Annexure 10 - Project Execution Requirements
Annexure 10 - Project Execution Requirements
ANNEXURE 10
Note: ANNEXURE 10 covers general project execution requirements and may not change substantially from project
to project, except for items marked*.
1.1 This ANNEXURE 10 is an AGREEMENT DOCUMENT forming part of the AGREEMENT, and shall be
read with and into the AGREEMENT.
1.2 The PARTIES agree and acknowledge that, notwithstanding anything to the contrary set out in this
ANNEXURE or any other, this ANNEXURE shall be read and applied in accordance with the order of
precedence set out at Clause 1.5 of the FORM OF AGREEMENT.
1.3 In this ANNEXURE 10, unless otherwise defined, capitalised words and expressions shall have the same
meanings as are respectively assigned to them in the GENERAL TERMS AND CONDITIONS.
1.4 For the avoidance of doubt, the Governing Law and Dispute Resolution provision of Article 50 of the
GENERAL TERMS AND CONDITIONS shall apply to this ANNEXURE 10.
(f) ANNEXURE 10F – ADNOC GROUP SUPPLIER AND PARTNER CODE OF ETHICS*.
Page 1 of 49
ADNOC Classification: Internal
ANNEXURE 10A
SERVICES TO COMPANY
Page 2 of 49
ADNOC Classification: Internal
Page 3 of 49
ADNOC Classification: Internal
2. OFFICE FACILITIES
CONTRACTOR shall provide office facilities as per the specifications and quantities specified
herein below and in Attachment 1 hereof.
1. The office facilities shall be adjacent to CONTRACTOR’S Project Office; in general, the
designated office area shall remain restricted to COMPANY personnel, other than for meetings
with CONTRACTOR’S personnel.
2. Alternatively, CONTRACTOR may provide a task force-based Project Office where
COMPANY’S and CONTRACTOR’S personnel are seated in the same area.
No WORK shall be performed by CONTRACTOR’S personnel in the above Office Facilities
which is not related to the PROJECT, therefore, no documents/drawings related to any other
project should be found there.
3. For purpose of security, the Office Facilities will be accessible only through use of electronic
key cards.
4. The Office Facilities shall comply with COMPANY’S and CONTRACTOR’S minimum
occupational HSE standards and latest COVID 19 minimum distancing guidelines.
5. The Office Facilities shall have access to:
▪ A dedicated Prayer room with ablution facilities,
▪ Dedicated kitchen facilities,
▪ Dedicated toilet and washroom facilities.
6. The key features of each type of Office Facility are specified in Attachment 1 hereof.
Page 4 of 49
ADNOC Classification: Internal
Page 5 of 49
ADNOC Classification: Internal
Similarly, CONTRACTOR shall also provide the following item(s) on a reimbursable basis, The details of
Company Vehicle Requirements are referred in ATTACHMENT 2 herein below:
d. 4 Nos. of New Nissan Patrol V8 (Auto) (Model No. PAT 710 LEV8) or equivalent for COMPANY
indemnified personnel with full Service/ Maintenance, Fuel Cost, Parking, and Tollgate charges, as
specified in SCHEDULE 3 of ANNEXURE 5 (PRICING SCHEDULE) of AGREEMENT.
e. 1 Nos. of New Toyota Previa Vans (8-Seater) (2.4S) or equivalent, including Driver with full service
/ Maintenance, Fuel cost, parking, and Tollgate charges, as specified in SCHEDULE 3 of
ANNEXURE 5 (PRICING SCHEDULE) of AGREEMENT.
CONTRACTOR shall submit a monthly (in arrears) reconciliation sheet showing quantity and
duration of all CONTRACTOR’S services and provisions for COMPANY requirements. This sheet
when approved by COMPANY shall be used to reimburse the cost of the above-mentioned
personnel, facilities and items in accordance with AGREEMENT Terms and Conditions.
8. DURATION
The facilities specified herein above and in the Attachment 1 hereof shall be provided for the
durations as stated in Attachment 1.
9. DEFINITIONS
The term “1 Lot” specified against certain items in Attachment 1 hereof means the total quantity,
without any limit, of the respective item that would be utilized by COMPANY or COMPANY
INDEMNIFIED PARTIES personnel during the EPC TERM and OPERATIONAL TERM.
Page 6 of 49
ADNOC Classification: Internal
ATTACHMENT 1
Page 7 of 49
ADNOC Classification: Internal
Page 8 of 49
ADNOC Classification: Internal
1 Nos. Dedicated Pantry Facility with Kitchen with tea/coffee making machines etc. Sink, hot + cold
sink, hot and cold water, water, microwave, refrigerator, hot plate, preparation area etc.
microwave, refrigerator and
preparation area. for overall
duration of the Project
2 Nos. Dedicated Toilet Facility for 2 Nos. Fully Equipped WC1 And WC2 with (18 sq. m) each at SITE
overall duration of the Project OFFICE with appropriate facilities to cater to the number of
personnel occupying the offices specified herein.
