Professional Documents
Culture Documents
Power Flow Monitoring and Analysis For 24.6 MW at 6.9 KV Bus Diesel Power Plant (DPP) Using ETAP
Power Flow Monitoring and Analysis For 24.6 MW at 6.9 KV Bus Diesel Power Plant (DPP) Using ETAP
Power Flow Monitoring and Analysis For 24.6 MW at 6.9 KV Bus Diesel Power Plant (DPP) Using ETAP
Power Flow Monitoring and Analysis for 24.6 MW at 6.9 kV Bus Diesel Power Plant
(DPP) Using ETAP
Abstract—It is obvious that power flow study and analysis are carry out electrical power flow analysis of diesel engine
important to any kind of electrical power system engineering. power plant. The software is a suit of fully integrated
The main purpose of this research paper is to study and software solutions including loadflow, short circuit, motor
analyze the power flow and system stability of the 24.6 MW starting, cable ampacity, relay coordination, grounding
Diesel Power Plant (DPP) which is the cement manufacture system study, etc., and transient stability studies. Power flow
located in Cambodia at 6.9 kV bus using the commercial study for this paper is the electrical power system analysis at
electrical transient analysis program called ETAP. S uch a the steady-state condition to check and confirm voltage drops,
power plant comprises of four diesel generators with the
voltage regulations, active power and reactive power flow
generation capacity of 6,150 kW each. There are three
limits, transformers capacities, cables sizing, power factor at
outgoing feeders to different load type in various processes in
this manufacture. Power flow study and analysis in this paper
the interconnection point, etc., for various operating
includes steady-state conditions to assure the voltage drop,
scenarios.[4]
voltage regulation, active and reactive power flow limits,
transformer capabilities, cable sizing, and power factor at all II. SINGLE LINE DIAGRAM OF CASE UNDER ST UDY
connection points. Four cases of operations are in Fig. 1 shows the single line diagram of the co mplete
consideration in this research. All diesel engine generators power system which is under study. DPP has four diesel
assume to be operating in isochronous load sharing control. engine generators operating as power island supplying
Nominal system voltage is at 6.6 kV plus/minus 5%. Maximum electric power to their customer, the Main Power Plant
continuous operating voltage of the interest island system is (MPP), through 6.9 kV feeders. MPP also has steam turbine
105% of 6.6 kV and minimum continuous operating voltage is generator operating in parallel with DPP. DPP exports power
95% of 6.6 k V nominal system voltages. All motors loads are through three outgoing feeders BAO901, BAO902, and
IEC standard design, typical motor load data from ETAP BAO903 to MPP. At MPP, there is 6.6 kV 7,500 kVA steam
software database is used for this study. The simulation results
turbine connected to 6.9 kV substations which is also
will be shown here in this paper. The simulation results supplied from DPP power plant through feeder BAO901.
analysis, discussion and conclusion are also illustrated.
DPP
Diesel Diesel Diesel Diesel
Keywords-power flow; system stability; ETAP; diesel power Generator 1 Generator 2 Generator 3 Generator 4
plant (DPP)
308
No overloading condition exists for all electrical amount of exported power is dependent upon the operating
equipment e.g. generator, transformers, switchgears, set point given by operator two diesel engine generators
cables, etc. operate in isochronous load sharing control with excitation
No reversed power condition exists for all generators. system operating in automatic voltage control, the other two
generators are in standby.
No under/over-excitation condition presented on all
generators. D. Case Study 4
This is the case when MPP operating at a certain loading
IV. CASE ST UDIES condition which MPP loads seems to be min imu m causing
Study cases are established for various possible practical reversed power fro m M PP plant to DPP power p lant through
scenarios in plant operations. BAO901 line with lagging power factor. MPP steam turbine
generator operates in base load control, droop mode with
A. Case Study 1 excitation system operating in power factor control. The
This is the operating case when MPP is operating during amount of exported power is dependent upon the operating
normal operation at maximu m loading condition. MPP steam set point given by operator. Three diesel engine generators
turbine generator operates in base load control, droop mode operate in isochronous load sharing control with excitation
with excitation system operating in power factor control. The system operating in automat ic voltage control, the other
amount of exported power is dependent upon the operating generator is in standby.
