Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

PIPELINE ROUTING CONSIDERATION

HTTPS://EPCMHOLDINGS.COM/PIPELINE-ROUTING-CONSIDERATION/

Overview of the Article

Pipelines provide the most economical and efficient means of


conveying fluid over long distances. In the oil and gas sector,
pipelines are used to convey liquid and gaseous hydrocarbon
from various facilities as may be required.

Due to the difficult terrains encountered along the pipeline route,


pipeline construction is difficult. An accurately selected pipeline
route significantly reduces the effort required to design and
construct the pipeline.

This article is aimed at explaining pipeline routing for onshore


pipelines. The routing discussed is in conjunction with the survey
and soil investigation performed to firm up the pipeline route.
Factors to be considered during pipeline routing will be discussed.
Though the routing considerations stated here are mainly for an
onshore pipeline, some offshore or water bodies considerations
are fused into the article
Figure 1: Ongoing Pipeline Construction on a ROW

2 Introduction

Pipelines may traverse a few kilometres, a hundred or thousands


of kilometres. In the case of short pipelines, routing is easy;
however, as pipelines become longer, pipeline routing becomes
more difficult.

A pipeline may be entirely onshore, offshore or both. Pipelines may


be designed to be installed above ground or below ground. The
installation state also greatly influences the selection of the
pipeline route.

Various obstacles may be encountered between a pipeline’s start


and endpoint. These obstacles include roads, railways, water
bodies, bad soil conditions, and utilities. The above-listed
parameters greatly influence the pipeline route.

Pipeline routing is performed to determine the optimal route from


the pipeline’s start to the endpoint.
Pipeline routing is a key activity performed during the design stage
of a pipeline. It is performed across all the design stages including
Conceptual stage, Front end engineering design and detailed
engineering design. In some cases, minor changes may be made
during the construction stage. The changes during construction
may result from uncaptured obstacles and information during
route surveys and soil investigations.

Pipeline routing considerations include:

• Establish the shortest possible route. Shorter route results in a


reduced cost of material and construction. Short route may
also eliminate the need for intermediate pumping or
compression station but this may not entirely be true if there
are numerous obstacles along the route.
• Minimize roads, rail and water bodies crossing.
• Minimize the number of bends. Bends angle should be limited
to maximum 90 degrees. The bend radius should satisfy the
requirements of codes and standards such as ASME B31.4
and 31.8.
• Avoid inhabited areas as much as possible.
• Utilize existing pipeline right of way as much as possible.
Utilizing other utility infrastructures and cables ROW should
be considered. Interference between cables and pipelines
should be properly investigated before the decision of
parallel routing is taken.
• Minimize environmental impacts by avoiding protected
areas, cultural resources etc.
• Avoid areas with side hills.
• Access from the existing road to the ROW is key for
transporting construction equipment and pipeline materials..
3 Developing A pipeline Route

Route development takes several stages; the development of the


route is performed on a desktop by marking on maps which may
be available in the public domain. One of the key software used for
preliminary route development is google earth. It provides satellite
imagery and a street view of the earth which is utilised for pipeline
routing. Other more advanced software’s utilised include ArcGis
and QGis. Offshore pipeline preliminary routings may be
developed using a combination of google earth maps and
admiralty charts. Note the charts used should be the latest version
to show all facilities and infrastructures within the pipeline route.
As the route is developed, it is refined until the final route is
approved. Also, note that the final route must have gone through
several approval stages from local to federal government
depending on the Country’s regulations.
Figure 2: Cropped Out section of an Admiralty Chart

The admiralty charts provide details of water body’s depth, the


location of obstacles such as existing pipelines and cables, and
the location of facilities such as seaports, anchoring zones etc.

Below are the steps to be taken to develop a pipeline route. Note


these steps may vary due to design requirements or local
regulations.

3.1 Identify the Connecting Facilities

A pipeline must connect at least two facilities, e.g. a fuel storage


facility and an export or import terminal, a crude processing
facility and a refinery, a wellhead and a flow station, a gas
processing facility and gas distribution facility etc.

The first step is locating these facilities appropriately on a map or


GIS software. For new facilities, location selection is not solely the
responsibility of a pipeline engineer but a joint task performed by
all departments (process, piping, mechanical and pipeline). The
client should be well briefed on selecting the respective facilities.
The coordinates of these locations are noted.

3.2 Develop Preliminary Routes on Maps

After identifying the facilities, preliminary routes are developed.


While developing a pipeline route, developing more than one
option may be required, which is further analysed to determine the
best. In some instances, Company’s best option presented to the
government for approval is never approved. An already-
developed alternative route is then presented.
Developing a preliminary pipeline route is mostly performed using
google earth software.

Google Earth seems to be the most effective tool for preliminary


pipeline routing. It uses satellite imagery that is periodically
updated, thus providing reliable information. Existing pipeline and
powerline right-of-way scars can be easily seen on Google Earth
satellite imagery because the scars from construction or
maintenance are evident. Roads, rails, rivers and other water
bodies are also easily identified.