1 LOT Power, lighting, air- 24 hour/day, 7day/week availability
conditioning (heat cool), water
utilities for overall duration of
the project including
DECOMMISSIONING.
12 Nos. Accommodation Provision of Accommodation facilities (new) and services at site for
Single Occupancy during COMPANY PERSONNEL including COMPANY PMT staff,
Construction Phase from O&M, PMC, TPA and other affiliated COMPANY Contractors.
SITE Mobilization till
Page 9 of 49
ADNOC Classification: Internal
QTY. COMPUTER
FEATURES
HARDWARE
18 Nos. DELL Precision 5570 Mobile Mobile workstation, featuring the latest Intel® Core™ and Xeon®
during EPC TERM + 3 Workstations or equivalents processors, NVIDIA® graphics, reference model as DELL
Months Precision 5570 Mobile workstation or equivalent with other
necessary software’s to execute the work effectively.
Page 10 of 49
ADNOC Classification: Internal
New A4/A3 with auto-feed, colour, which can scan and capable of
sending to the users’ inbox
1 Nos. for entire Project Paper Shredder NEW 20 sheet feed at a time capacity
duration
COMPUTER
QTY FEATURES
SOFTWARE
18 Nos. 'Minimum required Software for Mobile Workstations:
during EPC TERM + 3 - Microsoft Windows
Months - Microsoft Office Suite (Excel, Word, Power point, Access)
- 'Adobe Acrobat PRO, WinZip or equivalent Data Compression
7 Nos. Program
during OPERATIONAL -Primavera / MS Project Licence for Company Project Control
TERM - License for each CONTRACTORs in house software packages
used in the project.
-etc.
1 LOT CONTRACTORs in house License for each CONTRACTORS in house software packages
software packages used in the project. (CONTRACTOR will provide a process to
allow controlled access of in-house software for
validation/checking only.)
MISCELLANEOUS
REQUIREMENTS
QTY FEATURES
RELATED TO
OFFICE FACILITES
1 LOT for entire Project 'Internet Services (Wi-Fi) Unlimited download and upload capacity - for all offices and
duration workstations.
11 Nos. required during 'Car parking slots for cars Covered car parking in CONTRACTOR Home Office.
EPC TERM + 3
Months
7 Nos. required from 'Car parking slots for cars Covered car parking in SITE.
SITE Mobilization till
FIRST
COMMERCIAL
PRODUCTION
CERTIFICATE + 6
Months
Page 11 of 49
ADNOC Classification: Internal
MISCELLANEOUS
REQUIREMENTS
QTY FEATURES
RELATED TO
OFFICE FACILITES
7 Nos. required during
OPERATIONAL TERM
up-to
DECOMMISSIONING
1 LOT Daily supply of tea, coffee, fresh milk and drinking water (ambient + chilled).
1 LOT Consumables (toner cartridges etc.) and paper for printer, facsimile, photocopier
Page 12 of 49
ADNOC Classification: Internal
ATTACHMENT 2
VEHICLES REQUIREMENTS
Page 13 of 49
ADNOC Classification: Internal
Page 14 of 49
ADNOC Classification: Internal
ANNEXURE 10B
Page 15 of 49
ADNOC Classification: Internal
1.1 Introduction
The Project Controls Requirements described herein mainly covers the COMPANY’s
requirements on Project planning, progress measurement, invoicing and reporting, which are
to be strictly complied by the CONTRACTOR. The CONTRACTOR shall be responsible for
programming of the Work and use Industry Standard Project Management Software
(MSPROJECT / PRIMAVERA only) to plan, schedule, monitor, update and control the
Project activities.
All cost and time impact(s) incurred for complying with these Project Controls Requirements
shall be deemed to be included in the CONTRACT PRICE and Contract Schedule.
1.2.1 General
Within one week from COMMENCEMENT DATE of Contract, CONTRACTOR shall submit a detailed
draft Schedule for the activities planned for initial 30 days, for physical progress monitoring purposes.
This shall cover all aspects of survey and data collection, design & engineering deliverables, planning
documents, procedures, document register, standards, specifications, initial procurement activities, site
establishments, mobilisation etc., This schedule shall be updated on weekly basis and shall eventually
superseded by the approved EPC WORK Schedule.
Within thirty (30) days from COMMENCEMENT DATE, the CONTRACTOR shall submit Project
Plan with detailed schedule (along with soft copy) with full supporting details and basis, for COMPANY’s
review and approval. The project plan shall have level-3 detailed network schedule.
The CONTRACTOR shall clearly identify all activities pertaining to the Scope of Work, including but
not limited to following planning objectives:
▪ Identification of all significant milestones and interface activities within the project and/ or with
Page 16 of 49
ADNOC Classification: Internal
COMPANY’s other projects and/or other external influences which may have impact on the scope of
this Contract.
