Incoming Ahead /

Document ref. Document description Leader Forward to Forward date


date Delay
NAB-TCV-ACT-WP2-SHD-327-01 [LV] 8-10TH floor Lighting System Layout Plan (Individual System) 21/Dec/23 (5) Ravuth 21/Dec/23
NAB-TCV-ACT-WP2-SHD-328-01 [ELV] 8-10TH floor Public Address System Layout Plan (Individual System) 21/Dec/23 (5) Ravuth 21/Dec/23
NAB-TCV-ACT-WP2-SHD-331-00 [FF] 1st floor Fire Fighting System Layout Plan (Individual System) 30/Nov/23 (26) Ravuth 30/Nov/23
NAB-TCV-ACT-WP2-RFI-106-00 [MVAC] Missing Information for Duct Pipe and Pressure Relief Damper for Pressurization
18/Dec/23
System (8) Dara Jaime 18/Dec/23
NAB-TCV-ACT-WP2-MDS-080-00 [MEP] Lift, Dumbwaiter & Escalator 18/Dec/23 (8) Ravuth 18/Dec/23
NAB-TCV-ACT-WP2-SHD-345-00 [MEP] 2ND Floor Level - MEP Combined Services Access Panel 19/Dec/23 (7) Ravuth 19/Dec/23
NAB-TCV-ACT-WP2-SHD-346-00 [ELV] 8-10TH floor Access Control and CCTV System Layout Plan (Individual System) 21/Dec/23 (5) Ravuth 21/Dec/23
NAB-TCV-ACT-WP2-MDS-072-01 [PL] Testing and Commissioning of Submersible pump 21/Dec/23 (5) Ravuth 21/Dec/23
NAB-TCV-ACT-WP2-SHD-356-00 [MEP] 1ST Floor Level - MEP Equipment on the wall 22/Dec/23 (4) Ravuth 22/Dec/23
NAB-TCV-ACT-WP2-INS-616-00 [MEP] Inspection installation of uPVC conduit embedded for lighting for staircase 03 26/Dec/23
2MF to 3F 0 Samnang 26/Dec/23
NAB-TCV-ACT-WP2-RFA-119-00 [PL] Stop Valve (Brand COTTO) 26/Dec/23 0 Ravuth Dilip 27/Dec/23
NAB-TCV-ACT-WP2-MAS-051-02 [LV] Switch, Socket and Isolator Switch 26/Dec/23 0 Ravuth 26/Dec/23
NAB-TCV-ACT-WP2-MAS-137-03 [PL] Geotextile 26/Dec/23 0 Ravuth 26/Dec/23
NAB-TCV-ACT-WP2-INS-617-00 [MEP] 1F Inspection installation of Fire alarm System, Public address System and CCTV27/Dec/23
System 1 Dara 27/Dec/23
NAB-TCV-ACT-WP2-SHD-357-00 [MEP] 11TH Floor Level - MEP Ceiling Combined Services 25/Dec/23 (1) Ravuth 25/Dec/23
NAB-TCV-ACT-WP2-SHD-358-00 [MEP] 2ND Floor Level - MEP Equipment on the wall 28/Dec/23 2 Ravuth 28/Dec/23
NAB-TCV-ACT-WP2-SHD-340-01 [PL] 2ND floor Domestic Water Supply System Layout plan (Individual System) 29/Dec/23 3 Ravuth 29/Dec/23
NAB-TCV-ACT-WP2-INS-618-00 [MEP] 9F Inspection Installation of pipe sleeves & Opening Layout 29/Dec/23 3 Dara 29/Dec/23
NAB-TCV-ACT-WP2-SHD-359-00 [MVAC] 2ND Floor Ducting System Layout Plan (Individual System) 2/Jan/24 7 Ravuth 2/Jan/24
NAB-TCV-ACT-WP2-SHD-326-01 [LV] 8-10TH floor BMS & Power Supply for MVAC System Layout Plan (Individual System) 2/Jan/24 7 Ravuth 2/Jan/24
NAB-TCV-ACT-WP2-INS-621-00 [MEP] 9F Inspection Installation of PVC conduit embedded for Power socket, Power supply2/Jan/24
for MVAC and7 lighting Samnang 2/Jan/24
NAB-TCV-ACT-WP2-INS-622-00 [MEP] Inspection Installation of uPVC conduit at staircase 02 3F to 3MF 2/Jan/24 7 Samnang 2/Jan/24
NAB-TCV-ACT-WP2-INS-623-00 [MEP] 9F Inspection Installation WW PVC Pipe Sleeve for Plumbing System 2/Jan/24 7 Samnang 2/Jan/24
NAB-TCV-ACT-WP2-SHD-362-00 [PL] 4TH floor Storm drain and drainage system for Irrigation Layout plan (Individual System)
2/Jan/24 7 Ravuth 2/Jan/24