set point given by operator. Three diesel engine generators of
DPP operate in isochronous load sharing control with V. SIMULAT ION RESULT
excitation system operating in automatic voltage control, the
other is in standby. A. Loadflow Study Summary
Fro m the results of loadflow studies, Case 1 to Case 3
B. Case Study 2 shown in Fig. 4 to Fig. 6 respectively, DPP operates at high
This is the case when MPP operating at a certain loading loading condition and since the fuel consumption depends
condition which MPP loads seems to be min imu m causing upon the active power output but not reactive power output,
almost no active power exported from DPP to MPP power these three cases should not be the concerned case of the
plant through line BAO901 with lagging power factor. MPP problem for high fuel consumption. The worst case scenario
steam turbine generator operates in base load control, droop is likely to be Case 4 shown in Fig.7 which it is assumed that
mode with excitation system operating in power factor maximu m nu mbers of diesel generators are in operation
control. The amount of exported power is dependent upon while MPP plant steam turbine generator delivers power at
the operating set point given by operator. Two diesel engine its maximu m continuous rated power. It is realized that
generators operate in isochronous load sharing control with steam turbine at MPP operates in base load control and the
excitation system operating in automatic voltage control, the excitation system operates in power factor control which the
other two generators are in standby. set point are to be set by MPP operator. The excitation
system power factor set point is set at nearly 1.0 or 1.0 PF.
C. Case Study 3 DPP operates as swing source operating in isochronous
This is the case when MPP operating at a certain loading frequency control mode and excitation system operates in
condition which MPP loads s eems to be min imu m causing automatic voltage control mode to supplement the shortfall
reversed power fro m M PP plant to DPP power p lant through of MPP cement plant loads. Both DPP and MPP generators
line BAO901 with lagging power factor. MPP steam turbine operate in parallel to supply most of MPP cement plant loads.
generator operates in base load control, droop mode with
excitation system operating in power factor control. The
309
Figure 5. Case Study 2.
310
In normal operation, three diesel engine generators at maximu m nu mbers of generators operating at high
DPP operate in parallel with load sharing control function loading condition.
and the other is in standby (shutdown). During steady state
operation when MPP load does not abruptly decrease, The followings are the recommendations for the possible
solutions.
one diesel engine generator will be s hutdown depending on
the scheduled load profile given fro m MPP. However, A. Performance test for diesel engine generator efficiency.
recently there were the abrupt loads variations at MPP plant
Since there is no guarantee efficiency from Wartsila who
resulting in difficulty in power flow control at DPP power
is diesel engine manufacturer for low load operation
plant.
especially at load below 75% of the engine rated power, in
The result of MPP operation as base load and MPP
order to understand the expense occurred during pats period
power plant operates as swing source causes MPP power
of high fuel consumption, it is recommended that d iesel
plant operates to supplement the shortfall or absorb the
engine generator set be carried out the performance test and
excess of power required by MPP plant. Th is result in the
record the efficiency and fuel consumption fro m no load to
situation that MPP supplies power back to DPP power plant
full load. The result can be used in operation planning to
through feeder BAO901. In fact this excess power supplied
keep most or all generators operating at sufficiently high
fro m MPP flows to another feeder, BAO903. Therefore there
efficiency to minimize fuel expense. The result of test can
is no real reversed power to diesel engine generator at DPP
also give the information whether there are any other factors
power plant.
contributing to high fuel expense other than sole diesel
In case MPP operates their own steam turbine generator
engine fuel consumption.
at its higher output or at its maximu m continuous rated
power, during MPP plant low load operation, there will be B. Disable One Diesel Generator Load Sharing Control.
the excess power supplied back to DPP power plant through
Since the problem lies on the issue that there is the
feeder BAO901. Ho wever, the reactive power, kVar, still
mo mentary unbalance in power supply from DPP and the
flow fro m DPP power plant to MPP plant since MPP steam
MPP loads demand for situation that the number and
turbine generator seems to operate in power factor control
capacity of the operating diesel engine generators are more
mode and as such supply almost no reactive power.
