Professional Documents
Culture Documents
Commissioning Procedures
Commissioning Procedures
Special care must be taken during the check up and testing, to protect the persons from hazards and from
damaging goods and materials. Refer to NFC 15-100
The verification includes all the methods throughout, where the electrical system is checked as conform to the
selected norm. It includes a visual inspection and testing.
In the following 5 steps the system should be switched off and out of voltage.
1 – Visual inspection
Visual inspection is to ensure the quality of execution of the work.
Compliance criteria: presence and consistency of the data with the wiring diagram information.
Commissioning procedures 1
2 – Control
2.1 – Check the equipotential connections
This check verifies that all metal parts of the system are grounded via protective conductors. Action is tested
out of voltage.
Periodicity: at installation then once each year.
Tester: The tester should generate a minimum testing current of 0.2 A. the multimeter is not allowed.
Commissioning procedures 2
Measurement: the controls are carried out between the nearest point of the main equipotential bonding and,
successively, the different points of metal masses accessible:
Commissioning procedures 3
Measure the resistance between the active power conductors.
Measure the resistance of the primary and the secondary windings of the transformer.
Compliance criteria:
Commissioning procedures 4
2.3 – control of isolation resistance
This control is to check the condition of the electrical insulation of the structure.
Periodicity: at the commissioning and whenever necessary.
Measurers: This control can be done with an ohmmeter or installation tester.
Measurement: the measurements are taken equipment out of voltage.
Compliance criteria: The isolation threshold is 1000 ohms per volt test voltage.
Minimal values of the testing voltages:
Minimal voltage of the circuit (V) Testing voltage DC (V) Insulation resistance (MΩ)
≤ 50 V 250 V ≥ 0.25
Commissioning procedures 5
2.4 – control of the earthing system
This control is to measure the resistance of the earth electrode of
the installation.
Periodicity: at the commissioning and then yearly.
Measurers: this control is carried out using a mega ohmmeter or an
installation tester.
Measurement: the measurement method depends on the accessibility to the earth system:
When the earth connection is available, the measurement is made with an open earth link.
When the earth connection is not available, a measurement of the impedance of the fault loop gives a
default value of the earthing electrodes. In this case, the installation must be switched on.
Compliance criteria: in IT and TT systems, when the earth electrodes are separated, the maximum value of
the earth-electrode-resistance is prescribed by the standard NFC 15-100.
Commissioning procedures 6
2.5 – control of the residual current device RCD
This control is to check the proper functioning of the
protection devices by an automatic trip of the power feeder.
Periodicity: at the commissioning and then yearly.
Measurers: this control is carried out using a RCD tester or
an installation tester.
Measurement:
Compliance criteria: the device should trip in a time less than recommended by the standard and for a current
included between 50% and 100% of its sensitivity IΔn.
3 – Functional tests
The functional tests should be made by a qualified technician and under Voltage
Periodicity: at the commissioning and whenever necessary.
Commissioning procedures 7
Measurers:
1- Measure the voltage upstream of the 2- Measure the voltage downstream of the
opened protection device. closed protection device.
Commissioning procedures 8
When the system is entirely under voltage, we must check that the different loads are working correctly.
Compliance criteria:
- Conformity of voltage
- correct functioning of the loads
Commissioning procedures 9