▪ The integrated Project network schedule should have all necessary activities and milestones required
to complete the scope of work, which shall include but not limited to activities related to
CONTRACTOR, Sub-CONTRACTOR(s), Vendor(s), Manufacturer(s), Supplier(s) activities related
to COMPANY approval etc., within the appropriate Work Breakdown Structure described herein.
▪ Continuous comparison of actual Project Progress w.r.t. current & target plans.
▪ The prompt identification of delay/ potential delay and proposed corrective measures to recover
any slippage.
The Schedule shall be prepared without any imposed “Constraints” and negative floats. The Contractor shall
include in the Schedule, all activities related to “Company Review/ Approval” of all major drawings/documents
(including Technical Bid Evaluation Reports for Procurement items) by COMPANY, as a separate activity
in the Schedule, other than Contractor own plan with activities durations consistent with the review cycles
specified in the CONTRACT. Due consideration shall be given to the local holidays as well as shorter
working hours during the holy month of Ramadan, as applicable. Schedule shall be resource levelled prior to
submission to COMPANY for review / approval.
Within thirty (30) days from the COMMENCEMENT DATE, CONTRACTOR shall submit a detailed
Planning Package for COMPANY’s review and approval.
Page 17 of 49
ADNOC Classification: Internal
Commissioning (as applicable) & PERFORMANCE TEST and shall also indicate deployment forecast of
resources for these activities by disciplines/crafts.
The CONTRACTOR shall use the COMPANY approved Project plan as the basis for Daily, Weekly and
Monthly progress reporting, scheduling, forecasting and controlling performance of the WORK.
Monthly update of project Schedule with soft copy (in native form) shall be submitted to COMPANY
throughout the Project duration.
The weight factors for all deliverables shall be loaded into soft copy of the Project Plan in Budgeted Quantity
/ Budgeted Cost data element. Generation of S-curves shall be verifiable by COMPANY and independent of
CONTRACTOR’s in-house software packages. In case CONTRACTOR intends to utilize in-house software
for generation of S-curves and/ or progress measurement, CONTRACTOR shall provide access to
CONTRACTOR relevant Desktop/Laptop software program/ system for unrestricted use of COMPANY
including User Manuals & user training for COMPANY Project Controls Engineers for verification of S-
curves & progress certification. This access shall include ability to log-in & READ the CONTRACTOR’s
Server/ Database for the above, at any time during Project duration.
The WBS is a hierarchal breakdown of the project scope into smaller and more manageable components. The
breakdown is typically driven by logical grouping of deliverables and additional levels of breakdown to
develop the granularity of the overall task.
The objective of the WBS is to reduce the scope of a project into work packages for which cost, schedule and
risk may be defined. To that end, breakdown is only executed to the level required by the type and nature of
the work. Excessive breakdown becomes burdensome for Project Control teams to monitor and report.
Page 18 of 49
ADNOC Classification: Internal
COMPANY has specified certain minimum number of KEY MILESTONES (in the Scope of Work) from
which the CONTRACTOR’s Project Schedule shall be developed further. CONTRACTOR shall identify
sufficient additional milestones within the framework of the WBS, to adequately plan, progress and fully report
the complete Scope of Work.
The KEY MILESTONES and CONTRACTOR designated additional milestones, shall provide the common
framework for combining CONTRACTOR’s Project Schedule and external interface milestones to/ from
Sub-CONTRACTOR(s) and Vendors into the total Integrated Project Schedule.
Summary schedule of the Project is a rolled-up schedule. At this level shall include key milestone events and
duration of rolled-up activities for each major section of the Work including the following:
a) Engineering / Design
b) Procurement
c) Construction
d) Mechanical Completion
e) Commissioning
f) Ready for Test Run
g) Performance Test
h) First Commercial Production
Level 1 bar chart will represent a summary of the Level II schedules and highlight critical and sub-critical
activities and paths. This Level 1 bar chart will demonstrate overall objectives for completing the Work, within
the Contract Milestones. The Bar chart will be a graphical presentation of the work having the following
minimum details:
- Activity description;
- Activity early and late dates;
- A graphical bar from early start to early finish.
- Contractual Milestone dates [Baseline, Actual, Forecast].
The activities in the Level-3 Schedules in Primavera/MS Project shall have Custom Data/ Text field with
corresponding Document/ Drawings/ Deliverable Number.
Page 19 of 49
ADNOC Classification: Internal
Level 3 network shall also be assigned or loaded with approved weight factors.
The Computerized Project Network Level-3 activities should have the following minimum details:
- Activity ID;
- Activity description;
- Activity duration;
- Activity scheduled early start and scheduled early finish dates
(Forecast dates during the monitoring phase of the Project);
- Activity scheduled late start and scheduled late finish dates;
- Activities on the critical path;
- Actual Progress per each activity;
- Total Float
- Resource Content
No later than six (6) months prior to the first proposed COMMISSIONING activities, the
CONTRACTOR shall provide a detailed COMMISSIONING plan (Level-4/5) for the COMPANY’s
review and approval
The level-4/5 schedules shall be based on day basis and the activities shall be broken-down in detail
to enable accurate control of activities and any activity duration in these micro-schedules shall not
exceed 3 days. CONTRACTOR to ensure that the appropriate Level-3 activities (roll-up of Level-4/5
– i.e.: system level) of Pre-commissioning/ Commissioning are reflected and analysed in the Level-
3 project networked schedule at the stage of planning package submission to COMPANY. If
CONTRACTOR is using any computerized pre-commissioning / commissioning progress measurement
software / system, COPMANY shall be extended with full READ/Export access to such system for
Project controls/ commissioning personnel of COMPANY.
