Risk Assessment For Installation of Drainage Pipes
Risk Assessment For Installation of Drainage Pipes
TASK RISK ASSESSMENT (as per MPCL MSP: as per MSP-HSE-06) Company FACILITY:
GTH Gas Processing Facility
Activity: Installation & Removal of PSV Date:
Dapartment: Facilities Management
SPECIFIC LOCATION: MPCL, SGPC
PPES: PERSONAL PROTECTIVE EQUIPMENT & TOOLS NEEDED TO WORK ACTIVITIES: Hard hat, Safety Shoes, Safely Goggles, Hand Gloves, Hammer,Spanner, Gas Monitor, Airline
Base Risk Ranking Base Risk Ranking (With
(Without Controls) Controls)
No ACTIVITY HAZARDS HAZARD EFFECT CONTROL MEASURES RESPONSIBILITY
Risk
L S L S Risk Rating
Rating
2 Valve Replacement Check the work area is free from Toxic vapor &
Skin or eye irritation or burns, or
Exposure to Toxic Vapor Slightly open one bolt / stud to confirm no pressure
poising
& Use air line unit if required
GENERAL / ADDITIONAL COMMENTS: MANDATORY REQAUIRMENTS (to be filled by PH and verified by Approving Authority, Tick YES/NO):
1 1 Is joint survey conducted and all site specific hazards and controls incorporated ? Yes No
2 2 Is formal joint meeting conducted by team with key stake holders, inputs incorporated ? Yes No
3 3 Is formal job execution plan/method statement developed & attached as per Procedure? Yes No
4 4 TRA contain both job specific & site specific hazards Yes No
5 5
6 6
7 7
8
S. # ROLES NAMES DESIGNATION/COMPANY TASK RISK ASSESMENT APPROVAL RECORD
Prepared By:
PH (Performer)’ or
1st Review:
1 Supervisor of ‘Permit HSE / SZS
(By Supervisor of Permit Holder)
Holder’ in consultation with
AA
2nd Review:
2 TRA Team Member 1
(by site HSE rep)
Approved By:
3 TRA Team Member 2
(Issuing Authority/his designee)
e to hazard. The hazard is the potential to cause harm. The risk assessment is the technique of evaluating not just the likelihood of an
Catastrophic (5)
5
10
15
20
25
he likelihood of an event occurring, but also the outcome will be in terms of injury, loss, damage or harm.