than those necessary to supply MPP loads, however the DPP
It is apparent that diesel engine generators at DPP power
diesel engine generators cannot be shut down since there
plant during normal operation normally operates with three
might be unexpected MPP loads increment following such
generators in operation and one set in standby. However
mo mentary loads decrement and as such diesel generators
during some period with abrupt decreasing in MPP loads, all
still have to keep running at low loads condition, it is
these generators are still in operation resulting in engine
advisable that one diesel generator may needs to be
operation at its low loading condition and thus at its low
disconnected from group load sharing control and have those
operating efficiency. As it are the characteristics of diesel
majority of generators still in load sharing control operate at
engine that the efficiency at low load operation dramatically
approximately 75% to 80% of its rated capacity, to have
decreases compared with operation at 75% or h igher and this
them operate at high efficiency as much as possible, and
results in higher fuel consumption of diesel engine generator.
sacrifice one generator operating at high loading condition in
Since it is difficult to estimate the dynamic change in
droop control mode. However those generators operating in
MPP load, it is difficult for DPP operator to make decision
load sharing control should not operate at its full rated
on whether to shut down one diesel engine generator in order
capacity but should have some s mall margins for spinning
to balance power supply and mo mentary load demand and
reserve. The spinning reserve capacity on each generator
have all diesel engine generators operate at load higher than
depends on the expectation of the maximu m sudden load
75% to keep operation of diesel engine generators at high
increment shared between all of those generators operating in
efficiency. In summary, the variation in operating power
load sharing control. If after changing control mode of
output of DPP is highly dependent on the following factors;
generators, MPP loads tend to be settled at this condition or
MPP operating loads and MPP steam turbine generator
would not increase higher than the estimated maximu m
active power output.
sudden step load or load rejection for long period, DPP
VI. CONCLUSIONS AND RECOMMENDAT ION SCHEMES operator may co mmunicate with MPP operator to request for
shutting down the generator running in droop control to
The problem of high fuel consumption, if it is not minimize fuel consumption at low operating loading
attributed fro m factors other than operating fuel consumption condition, however DPP still have sufficient spinning reserve
of diesel engine, is due to the fact that diesel engines operate for any sudden load changes not higher than that DPP
at low loading condition. The solution to solve such problem provided as spinning reserve. For examp le one diesel
are principally as follows; generator may need to be isolated from load sharing control
Try to operate diesel engine at high loading of the group of three generators and change to droop control
condition which will increase engine operating instead while those two generators still remain in
efficiency. isochronous load sharing control. One generator which is to
Minimize numbers of d iesel engines generators be operated in droop control, its active power output set
operating at low loading condition or to keep point shall be set at high loading condition while remaining
311
two generators operating in load sharing control should be [2] N. Nisar et al., Analysis and optimization of 132KV grid using ETAP,
kept to operate at approximately 75%-80% of its rated Power Generation System and Renewable Energy T echnologies
(PGSRET ), (2015), pp. 1-6.
capacity.
[3] C.J.Soni, P.R.Gandhi, and S.M. Takalkar, Design and analysis of 11
C. Battery Energy Storage System. KV Distribution System using ETAP Software, International
Conference on Computation of Power, Energy Information and
The system needs investment on energy storage system Commuincation (ICCPEIC), (2015), pp.451-456.
using battery system. Battery capacity depends on the [4] Glenn W. Stagg and Ahmed H. El-Abiad, “Computer Methods in
required maximu m expected step load and back up time. Power System Analyses”, Bib ID 537411, New York, McGraw-Hill
However this solution is not practically feasible since this [1968], pp. 110-127.
needs huge investment in the above new equip ment and [5] Annual Report, “Kampot Diesel Power Plant Loadflow Study
building and facilit ies. The system still has disadvantage Report”, 2012.
in that when battery is fully discharged or is being [6] Gonen, T., “Electric Power Transmission System Engineering”,
charged before reaching fully charged stage, if the step Wiley, New York, 1986, pp. 87-93.
load comes, the system cannot effectively supply power [7] Keith Brown, Farrokh Shokooh, Herminio Abcede and Gary
“Donner interactive simulation of power system: etap techniques and
to load. Nevertheless this solution still cannot solve the applications”, IEEE Flour Daniel Inc. Irvine, ISBN: 0-87942-553-9,
problem of load rejection. Page(s): 1930-1941 vol.2, 7-12 Oct 1990, Seattle, WA, USA.
REFERENCES
[1] R.A.J. Khan et al., Analyses and Monitoring of 132 kV Grid using
ET AP Software, International Conference on Electrical and
Electronics Engineering (ELECO), (2009), pp. 113 – 118.
312