• Milestones
o Construction Completion by system (Higher Level) and subsystem (lower level);
o Pre-commissioning Completion by system (Higher Level) and subsystem (lower level);
o Commissioning Completion by system.
o Project RFSU (Ready for Start-Up) or Ready for Test Run
Page 20 of 49
ADNOC Classification: Internal
o Performance Test
o First Commercial Production
• Pre-commissioning
o System (Number & Description)
▪ Sub-system (Number & Description)
o Disciplines: Activities to cover all check sheets and test sheets by Equipment,
Package, Instruments, Pumps, Motors, Piping Lines, Valves, Cables etc., (details
to be gathered from commissioning software or by other means)
The CONTRACTOR shall submit to the COMPANY, no later than ninety (90) days prior to the proposed
MAINTENANCE SCHEDULE for such CONTRACT YEAR, and for the next two (2) CONTRACT
YEARS (or until the end of the OPERATIONAL TERM, whichever is earlier) for the COMPANY’s review
and approval. Any MAINTENANCE activities need to be performed only upon approved MAINTENANCE
SCHEDULE.
Upon approval of the Project plan by COMPANY, it will be baseline plan and shall remain unchanged
throughout the Project and shall not be changed by CONTRACTOR.
In case of any delay/slippages on physical progress against the baseline plan, CONTRACTOR shall
within 7 DAYs from COMPANY notification date, develop a Recovery plan based on recovery schedule
and revised resource deployment and submit to COMPANY for review/approval.
The Recovery plan shall be treated as forecast plan with firm commitment towards achieving the KEY
MILESTONEs DATES. The approval of Recovery Plan shall not affect/ change the Contractual K E Y
MILESTONES and Schedule/Project Completion Date & Contractual obligations thereof. The preparation
& implementation of such Recovery Plan by CONTRACTOR shall be without any additional cost & time
impact to COMPANY.
Normally under the following circumstances, COMPANY may notify CONTRACTOR for submission of
Recovery Plan:
Page 21 of 49
ADNOC Classification: Internal
CONTRACTOR shall produce a Recovery Plan, including but not limited to following conditions:
• Category 1:
Overall Plan progress: Early Plan ≤ 25% (or) Late Plan ≤ 20%
Progress Variance: Early Plan - Actual ≥ 4% (or) Late Plan – Actual ≥ 3% However, the
above formula is not applicable for first three months from COMMENCEMENT DATE.
• Category 2:
Overall Plan progress: 25% < Early Plan ≤ 50% (or) 20% < Late Plan ≤ 45%
Progress Variance: Early Plan - Actual ≥ 6% (or) Late Plan - Actual ≥ 3%
• Category 3:
Overall Plan progress: 50% < Early Plan ≤ 75% (or) 45% < Late Plan ≤ 65%
Progress Variance: Early Plan - Actual ≥ 6% (or) Late Plan - Actual ≥ 3%
• Category 4:
Overall Plan progress: 75% < Early Plan ≤ 100% (or) 65% < Late Plan ≤ 100%
Progress Variance: Early Plan - Actual ≥ 4% (or) Late Plan - Actual ≥ 3%
However, in addition to the above, COMPANY reserves the right to notify the CONTRACTOR for
submission of a Recovery plan, if deemed necessary in COMPANY’s view for achieving the Contractual
milestones and schedule/ project completion date.
During Project execution, if actual performance deviates from the approved schedule to the point where
the original Plan can no longer be an effective basis for control, then it is appropriate and desirable to
create a new performance measurement Plan, based on revised scheduling and manpower deployment. In
such case COMPANY may notify the CONTRACTOR for a Revised plan without changing the
Contractual Project completion date.
From a mutually agreed cut-off date, CONTRACTOR shall establish remaining works to be completed
and re-schedule activities to achieve the Contractual milestones and Schedule/ Project completion date.
All plans shall be re-scheduled based on the remaining duration and balance quantities to complete for
each activity. Remaining duration estimate must be realistic and consider the actual recorded productivity.
Up to date information shall then be updated into the Integrated Planning Network for a new time analysis
run. A revised document, titled as ‘Revised Planning Package’ having all the revised contents detailed
herein under clause “Planning Package”, shall be submitted for COMPANY’s approval.
Once COMPANY approves the Revised Planning Package, all reporting shall be re-base lined to reflect the
approved revised plan. However, if required by COMPANY, CONTRACTOR may be advised to indicate
the original baseline data/graph in any of the reports along with the revised plan/actual details.
