OPERATIONS

MANAGEMENT
Final Project
Duration
Activities Human resources Conections
(days)
1 - RESEARCH MARKET
OPPORTUNITIES 5 MARKETING SPECIALIST

2 - ANALISYS OF THE
COMPETITION 5 MARKETING SPECIALIST S TO S WITH 1

3 - SELECTION OF TARGET MARKETING SPECIALIST F TO S WITH 1


CONSUMERS 4

4 - ESTABLISH A QUALITY MARKETING SPECIALIST


MATRIX 1 RESEARCH SPECIALIST F TO S WITH 3

5 - ESTABLISH A MARKETING 10 MARKETING SPECIALIST F TO S WITH 4


STRATIGY RESEARCH SPECIALIST
Duration
Activities Human resources Conections
(days)
6 - DEFINIG THE GENERAL DESIGNER
PRODUCT DESIGN 7 DESIGN TEAM F TO S WITH 5

7 - DEFINIG THE SPECIFIC DETAILS DESIGNER


OF THE DESIGN 15 DESIGN TEAM S TO S WITH 6

8 - IDENTIFY THE CRITICAL DESIGNER F TO S WITH 6


ASPECTS 1 RESEARCH SPECIALIST

9 - EXTERNAL RESEARCH TO FIND DESIGNER S TO S WITH 6


WHERE TO IMPROVE 20 RESEARCH SPECIALIST

10 - INTERNAL RESEARCH TO FIND 10 DESIGNER S TO S WITH 6


WHERE TO IMPROVE RESEARCH SPECIALIST
Duration
Activities Human resources Conections
(days)
11 - WBS 5 PLANNING SPECIALIST S TO F WITH 9 AND 10

12 - COMPONENTS MANUFACTURING ENGINEER


MANUFACTURING 30 MANUFACTURING TEAM
DESIGN TEAM
S TO F WITH 11

13 - MARKETING RESEARCH FOR MARKETING SPECIALIST S TO S WITH 12


COMPONENTS ACQUISITION 2 MARKETING ASSISTANT

F TO S WITH 13
14 - ORDERS REQUESTS 5 MARKETING ASSISTANT

15 - CONTRACTS 3 FINANCE SPECIALIST


LAWYER
F TO S WITH 14
Duration
Activities Human resources Conections
(days)
16 - PRODUCT ASSEMBLY 2 PLANNING SPECIALIST S TO F WITH 9 AND 10

MANUFACTURING ENGINEER
17 - TESTING 2 MANUFACTURING TEAM
DESIGN TEAM
S TO F WITH 11

MARKETING SPECIALIST S TO S WITH 12


18 - REDESIGN 30 MARKETING ASSISTANT

F TO S WITH 13
19 - COST ANALYSIS 4 MARKETING ASSISTANT
LOGICAL NETWORK
CRITICAL PATH
TOTAL FLOATS

Tf A1= 0 Tf A8= 88
Tf A2= 0 Tf A9= 0 Tf A15= 20
Tf A3= 0 Tf A10= 0 Tf A16= 0
Tf A4= 0 Tf A11= 0 Tf A17= 0
Tf A5= 0 Tf A12= 0 Tf A18= 0
Tf A6= 0 Tf A13= 0 Tf A19= 0
Tf A7= 0 Tf A14= 21
LEVELING OF
RESOURCES
LEVELING OF
RESOURCES
ORDERING METHOD
activities criteria duration resources

A1 C1 5 R1

A2 C4 5 R1

A3 C1 4 R1

A4 C1 1 R1

A5 C1 10 R1
ORDERING METHOD
activities criteria duration resources

A6 C1 7 R2

A7 C3 15 R2

A9 C3 20 R2

A10 C3 10 R2

A11 C3 5 R3
ORDERING METHOD
activities criteria duration resources

A12 C3 30 R4

A13 C3 2 R1

A14 C3 5 R1

A15 C3 3 R5

A16 C3 2 R4
ORDERING METHOD

activities criteria duration resources

A17 C3 2 R4

A18 C3 30 R4

A19 C3 4 R5

A8 C1 1 R2
AHEAD ORDERING