The engineer gradually and carefully identify paths that are


predominantly free from obstacles, i.e., from buildings, crossings,
etc. This is done by carefully placing marks along the map and
using a line to connect the marks. Note the coordinates of the
marks are noted as they are placed along the route.

A pipeline should be routed to avoid cemeteries, reserved forests


and lands housing sacred objects.

Below is a preliminary route drawn on google earth for illustration.


The route connects a proposed power plant to an existing terminal
gas station. The various turning points along the route are aimed
at minimising pipeline proximity to existing facilities.
Figure 3: Preliminary Route Drawn on Google Earth

3.3 Identify Obstacles along the Routes

After the preliminary routes are developed, all obstacles are


properly noted and documented. In addition to marking the
obstacles on the route, a detailed list of all obstacles with their
description is developed. The obstacle list should include details
such as:

• The name of the obstacle, e.g. road crossing, river crossing,


railway crossing, pipeline crossing.
• The centre point coordinate of the obstacle.
• Description of the obstacle this may include information such
as dual carriageway, major river.
• The start coordinate of the obstacle, i.e. start point of the
road or river crossing.
• The end coordinate of the obstacle.
• The total length of the obstacle, i.e. total river crossing length,
total road crossing length.
• The state, local government and community the obstacle is
located

3.4 Identify and Review Pipeline Impact on Communities

The community should be consulted during the planning stage of


the pipeline because the pipeline has a significant impact on the
community. Pipeline and Community safety should be reviewed,
and the route updated to accommodate all recommendations.
Safety of the pipeline is key; close community interaction with the
pipeline may lead to pipeline vandalisation.

The land is also critical to the community; therefore, the ease of


land acquisition from the community and other organisations
should be factored into the pipeline route.

3.5 Select the Most Feasible Route for Survey

In this sense, the preliminary most feasible route does not refer to
the route with the lowest construction cost. In selecting the most
feasible route, the pipeline’s safety and constructability are key
factors. The pipeline’s impact on the environment and other
factors should be considered. The most feasible route is thus
presented to the government to seek a survey permit.
3.6 Develop the Pipeline Route Utilising Appropriate Scale

After the preliminary route is marked out on maps or appropriate


software, the route is further presented on a standard back sheet
with an appropriate scale.

The route may be developed on A1 or A2 paper with an


appropriate scale depending on the length of the pipeline. Typical
drawing scale used includes 1:50,000, 1:100,000 etc

3.7 Obtain a Permit to Survey from Government

Obtaining a permit to survey is very important because the


pipeline route developed is through lands owned by individuals,
organisations, etc.; therefore, the appropriate government
authority must grant a permit. The developed route is submitted
with the application for the permit to survey. After reviewing the
route and the application, the government may grant a permit to
survey or reject it. The government may give reasons for rejection,
and alternate routes may be developed and resubmitted.

A granted permit permits the holder, together with his workers and
equipment, to enter any route specified to perform activities such
as:

• Survey and take levels of the land along the proposed route;
• Dig and bore into the soil and subsoil;
• Cut and remove trees, vegetation and other objects that may
impede the survey activities
• Perform all acts necessary to ascertain the suitability of the
proposed route for the planned pipeline.

While trying to access the proposed route, access through a third-


party facility may be required; therefore, the permit also grants the
holder the right to access these third-party facilities. Before any
land or third-party facility is accessed, discussion and notification
shall be served accordingly to all parties, in some cases a
minimum of 14 days.

3.8 Carry Out Pipeline Route Survey

A route survey is the most critical activity performed in the


technical execution of pipeline routing. It is only performed after
the preliminary route has been developed. Most of the alterations
to the preliminary route result from a detailed survey performed.
Before acquiring a ROW, the route must be surveyed and deemed
okay for the pipeline construction.

Below are major surveys performed to firm up a pipeline route.

Figure 4: Pipeline Route Survey Works


3.8.1 Pipeline Centreline Survey
A pipeline centreline survey is performed to verify the preliminary
desktop-developed route. It is performed to confirm the suitability
of the route for pipeline construction.

During this activity, the surveyor performs a reconnaissance


survey of the entire route, utilising equipment such as a global
positioning system (GPS), theodolite, magnetic compass,
inclinometer etc. While inclinometers estimate the slope along and
across the pipeline route, theodolite, GPS and magnetic compass
are used to estimate positions on the pipeline route.

During this survey, the route is established on the ground,


restrictive areas are identified, and detours to the preliminary
route are established and firmed up. While performing this
operation, developmental plans and information required for
obtaining clearance for the pipeline are obtained.

The surveyor establishes stakes and flag control points on the


ground at key locations along the proposed pipeline centreline,
rivers, canal, major roads, rail, terminal stations etc. these stakes
and control points are also necessary if the Client desires to verify
the activity performed by the survey physically.