1.2.13.2 Revised Plan – Changes to Baseline Milestone(s) and/or Project Completion
In case a Variation Order with schedule impact is issued by COMPANY for any changes with regard to
Contractual milestones, extension of time, then CONTRACTOR shall prepare a Revised plan covering
approved additional scope of work (if any) in-line with COMPANY approved schedule extension /
changes to milestone(s).
The procedures described under clause 2.4.1 above shall be followed for revision of Planning package
and reporting requirements subsequent to approval of revised planning package by COMPANY.
Page 22 of 49
ADNOC Classification: Internal
On the contrary, if CONTRACTOR submits the updated schedule by 9th month instead of 7th month
(delay occurred period), it may not be possible to clearly identify the impact of delay solely attributable
to COMPANY, as other delays attributable to CONTRACTOR (including Sub-CONTRACTOR,
Vendor, Third party etc.,) might have resulted in delay mitigation/ enhancement/ nullification of
COMPANY caused delay(s).
1.4 Progress Measurement
Within thirty (30) days from COMMENCEMENT DATE, CONTRACTOR shall submit a detailed procedure
for progress measurement without any deviation to the below mentioned level-IV progress gates and their stage
percentage progress for COMPANY’s review and approval. The objectives of the procedure shall be accurate
measurement of progress earned, as determined by physical work completed and verifiable by COMPANY’s
representative. The procedure shall include the following:
• The methodology to be used for measuring physical progress in each work phase of the Project
works.
• Individual person(s) responsible for assessing progress.
• Description of the review cycles.
• Progress Measurement procedure of SUBCONTRACT.
• Methods for evaluation, weighting and combining various measurements to arrive at overall
progress assessment figure for the work.
The procedures shall clearly describe methods for measuring progress according to the breakdown of
Contract Price and the principles of invoicing contained in the Contract.
As a minimum, progress shall be assessed on a weekly basis and the results incorporated into schedule
forecasts and progress reports. However, progress evaluations for discrete, critical phases of work may be
required more frequently.
The basis of progress measurement shall be based on the progress gate(s) and respective stage percentage
which shall be rolled up using weight factors based on the relative weight unit/ Man-hours/ efforts
etc. The CONTRACTOR shall demonstrate an acceptable procedure for measuring the progress of
computer-aided design work (Software based deliverables).
A minimum of 2 % of total budget man-hours / weighting will be allocated to “Miscellaneous Deliverables/
activities” in the respective Planning Registers during Execution phases of Contract (separately for each Area,
Phase, Discipline), as a contingency towards the unidentified activities and/or the anticipated increase in the
Page 23 of 49
ADNOC Classification: Internal
workload. This will eliminate the need for frequent adjustment of weight factors assigned to each activity /
deliverable. At an appropriate time during the period of implementation when full details of deliverables / MRs
/ POs and Construction work elements become available, any unused portion of this contingency will be
progressed and equivalent progress claimed, in consultation with COMPANY.
1.4.1 Engineering deliverables / documents:
*Notes:
▪ 5 working days (or 7 calendar DAYS) review cycle shall be considered for following stages.
▪ The CONTRACTOR shall, within fourteen (14) DAYS of the COMMENCEMENT DATE,
submit to the COMPANY a list of the categories of DRAWINGS and WORKS
DOCUMENTATION that the CONTRACTOR intends to prepare for the WORKS
▪ Further to Appendix B from the ANNEXURE 3 – SCOPE OF WORK, CONTRACTOR to look
for an option to fast track the review cycle from Document issuance to approval in close
coordination with COMPANY.
1.4.2 Procurement Services:
Page 24 of 49
ADNOC Classification: Internal
➢ Painting: Surface preparation / Blasting (50%), 1st coat (25%) and 2nd coat (25%) are the events of
measurement for Painting and shall be based on area.
➢ Pipe Coating: Number of pipes coated against total pipes to be coated (line pipe dia. wise)
➢ Civil (foundations): Foundation progress will be based in number of foundations completed vs. total
number of foundations to be completed.
➢ Civil (cut & fill, excavation): quantity of cubic metres executed vs. total amount of cubic metres.
➢ Civil (grading & levelling, sand stabilization, compaction, etc.): Quantity of square metres completed
vs. total amount of square metres.
Page 25 of 49
ADNOC Classification: Internal
➢ Civil (roads, fencing, trenches, etc): quantity of metres executed vs. total amount of metres.
➢ Civil (road crossing, etc): No. of crossings completed Vs. total No. of crossings in the Scope.
➢ Structural Erection / Installation: Tonnage complete vs. total tonnage.
➢ Pre-Commissioning/Start-up: Number of units completed and System Ready for Commissioning
(RFC) certificates obtained.
➢ Commissioning: Number of Commissioning Completion certificates obtained against total systems.
