MONITORING WATERPROOFING

GROUND FLOOR

Type Material : Brush Bond Flex ex Fosroc

Waterproofing Cementitious (Coating)

No Floor/Room Waterpounding Waterpounding WP Screed


Cleaning & Chamfer Repair Injection Grinding & Cleaning Coating Closing & BA
Structure (1x24 Jam) (2x24 Jam) (by civil)
Ground Floor action status action status action status action status action status action status action status status
1 Kitchen (Chiller Area) 18/12/23 OK 14/12/23 Not OK 19/12/23 OK 18/12/23 OK 20/12/23 OK 30/12/23 OK 02/01/24 OK Done

2 Trash Room 19/12/23 OK 21/12/23 OK - - 22/12/23 OK 28/12/23 OK 02/01/24 OK 05/01/24 OK Done

3 Staff Canteen 27/12/23 OK 30/12/24 OK - - 04/01/24 OK 07/01/24 OK 11/01/24 OK 13/01/24 OK Done

4 Ablution Room 22/12/23 OK 24/12/23 OK - - 26/12/23 OK 27/12/23 OK 29/12/23 OK 02/01/24 OK Done

5 Staff Female Toilet 21/12/23 OK 23/12/23 OK - - 25/12/23 OK 27/12/23 OK 29/12/23 OK 02/01/24 OK Done

6 Staff Male Toilet 20/12/23 OK 23/12/23 OK - - 25/12/23 OK 28/12/23 OK 02/01/24 OK 05/01/24 OK Done

7 KEG Room 21/12/23 OK 24/12/23 OK - - 26/12/23 OK 27/12/23 OK 29/12/23 OK 02/01/24 OK Done

8 Nursing Room 29/12/23 OK 03/01/24 OK - - 06/01/24 OK 11/01/24 OK 14/01/24 OK 16/01/24 OK Done

9 Disable Toilet 27/12/23 OK 03/01/24 OK - - 09/01/24 OK 11/01/24 OK 14/01/24 OK 16/01/24 OK Done

10 Janitor 29/12/23 OK 03/01/24 OK - - 09/01/24 OK 11/01/24 OK 14/01/24 OK 16/01/24 OK Done

11 Female Public Toilet 26/12/23 OK 03/01/24 OK - - 06/01/24 OK 11/01/24 OK 14/01/24 OK 16/01/24 OK Done

12 Male Public Toilet 29/12/23 OK 03/01/24 OK - - 09/01/24 OK 11/01/24 OK 14/01/24 OK 16/01/24 OK Done

13 Outdoor Dinning 03/01/24 OK 17/01/24 Not OK 22/01/24 OK 24/01/24 OK 30/01/24 OK 02/02/24 OK 05/02/24 OK Done
MONITORING WATERPROOFING
LANTAI 2

Type Material : Brush Bond Flex ex Fosroc

Waterproofing Cementitious (Coating)

No Floor/Room Waterpounding
Cleaning & Waterpounding WP Screed
Structure (1x24 Repair Injection Grinding & Cleaning Coating Closing & BA
Chamfer (2x24 Jam) (by civil)
Jam)
Lantai 2 action status action status action status action status action status action status action status status
1 Male Toilet 14/01/24 OK 15/01/24 OK - - 17/01/24 OK 20/01/24 OK 22/01/24 OK 24/01/24 OK Done

2 Female Toilet 14/01/24 OK 15/01/24 OK - - 17/01/24 OK 20/01/24 OK 22/01/24 OK 24/01/24 OK Done

3 Toilet Public Female 15/01/24 OK 17/01/24 not OK 18/01/24 OK 19/01/24 OK 20/01/24 OK 22/01/24 OK 24/01/24 OK Done

4 Toilet Public Male 15/01/24 OK 17/01/24 OK - - 19/01/24 OK 20/01/24 OK 22/01/24 OK 24/01/24 OK Done

5 Janitor 15/01/24 OK 17/01/24 not OK 18/01/24 OK 19/01/24 OK 20/01/24 OK 22/01/24 OK 24/01/24 OK Done

6 Smoking Terrace & Planter Box 28/01/24 OK 31/01/24 OK - - 02/02/24 OK 04/02/24 OK 06/02/24 OK 08/02/24 OK Done

7 Outdoor Dinning & Planter Box 07/02/24 OK 10/02/24 OK - - 13/02/24 OK 20/02/24 OK 21/02/24 OK - - -

8 Compressor Room 09/02/24 OK 12/02/24 OK - - 18/02/24 OK 20/02/24 OK waiting H+2 - - - -

9 Blower Room not ready - - - - - - - - - - - - - -

10 Roof Deck not ready - - - - - - - - - - - - - -

11 Cold / Salad Desert 20/02/24 OK - - - - 20/02/24 OK 20/02/24 OK 21/02/24 proses

12 Daily Chiller 20/02/24 OK - - - - 20/02/24 OK 20/02/24 OK 21/02/24 proses


MONITORING WATERPROOFING
LANTAI 3

Type Material : Brush Bond Flex ex Fosroc

Waterproofing Cementitious (Coating)

No Floor/Room Waterpounding
Waterpounding Screed
Cleaning & Chamfer Structure (1x24 Repair Injection Grinding & Cleaning Coating Closing & BA
WP (2x24 Jam) (by civil)
Jam)
Lantai 3 action status action status action status action status action status action status action status status
1 Toilet 29/01/24 OK 31/01/24 OK - - 02/02/24 OK 02/02/24 OK 05/02/24 OK 07/02/24 OK Done

2 Janitor 30/01/24 OK 31/01/24 OK - - 02/02/24 OK 02/02/24 OK 05/02/24 OK 07/02/24 OK Done

3 Female Toilet 13/02/24 OK waiting - - - - - - - - - - - -

4 Male Toilet 12/02/24 OK waiting - - - - - - - - - - - -

5 Outdoor Bar 05/02/24 OK 07/02/24 OK - - 10/02/24 OK 12/02/24 OK 14/02/24 OK 16/02/24 OK Done

6 Roof Deck 09/02/24 OK 12/02/24 not OK 13/02/24 OK 16/02/24 OK 17/02/24 OK 20/02/24 proses - - -
MONITORING WATERPROOFING
ROOFTOP

Type Material : Guard PU Seal Pro Ex. Movex

Waterproofing PU (Coating)

No Floor/Room Cleaning & Grinding & Layer 3 + Silica Layer 3 + Silica Geotex + Screed
Layer 1 Layer 2 Screed ( by civil ) Layer 1 Layer 2
Chamfer Cleaning Sand Sand ( by civil )

Rooftop action status action status action status action status action status action status action status action status action status action status
1 Zona 1 OK OK 22/01/24 OK 23/01/24 OK 24/01/24 OK Done OK

2 Zona 2 OK OK 16/01/24 OK - - 19/01/24 OK Done OK

3 Zona 3A OK OK 23/01/24 OK 24/01/24 OK 29/01/24 OK Done OK

Zona 3B 18/02/24 OK 20/02/24 OK

4 Zona 4A OK OK 15/02/24 OK 15/02/24 OK

Zona 4B OK OK 18/02/24 OK 19/02/24 OK

5 Zona 5A OK OK 18/02/24 OK 19/02/24 OK

Zona 5B OK 21/02/24 proses

6 Zona 6 OK 21/02/24 proses

7 Zona 7 ( T-Line) OK OK 12/02/24 OK 13/02/24 OK 18/02/24 OK Done OK