At the end of this survey, the route is updated on topographical


maps, ground profile showing elevation along the route is
developed. Also, a report shall be developed showing details
including:

• Route description
• Ground profile along the route
• Topographical features
• Bathymetric feature for water bodies
• Land use pattern
• Crossing details
• Site location suitable for pipe storage
• Soil strata along the route
• Features such as forest reserves
• Developmental plans
• Site photographs

A bathymetric survey shall be performed for offshore pipelines as


part of the centreline and detailed route survey to determine the
depth of water and map out features of water bodies

3.8.2 Detailed Route Survey


In some cases, a detailed route survey may be performed
separately to supplement the centreline survey, while it may be
performed in conjunction with the centreline survey. The detailed
survey covers a minimum of the envisaged right of way (ROW).
Some of the detailed information to obtain if not done during the
centreline survey include:

• Reconfirm the pipeline alignment on the ground


• Obtain all topographical features within to beyond the
envisaged right of way
• Finalise crossing angles and locations
• Obtain ground levels and contours
• Obtain details of land use
• Reconfirm or establish stakes at all turning
points/intersection points (TP/IP)

3.8.3 Cadastral Survey


Along the proposed pipeline route, a cadastral survey is performed
to establish land ownership boundaries, land ownership status,
restriction and interest in the designated land.
This survey is used to plan for ROW of acquisition, dispute
settlement etc.

The cadastral survey shows all the information on land ownership


and status obtained from relevant government agencies or
persons. At the end of this survey, maps showing physical
delineation are developed, and a detailed report covering the
entire proposed route is developed.

3.8.4 Soil Investigation Survey


A soil investigation survey is performed to obtain the physical and
geotechnical properties of the soil along the pipeline route for
engineering design and construction planning. Soil investigation
activities performed include

• Boring
• Obtaining disturbed samples from boreholes
• Visual engineering classification of soil along the proposed
pipeline route
• Perform standard penetration test at a specific location
• Laboratory testing of the collected soil samples to determine
engineering properties

Usually, boreholes are drilled at an identified location, usually


around 250m apart, except:

• At the intermediate point where a change in soil type is


observed
• For streams, river crossings and canals, boreholes shall be
drilled on both banks and one on the bed of the water body.
• At least one borehole shall be made at railroad and
highways.
The samples obtained from boreholes are tested to determine
properties including:

• Type of the soil up to the boring depth


• Soil bulk and dry density
• Natural moisture content
• Grain size
• Water table level
• For clayey soil; Un-drained shear strength
• Soil angle of internal friction

3.8.5 Location Classification Survey (Applicable to Gas Pipeline)


A location class survey is performed to determine the level of
development along the pipeline route. The development is a
function of the number of building intended for human occupancy.

Location classes are defined in ASME B31.8 section 840.2.1.

To determine the number of buildings intended for human


occupancy for an onshore pipeline:

Lay out a 0.4km wide zone along the pipeline route with the
pipeline on the centreline of the zone.

Divide the pipeline into random sections 1.6 km in length.

Note that each dwelling unit in a building is considered a separate


building intended for human occupancy.

Four location classes are defined in ASME B31.8, which are location
classes 1, 2, 3 or 4.

Location Class 1: Any 1mile (1.6km) section that has 10 or fewer


buildings intended for human occupancy
Location Class 2: Any 1mile (1.6km) section that has more than 10
but fewer than 46 buildings intended for human occupancy

Location Class 3: any 1mile (1.6km) section that has 46 or more


buildings intended for human occupancy except when a Location
Class 4 prevails

Location Class 4: Areas where multi-storey buildings are


prevalent, where there is heavy or dense traffic, and where there
may be numerous other utilities underground

Note: The higher the location class, the lower the design factor (F);
this results in a higher wall thickness, thereby increasing pipeline
safety. See ASME B31.8 Table 841.1.6-1 and Table 841.1.6-2 for design
factors corresponding to the various location classes.

3.9 Review the Routes and Reroute Accordingly

If required, the developed route is refined utilising the survey


results. Based on the survey results, detours to sections of the
route may be proposed resurveyed and implemented. The detours
may result from avoiding unstable soil, hilly grounds, cemeteries,
religious centres, forest reserves, rivers etc.

The refined route developed on a proper back sheet is further used


to obtain final approval to construct the pipeline.

3.10 Seek Government Approval

Seeking government approval implies obtaining a permit to


construct the pipeline. All documentation, including the surveyed
route, is collated and submitted to the government to grant the
construction of the pipeline
4 References

ASME 31.8: Gas Transmission and Distribution Piping Systems

Code of Federal Regulations 49 (CFR 49), Part 192

Oil Pipelines Act Chapter 338; Laws of the Federation of Nigeria


1990

DPR P-1P: Guidelines and Procedures for the Design, Construction,


Operation and Maintenance of Oil and Gas Pipeline Systems in
Nigeria

You might also like