Professional Documents
Culture Documents
Supervision Proj
Supervision Proj
percentage rate of the actual price paid or due to be paid calculated, where
provision has been made in the Bill of Quantities for a rate to be set against
the relevant Provisional Sum, at the rate inserted by the Contractor against that
item or, where no such provision has been made, at the rate inserted by the
Contractor in the Appendix to the Tender and repeated where provision for
such is made in a special item provided in the Bill of Quantities for such purpose
Clause 60
The Contractor shall submit to the Engineer after the end of each month,
(a) the quantities and value of the permanent work executed on Site.
hereunder.
contractor.
Chilot.wordpress.com
ii) the rates and prices, used to ascertain the values of permanent
Quantities, in so far as such rates and prices are in the opinion of the Engineer
applicable.
iii) if the said Bill of Quantities do not, in the opinion of the Engineer,
contain any rates or prices applicable to some or any part of the work executed
and there has not been a rate or price fixed at the time when the statement is
Engineer.
estimated value of the work executed up to the end of the previous month,
together with the value of materials on Site intended to form part of the
permanent work as and from such time as they are reasonably, properly and not
prematurely brought upon the Site but only if adequately stored and/or
completion, which sum shall be retained until the expiration of the maintenance
period.
Completion for the whole of the Works under Clause 48 hereof, the Engineer
shall, after allowing for the amount of all previous payments and after
determining and allowing for any sum due to the Employer from the Contractor,
certify as payable to the Contractor such a sum out of the balance so calculated
a sum equal to 5% of the value of work executed of the complete sections of the
Works.
Chilot.wordpress.com
the expiration of the latest such period, and provided what the Contractor has
sub-clause (6) of this Clause, the Engineer shall certify as payable to the
modification in any previous Payment Certificate which shall have been issued
by him, and the Engineer shall have power to withhold any Certificate if the
works or any part thereof are not being carried out to his satisfaction or to
Employer to the Contractor or the purposes of the Works in the event of such
Not later than 30 days after the date of issue of the maintenance
account with supporting documents showing in detail the value of the work done
in accordance with the Contract together with all further sums which the
contractor considers to be due to him under the Contract. Within 30 days after
receipt of this final account and of all information reasonably required for its
i) the amount which in his opinion is finally due under the Contract
and after giving credit to the Employer for all amounts previously paid by the
Employer and for all sums to which the Employer is entitled under the Contract.
ii) the balance, if any, due from the Employer to the Contractor or
from the Contractor to the Employer as the case may be. Such balance shall,
All payment under this Contract shall be in Birr unless otherwise agreed
upon.
Clause 62
Chilot.wordpress.com
Certificate shall have been signed by the Engineer and delivered to the
Employer stating that the Works have been completed and maintained to his
parts of the Works, the expiration of the latest such period, or as soon thereafter
hereof, shall have been completed to the satisfaction of the Engineer and full
effect shall be given to this Clause, notwithstanding any previous entry on the
Works or the taking possession, working or using thereof or any part thereof by
the Employer. Provided always that the issue of the Maintenance Certificate
portion of the retention money in accordance with the conditions set out.