone Arabia Standard Time

1.3 Negotiation Controls


Response Visibility Blind

Lines Settings
Rank Indicator 1,2,3...
Ranking Method Price only
1.4 Response Rules
This negotiation is governed by all the rules displayed below.
Rule
Negotiation is restricted to invited suppliers
Suppliers are allowed to respond to selected lines
Suppliers are required to respond with full quantity on each line
Suppliers are allowed to provide multiple responses
Suppliers are allowed to revise their submitted response

1.5 Terms

Payment Terms Immediate Freight Terms DDP


Shipping Method Land-Road FOB Insured by Vendor
Negotiation Currency SAR (Saudi Riyal)
Price Precision 3

Proprietary and Confidential 16-Apr-2019 7:00 PM


5
RFQ SPBU-778

2 Requirements
*Response is required
Shop Drawing Shall Be Submitted For Approval Prior To Manufacturing.
-The Dimensions Shown In Attached Signed Door Schedule Are To Be Followed.
-The Drawing To Be Used For Information Only.
-Pre- Approved Sub-Contractor.
Note : Providing Accommodation To Subcontractor Will Be ESECs Responsibility.

Proprietary and Confidential 16-Apr-2019 7:00 PM


6
RFQ SPBU-778

3 Lines

3.1 Line Information

Line Target UOM Response Response Line Promised


Quantity Quantity Price Amount Date
1-WD01-Single 1 NOS
leaf solid wooden
door with
hardwood veneer
finish on power
coated galvanized
steel frame, size:
1000mm x
2100mm 30 Mnts
FR, There are 02
No's of Vision
Panels on Door
leafs
2-WD02-Single 1 NOS
leaf solid wooden
door with
hardwood veneer
finish on power
coated galvanized
steel frame, size:
1000mm x
2100mm 30 Min
FR, As per MEP
requirement needs
01 No's of door
Louver Size:
250mm x 250mm
3-WD03-Single 1 NOS
leaf solid wooden
door with
hardwood veneer
finish on power
coated galvanized
steel frame, size:
800mm x 2100mm
NFR, As per MEP
requirement needs
01 No's of door
Louver Size:
250mm x 250mm
4-SD01-Double 2 NOS
leaf powdercoated
GI door Size:
1800mm x
2400mm NFR
approved door
Color RAL-7035

Proprietary and Confidential 16-Apr-2019 7:00 PM


7
RFQ SPBU-778

Line Target UOM Response Response Line Promised


Quantity Quantity Price Amount Date
5-SD03-Double 1 NOS
leaf powdercoated
GI door Size:
1800mm x
2400mm With
Louver 350mm x
350mm, NFR
approved door
Color RAL-7035,
As per MEP
requirement both
door leaf is having
01 No's Of door
louver at the
bottom level. Door
Louvers are to be
Sand Trap
6-SD04-Single 1 NOS
leaf powdercoated
GI door Size:
1000mm x
2100mm With
Louver 400mm x
400mm, NFR
approved door
Color RAL-7035,
As per MEP
requirement door
leaf is having 01
No's Of door
louver at bottom
level & 01 No's of
Vision Panel
(600x600). Door
Louvers is to be
Sand Trap

Proprietary and Confidential 16-Apr-2019 7:00 PM


8
RFQ SPBU-778

Line Target UOM Response Response Line Promised


Quantity Quantity Price Amount Date
7-SD05-Double 3 NOS
leaf powdercoated
GI door Size:
1800mm x
2400mm With
Louver 400mm x
400mm, NFR
approved door
Color RAL-7035,
As per MEP
requirement both
door leaf is having
01 No's Of door
louver at the
bottom level.
Louvers are to be
Sand Trap & All
the storage Area
doors
subcontractor
needs to
recommend &
provide the
suitable door
hardware as per
highlighted CDD
requirements
8-SD06-Single 1 NOS
leaf powdercoated
GI door Size:
900mm x 2100mm
With Louver
750mm x 750mm,
NFR approved
door Color RAL-
7035, As per MEP
requirement door
leaf is having 01
No's Of door
louver at the
bottom level. and
Door Louvers is to
be Sand Trap
3.2 Line Details
3.2.1 Line 1 WD01-Single leaf solid wooden door with hardwood veneer finish on power coated galvanized
steel frame, size: 1000mm x 2100mm 30 Mnts FR, There are 02 No's of Vision Panels on Door leafs
To provide an alternate line, see appendix.
Category Name Doors And
Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering

Proprietary and Confidential 16-Apr-2019 7:00 PM


9
RFQ SPBU-778

Contracting Company
TABUK
Start Price (SAR)

Note For POL Store


3.2.2 Line 2 WD02-Single leaf solid wooden door with hardwood veneer finish on power coated galvanized
steel frame, size: 1000mm x 2100mm 30 Min FR, As per MEP requirement needs 01 No's of door Louver
Size: 250mm x 250mm
To provide an alternate line, see appendix.
Category Name Doors And
Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering
Contracting Company
TABUK
Start Price (SAR)

Note For POL Store


3.2.3 Line 3 WD03-Single leaf solid wooden door with hardwood veneer finish on power coated galvanized
steel frame, size: 800mm x 2100mm NFR, As per MEP requirement needs 01 No's of door Louver Size:
250mm x 250mm
To provide an alternate line, see appendix.
Category Name Doors And
Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering
Contracting Company
TABUK
Start Price (SAR)

Note For POL Store


3.2.4 Line 4 SD01-Double leaf powdercoated GI door Size: 1800mm x 2400mm NFR approved door Color
RAL-7035
To provide an alternate line, see appendix.
Category Name Doors And
Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering
Contracting Company
TABUK
Start Price (SAR)

Note For POL Store


3.2.5 Line 5 SD03-Double leaf powdercoated GI door Size: 1800mm x 2400mm With Louver 350mm x
350mm, NFR approved door Color RAL-7035, As per MEP requirement both door leaf is having 01 No's Of
door louver at the bottom level. Door Louvers are to be Sand Trap
To provide an alternate line, see appendix.

Proprietary and Confidential 16-Apr-2019 7:00 PM


10
RFQ SPBU-778

Category Name Doors And


Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering
Contracting Company
TABUK
Start Price (SAR)

Note For POL Store


3.2.6 Line 6 SD04-Single leaf powdercoated GI door Size: 1000mm x 2100mm With Louver 400mm x
400mm, NFR approved door Color RAL-7035, As per MEP requirement door leaf is having 01 No's Of door
louver at bottom level & 01 No's of Vision Panel (600x600). Door Louvers is to be Sand Trap
To provide an alternate line, see appendix.
Category Name Doors And
Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering
Contracting Company
TABUK
Start Price (SAR)

Note For POL Store


3.2.7 Line 7 SD05-Double leaf powdercoated GI door Size: 1800mm x 2400mm With Louver 400mm x
400mm, NFR approved door Color RAL-7035, As per MEP requirement both door leaf is having 01 No's Of
door louver at the bottom level. Louvers are to be Sand Trap & All the storage Area doors subcontractor
needs to recommend & provide the suitable door hardware as per highlighted CDD requirements
To provide an alternate line, see appendix.
Category Name Doors And
Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering
Contracting Company
TABUK
Start Price (SAR)

Note For POL Store


3.2.8 Line 8 SD06-Single leaf powdercoated GI door Size: 900mm x 2100mm With Louver 750mm x 750mm,
NFR approved door Color RAL-7035, As per MEP requirement door leaf is having 01 No's Of door louver at
the bottom level. and Door Louvers is to be Sand Trap
To provide an alternate line, see appendix.
Category Name Doors And
Windows.Hollow
Metal Doors And
Frames
Item Revision
Allow Alternate Lines Yes Alternate Line Provided Yes No
Requested Date Location El Seif Engineering

Proprietary and Confidential 16-Apr-2019 7:00 PM


11
RFQ SPBU-778

Contracting Company
TABUK
Start Price (SAR)

Note For POL Store

Proprietary and Confidential 16-Apr-2019 7:00 PM


12
RFQ SPBU-778

4 Appendix: Alternate Lines

4.1 Instructions for Alternate Lines

Alternate lines are allowed for some negotiation lines. For these lines, you can propose one or more alternatives by
entering information for each alternate line in the format given below. Print and insert multiple copies as per your
requirement.

4.2 Alternate Lines Template

Negotiation
Line
(Number and description of the negotiation line for
which you have an alternative)
Example:1-xxxxxx
where xxxxxx is the line description of first negotiation
line.
Alternate Line Number
(Enter only numbers in sequence starting with 1 for
every alternate line)
Alternate Line Description

Response Price
(For a negotiation line with cost factors, enter your line
price in the cost factors table)
Response Quantity

UOM

Promised Date

Note to Buyer

Proprietary and Confidential 16-Apr-2019 7:00 PM


13

You might also like