Progress measurement of this Pre- commissioning and Commissioning tasks to a system or
subsystem level shall be based on man-hours or weight factors assigned against check sheets, test
sheets, preliminary checks, functional tests, operational tests and pre-startup activities or any other
activities necessary to complete these tasks.
1.4.6 Miscellaneous
The CONTRACTOR shall submit for COMPANY’s approval, their proposed progress gates & stage
Percentage for the activities not covered above.
1.5.1 Daily Progress reporting for Construction works during EPC TERM
CONTRACTOR shall submit to COMPANY each morning, during execution of works at Construction
site, a Daily Report of the previous day’s progress, also covering trade split of manpower, Plant &
Equipment deployment. The format and detailed content of this Report shall be finalized in consultation
with COMPANY Representative.
Page 26 of 49
ADNOC Classification: Internal
Page 27 of 49
ADNOC Classification: Internal
CONTRACTOR is required to maintain the Daily production in the TABLE 1 template below.
On the days when the GAS export is constrained by reservoir limitation (not attributed to the
CONTRACTOR), the gas export is considered as Production Guaranteed Capacity, provided the facilities
are deemed to be operational at design capacity as assessed by the COMPANY.
In the event, COMPANY assessed that guarantee in terms of PERFORMANCE GUARANTEE and
PRODUCTION GUARANTEE is deficient, the contractor shall be paid only proportionate as assessed by
the COMPANY.
1.5.5 DECOMMISSIONING SCHEDULE
During DECOMMISSIONING period, CONTRACTOR shall submit the Monthly Progress Report, which
contains comprehensive description of works accomplished during the month, progress, lookahead activities
and the updated DECOMMISSIONING SCHEDULE with Milestones status and Key dates against the
Baseline Plan / Target Date.
As part of Progress measurement procedure, the CONTRACTOR and COMPANY shall agree on the detailed
procedure for measuring the progress of WORK for each category of the Contract Price.
CONTRACTOR shall submit a detailed progress calculations and draft invoice for each month to
COMPANY’s project management team, on or before the 5th day of the month. While submitting the draft
invoice, CONTRACTOR shall ensure that the monthly invoices are based on the COMPANY certified or
COMPANY INDEMNIFIED PARTIES progress up to the agreed monthly cut -off date and attach the
monthly production certificates signed by COMPANY.
Page 28 of 49
ADNOC Classification: Internal
In case of no dispute(s) in draft invoice, COMPANY will convey the agreement of the draft invoice to
CONTRACTOR for submission of final invoice to COMPANY. In case of any dispute, COMPANY shall
advise the dispute(s) in writing to CONTRACTOR for necessary amendment and re-submission of draft
invoice.
Final Invoice(s) for the undisputed/ certified amount shall thereafter be formally submitted to COMPANY in
SAP Ariba system, addressed to COMPANY’s Manager-Finance for subsequent processing for payment of
all undisputed sums.
The invoice formats to be mutually agreed between COMPANY and CONTRACTOR and shall include
details of invoice amount for the invoice period, amount already invoiced and cumulative amount including
current invoice against each Bills of Total Agreement Price. A complete set of original supporting documents
shall be attached to each of the invoices.
Page 29 of 49
ADNOC Classification: Internal
Notes:
Page 30 of 49
ADNOC Classification: Internal
ANNEXURE 10C
Page 31 of 49
ADNOC Classification: Internal
ANNEXURE 10D
Page 32 of 49
ADNOC Classification: Internal
1. PURPOSE
This ANNEXURE 10D covers the Training requirement for UAE Nationals.
ATTACHMENT 1
Page 33 of 49
ADNOC Classification: Internal
Page 34 of 49
ADNOC Classification: Internal
MISCELLANEOUS REQUIREMENTS
QTY FEATURES
RELATED TO OFFICE FACILITES
1 LOT 'Internet Services (Wi-Fi) Unlimited download and upload capacity - for all
offices and workstations.
1 LOT Daily supply of tea, coffee, fresh milk and drinking water (ambient + chilled).
1 LOT Consumables (toner cartridges etc.) and paper for printer, facsimile, photocopier
Note:
1. The term “1 Lot” specified against certain items in Attachment 1 hereof means the total quantity, without any limit, of
the respective item that would be utilized by COMPANY or COMPANY INDEMNIFIED PARTIES personnel during
the term of the AGREEMENT.
Page 35 of 49
ADNOC Classification: Internal
ANNEXURE 10E
ADMINISTRATION
Page 36 of 49
ADNOC Classification: Internal
2. Variation Handling
Refer Article 27, ANNEXURE 2 (GENERALTERMS & CONDITIONS)
Page 37 of 49
ADNOC Classification: Internal
ANNEXURE 10F
Page 38 of 49
ADNOC GROUP SUPPLIER & PARTNER
CODE OF ETHICS
V3 - 2021
The Code sets out the minimum standard The Code applies to all Suppliers and
of ethical business practice we expect Partners that undertake any work for, or
from any Supplier or Partner to any part of represent, the ADNOC Group when they
the ADNOC Group. are working for or representing us. When
we say in the ADNOC Group’s Code of
It sets out the basic rules and standards that
Conduct that we expect all our Suppliers
are necessary to conduct ADNOC Group
and Partners to align themselves with its
business in an ethical and compliant manner
principles, we mean that we expect them
and in accordance with the ADNOC
to comply with this Supplier Code. If a
Group’s values.
