i. CRS sanctions must be obtained for launching steel girders over railway tracks and traffic and power blocks arranged.
ii. The track must be protected according to railway manual and wind speed cannot exceed 15 kmph during launching.
iii. Materials, cranes, trestles, winches, wire ropes and safety nets must be arranged and the site protected before launching begins.
Original Description:
Original Title
specification for launching of steel girders over railway track
i. CRS sanctions must be obtained for launching steel girders over railway tracks and traffic and power blocks arranged.
ii. The track must be protected according to railway manual and wind speed cannot exceed 15 kmph during launching.
iii. Materials, cranes, trestles, winches, wire ropes and safety nets must be arranged and the site protected before launching begins.
i. CRS sanctions must be obtained for launching steel girders over railway tracks and traffic and power blocks arranged.
ii. The track must be protected according to railway manual and wind speed cannot exceed 15 kmph during launching.
iii. Materials, cranes, trestles, winches, wire ropes and safety nets must be arranged and the site protected before launching begins.
Specifications for launching of ROB girders over railway tracks
i. CRS sanctions should be obtained for launching scheme of girder.
ii. Traffic and power blocks are to be arranged for erection of steel girder over Railway Track. iii. Track is to be protected in accordance with relevant clauses of Indian Railways P. Way Manual. iv. Pulling/ launching of the girder shall be stopped in case wind speed at site exceeds 15 kmph and it shall be made sure that weather conditions are normal and visibility is clear. v. Level & compact the ground as per requirement for assembly of trestle, girder & movement of crane on launching end side. vi. Arrange material, crane, cribs/ trestle, 2 pulling winches & 2 restraining winches of sufficient capacity, wire rope of suitable grade etc. for execution of work. vii. Safety net shall be provided under the girders while fixing the bracing and shuttering work. viii. Clearance from Railway Track to be maintained in accordance with Indian Railway Schedule of Dimensions for Broad Gauge. ix. Protect the site of work for any trespass of any living beings. x. Ground at the location of trestle pedestal should be compacted to attain safe bearing capacity of soil. Field engineer should certify that SBC of soil is more than foundation pressure at foundation level. xi. Launching Track should be laid in correct alignment & level on trestles for longitudinal slewing of girder. xii. Speed restriction of 20 kmph is to be imposed before start of work & will be continued up to completion of work. xiii. Skid plate surface for skidding arrangement shall be smoothened by lubrication. It shall be ensured by field engineer, that there should be no gaps in skid plate, which should be closed by welding & smoothened by grinding. xiv. Before launching of girder, it must be ensured that fabrication of girder and its inspection have been done as per approved QAP (Quality Assurance Plan) & WPSS (Welding Procedure Specification Sheets). xv. All steel to steel member will be connected with tack weld to avoid any longitudinal & transverse movement. xvi. Pulling arrangement shall be trial tested with actual load well before taking traffic and power block. xvii. Fabrication of BSG shall be done after locking the skidding arrangement with suitable method. Locking shall also be done after each stage of pulling to prevent from skidding. xviii. The condition of crane shall be strictly observed in the light of Railway Board instructions issued from time to time. xix. Any activity near or over existing railway track shall be performed under traffic & power block.