Professional Documents
Culture Documents
Pile Foundation
Pile Foundation
ARCHITECTURAL
STRUCTURES
MODULE 5
PILE FOUNDATION 1
TOPIC OBJECTIVE
• To understand the principles of friction piles
and end bearing piles, driven piles and
bored piles, and the methods based on
installation.
• To assimilate the principles involved in pile
foundation application and construction
methodology.
• To recognize the risks associated in the
installation process of pile foundation. 3
INTRODUCTION
4
The Leaning Tower of Pisa (Torre di Pisa)
A freestanding bell tower, of the cathedral of the Italian city of Pisa.
Constructed on August 9, 1173. The seventh floor was completed in
1319 and in 1372 the bell chamber was added for its final design. To
date the tower is 848 years old.
The height of the tower is
55.86 meters from the ground
on the low side and 56.67
meters on the high side. Its
estimated weight is14,500
metric tons.
8
The 3 meter foundation was set on weak unstable subsoil that
caused the tilt and dropped 2 meters deep over the years,.
8
It was in February 27, 1964, when
the government of Italy requested
aid in preventing the tower from
toppling, or at least keep to a safer
angle.
In May 2008, the team of engineers
working on its restoration
announced that the Tower had been
stabilized for the first time in its
history. They stated it would be
stable for at least 200 years.
9
In summary,
a) the tilting of the bell tower
was largely attributed to the
differential stability of the
ground to properly support
the weight of the structure,
displacing the horizontal
foundation of the tower.
b) Technology was the key to
the success of the
restoration. 4 13
Soil Mechanics
Laser scanners
Computer Aided Analysis
Modern
Equipment
Geotechnical engineering
is the branch of civil engineering concerned with the
mechanical behavior of earth materials, concerned
with construction occurring on the surface or within
the ground, earthwork and foundation construction to
mitigate risks in foundation displacement or
settlements.
Soil Mechanics
12
PILE FOUNDATION
is used for those tall
buildings of massive
structures, which
require foundations
that can bear the
load of thousands of
tons, most probably
in unstable or difficult
soil conditions.
4
PILES
are vertically installed
structural elements to
prevent the
displacement of a
foundation produced
by the weight of a
structure, or an
overturning moment
PIER OF BRIDGE 5
It is usually installed in rows at an even distance
to produce a uniformly distributed load capacity.
6
It is a Vertical
shaft buried deep
in the ground to
transfer the
weight of the PILE CAP
whole structure,
live loads and
movable loads or
uplift loads
produced by lateral
forces on the
7
superstructure.
Piles will increase the stability
of tall structures, where the
foundations are subjected to
large eccentric loads, inclined
loads and overturning
moment.
8
The eccentric load will produce an
overturning moment at the
clockwise direction.The horizontal
foundation at point A will deflect
upwards while at point B will
deflect downward, if pile A is uplift,
thus in tension it is called tension
pile,…..while pile D is a A B C D
compacting pile.
9
It is a Deep PILES
Foundation to
transfer the load
or weight, and the
imposed loads,
such as movable
loads, live loads,
and environmental
loads to guarantee
the integrity of a
massive structure.
6
TYPES OF PILES
Piles are classified on the basis of
the following characteristics:
➢ Mechanism of load transfer
➢ Type of materials
➢ Method of installation 10
Mechanism of
load transfer
The ability of a pile to resist
settlement is dependent on
the cohesive qualities of
the soil which produce
friction along the length of
the pile shaft.
FRICTION PILE
11
Mechanism of load transfer
When a pile toe rest on a
founding layer or hard
bearing strata, but the soil is
too fluid to grip the shaft, all
the loads are transferred to
the longitudinal axis of the
shaft.
TIMBER PILES 14
Timber piles are made of-tree trunks with
structural importance due to its ability to
withstand shear force and bending moment with
a load bearing capacity of 100 to 250 KN per pile.
It is the most economical pile material.due to its
flexibility in handling and installation. However
its length, and diameter is limited due to its
natural growth.
15
The method of installation is, driven to the ground with a
hammer of 250 to 1,000 Kg. of weight, displacing the
earth as it is forced to penetrate beneath the strata. 16
The head is protected by a steel
helm to avoid splinter, while the
toe is protected by a metal
shoe.
17
STEEL PILES
The cross sectional area vary from different forms,
circular, pipe, I-section, H-section, sheets, hexagonal,
etc. it’s load bearing capacity is 1,800 KN per pile
18
Maximum
length of steel
pipes are
practically
unlimited due
to its ability to
be welded.
19
Steel piles are basically
driven to the ground,
wide flange beams & I-
beams proportioned to
withstand the hard
driving stress to which the
pile may be subjected.
20
Ability to penetrate
through light obstructions
displacing lesser soil due
to its minimal cross
sectional area, therefore
occupying lesser space.
It is a non-displacement method
because
the soil is extracted out
and replaced by casting a reinforced
concrete mix. 26
BORED PILES
28
CASED PILES are also categorized into two types
The permanent cased and the temporary cased PILES
29
In summary;
5
Detailed drawing requirement
6
EXECUTION STAGE
7
Stage 1 - Pre-drilling
8
Stage 2 –
installation of
temporary casing
11
Stage 4 – installation of
the reinforcement cage.
CHECK
➢ Specified number and
diameter of the
reinforcing bars
➢ Spiral hoops diameter
and pitch
➢ Tack welding to
specification 12
Stage 4 –
CHECK
➢ Correct lap length
➢ Correct length
above pile
➢ Free of dirt and
corrosion
➢ Roundness and
specified clear
cover 13
Stage 5 – Installation
of tremie pipe and
concrete pouring
➢ Slump test
➢ Check Level of
concrete to tremie
height 2 M
➢ Toe of casing
14
Stage 5
Removal of
temporary
casing while
the concrete
is still fluid,
by judgement
call of the
technician.
15
END OF MODULE 3
THANK YOU!
31