Supplier or Partner uses sub-contractors
Our Suppliers and Partners should comply to undertake the business of the ADNOC
with all applicable laws and regulations, and Group, that Supplier or Partner is
MD & GCEO
behave ethically. Suppliers and Partners that responsible for ensuring that those sub-
violate applicable laws are unacceptable contractors also comply with this Code.
FOREWORD
to us. The Code is not a summary of all
We will update the Code from time to time.
the laws, standards and policies that apply
Suppliers and Partners should always
to the ADNOC Group or to a Supplier’s
refer to www.adnoc.ae to ensure they
business.
are complying with the latest version of
Acting with integrity is central to how we It also sets out our commitment The Code does not dilute a Supplier’s the Code. We expect our Suppliers and
conduct the business of the ADNOC Group. to supporting the building of long-term legal obligations, and it does not override Partners to ensure that any of its personnel
success based on strong the terms of any agreement we have
That means not only adhering to the highest who work on ADNOC Group business are
ethical foundations. contractually agreed. If there is any conflict
standards of ethical conduct ourselves, but familiar with, and comply, with the standards
only partnering with Suppliers and Partners Please ensure you abide by our between the terms of an agreement we have set out in this Code.
who can commit to similar standards of Supplier or Partner Code of Ethics as a with a Supplier or Partner and this Code, that
integrity in conducting their business. fundamental part of committing to do agreement will prevail.
business with any part of the ADNOC
As such, I am pleased to launch a new
Group.
ADNOC Group Supplier & Partner Code
of Ethics, setting out the basic standards
of ethical behavior that we expect from H. E. Dr. Sultan Ahmed Al Jaber
those who seek to do business with the Managing Director & Group Chief Executive Officer
ADNOC Group. ADNOC Group
RESPECT FAIR LABOR PRACTICES If a Supplier or Partner uses sub- designed to help us all achieve these
The ADNOC Group strives to provide The ADNOC Group supports the protection contractors or agencies, it is the aims when doing the business of the
a working environment that respects of labor rights. Suppliers and Partners Supplier’s or Partner’s responsibility to ADNOC Group. Suppliers and Partners
diversity and looks after its people. We should not deploy any kind of forced ensure that they comply with this Code should make sure that they and their
expect our Suppliers and Partners to do labor. Suppliers and Partners must not including when it comes to fair labor personnel are aware of the policies,
the same. Our Suppliers and Partners use, employ, or seek to exploit in anyway practices. procedures and codes that apply to
should foster an environment that is the services of child, under-aged, slave them and the work they do, and act in
HEALTH, SAFETY & THE
inclusive of all, and treats individuals or trafficked labor. Except to the extent compliance with them.
ENVIRONMENT
respectfully, fairly and with dignity. permitted by law, Suppliers and Partners
The ADNOC Group is committed Suppliers and Partners should protect
should not retain employees’ identification,
We expect our Suppliers and Partners to to protecting the health and safety their personnel from over-exposure
work or travel documents, or deposits as a
be honest with us and with their people, of people, and protecting the to chemical, biological and physical
condition of employment.
and to communicate in ways that are environment. Suppliers and Partners hazards in the workplace and in any
effective. We expect our Suppliers and We expect our Suppliers and Partners to must share the same commitment and company-provided living quarters.
Partners to keep their commitments to us comply with all applicable labor laws and deliver it effectively in respect of its Emergency planning should be
and to those who work for them. related laws and regulations - in particular own operations. undertaken and response procedures
those relating to working and living implemented.
Harassment, intimidation, abuse, violence There are specific policies, procedures
conditions, wages, working hours and the
and any other disrespectful or offensive and codes of practice in place We expect our Suppliers and Partners
payment of overtime.
behavior to individuals is unacceptable to throughout the ADNOC Group that are to operate in an environmentally
the ADNOC Group. Retaliation is Suppliers and Partners must comply with responsible manner, and comply with
also unacceptable. the terms of the contract that is agreed all applicable environmental laws and
with the people working for them, and the regulations. All required environmental
How we dress at work is one way we
law. Everyone working for our Suppliers permits and licenses must be obtained
demonstrate our respect for each other
and Partners must be paid no less than and their operational and reporting
within the ADNOC Group. When attending
the prescribed minimum wage in a requirements followed. Sustainability is
the premises of the ADNOC Group,
timely manner, and given holidays, leave important to the ADNOC Group, and our
we ask our Suppliers and Partners to
and medical cover in accordance with Suppliers and Partners should minimize
adhere to widely accepted standards of
applicable laws. any waste of energy water or other
professionally appropriate dress, with
resources.
sensitivity to cultural considerations.
