MOC 01 - NTI Tanjung Karang - Tank Pre-Fit Issue
MOC 01 - NTI Tanjung Karang - Tank Pre-Fit Issue
MOC 01 - NTI Tanjung Karang - Tank Pre-Fit Issue
How?
Describe how the To omit the pre-fit sump work. This will reduce the total height of the tank on low
change should be made loader trailer to 4.6m. The current height of the overhead cables from the ground is
around 4.65m to 4.7m (refer photos attached).
Comments:
Provide any further Kindly Refer Attachment for References
comments to support
the change
Page 1 of 5
Management of Change Proposal & Authorities QMS-TM-MOC Rev2
☐ New technology used for the ☐ New of changed policy to be ☐ Change in contractors being
first time implemented used
☐ New materials being used ☐ Traffic management plan ☐ Changes affecting other parts
modifications of the business
Page 2 of 5
Management of Change Proposal & Authorities QMS-TM-MOC Rev2
Client
Comments / conditions
Page 3 of 5
Management of Change Proposal & Authorities QMS-TM-MOC Rev2
AMENDED DCP /
DISTRIBUTION:
Page 4 of 5
Management of Change Proposal & Authorities QMS-TM-MOC Rev2
Attachment 1
Page 5 of 5