If Supplier or Partner personnel have a TRANSPARENCY FAIR BUSINESS PRACTICES SUPPLY CHAIN
personal relationship (including a family Our Suppliers and Partners should Our Suppliers and Partners should Suppliers and Partners must carefully select
relationship) with anyone in the ADNOC maintain accurate books and records that conduct their business consistent and monitor the third parties they use to
Group who could affect (or be seen to demonstrate compliance with applicable with fair and vigorous competition and perform work for the ADNOC Group or to
affect) any element of the ADNOC Group’s laws and regulations. Suppliers and in compliance with all applicable anti- supply materials. Suppliers and Partners
business dealings with that Supplier or Partners should be alert to any irregular trust laws. In performing ADNOC Group should conduct contextually appropriate
Partner; or if a Supplier or Partner has any payments, suspicious transactions, or business, you should ensure you are in due diligence and background checks.
other relationship with any ADNOC Group suspected money laundering and have compliance with local and international Third parties, contractors, agents, or
personnel that might represent a conflict of facilities to enable internal reporting within a trade laws including laws relating to subcontractors should be selected based
interests, our Suppliers and Partners should reasonable timeframe. import, export and customs procedures on merit and competitiveness.
disclose this fact to the relevant company and restrictions on dealings with certain
Suppliers and Partners should notify We reiterate that Suppliers and Partners are
within the ADNOC Group or ensure that the countries, entities and individuals.
the relevant ADNOC Group Company, responsible for ensuring their third party
relevant ADNOC Group personnel does so.
if permitted by applicable law, of any Suppliers and Partners should use only contractors comply with this Code when
We expect our Suppliers and Partners to investigation, audit, assessment, litigation fair business practices, including they are utilized in the service of ADNOC
have appropriate protections in place to or unusual request that relates to the transparent and honest participation Group business.
ensure that Supplier or Partner personnel ADNOC Group or concerns the work the in any sourcing process, and accurate
are not themselves impacted by a conflict Supplier or Partner is performing for or with and truthful advertising.
of interests when undertaking the work of the ADNOC Group.
the ADNOC Group.
GLOSSARY:
ADNOC means Abu Dhabi National Oil Company.
ADNOC Group means ADNOC together with each company in which ADNOC (i), directly or indirectly, controls fifty
percent (50%) or more of the share capital, or (ii) controls less than fifty percent (50%) of the share capital but in respect
of which ADNOC has, directly or indirectly, the ability to direct or procure the direction of the management and policies
(whether through the ownership of shares, by contract or otherwise), and excludes ADNOC Minority Entities.
ADNOC Group Company means any company in the ADNOC Group other than ADNOC.
ADNOC Minority Entity means any company in which ADNOC, directly or indirectly, controls less than fifty percent (50%)
of the share capital (and in respect of which ADNOC does not have the ability to direct or procure the direction of the
management and policies).
Code means this ADNOC Group Supplier & Partner Code of Ethics, as may be amended from time to time.
Supplier and/or Partner means anyone who does or seeks to do business of any kind with any part of the ADNOC Group.
ANNEXURE 10G
Page 46 of 49
ADNOC Classification: Internal
TABLE OF CONTENTS
1 PROJECT CONTROLS REQUIREMENTS – POST AWARD OF CONTRACT ......... 16
1. PURPOSE 33
1. INTRODUCTION ................................................................................... 48
6. ENGINEERING ..................................................................................... 48
7. PROCUREMENT ................................................................................... 48
Page 47 of 49
ADNOC Classification: Internal
1. INTRODUCTION
1.1 Purpose of Document
1.2 Definitions
1.3 Background
5. PROJECT CONTROLS
5.1 Basis of Schedule
5.2 Major and Key Milestones
5.3 Level 3 Project Schedule
5.4 Manpower Plan & Histogram
5.5 Resources (Machine / Equipment’s) Histogram
5.6 Progress Measurement System
5.7 Project Reporting
6. ENGINEERING
6.1 Basis of Design
6.2 Engineering Team Management
6.3 Engineering Execution
6.4 Engineering Status Monitoring
6.5 List of Design Reviews, HSE Studies & Workshops
7. PROCUREMENT
7.1 Procurement Strategy
7.2 Subcontracting Plan
7.3 Expediting & Material Control
7.4 Spare Parts
Page 48 of 49
ADNOC Classification: Internal
13. DECOMMISSIONING
14. APPENDICES
14.1 Project Organization Chart
14.2 Work Breakdown Status
14.3 List of LLI’s
14.4 Major and Key Milestones Schedule
14.5 Overall Level 3 Schedule
14.6 Critical Path Schedule
14.7 Manpower Plan for PMT, Engineering, Construction, Commissioning &
Operations
14.8 Responsibility matrix between Consortium Leader, Partners, Subcontractor
14.9 List of vendor Outside AVL (if any)
14.10 List of Software
14.11 List of Codes & Standards
Page 49 of 49