CS Comments - Method Statement For GRC Works
CS Comments - Method Statement For GRC Works
CS Comments - Method Statement For GRC Works
1 OBJECTIVE
The objective of this method statement is to ensure, that all processes of Glass fiber reinforcement
concrete works for external façade of building are done systematically and correctly in
accordance with GRC works requirements mentioned in the contract no package BP#3
construction of parcel 4.
2 SCOPE
This procedure provides a method statement for executing of GRC works in order to achieve
compliance with contract specifications and drawing.
Applicable to cover the requirement for GRC works that included cornices, fixation.
Solid shall furnish all labors, materials, equipment's, executing the plaster works including
inspecting materials (i.e. grc cornices, anchors, bolts and accessories), proper storing, cleaning,
surface preparation, surveying, install accessories, mixing mortars. Apply cement plaster till
finish coat, curing plaster work and taking all safety precautions. All as indicated on drawings
and specifications.
3 REFERENCE
4 PERSONAL RESPONSIBILITIES
• A full and detailed description of the roles and responsibilities of all (Solid
Constructions) staff is included within the Project Quality Plan.
5 QUALITY ASSURANCE
• Sequencing and Scheduling: solid shall execute the work in this section carefully
and coordinate with the work of other sections to prevent damage to other works.
• Applicator Qualification: Solid shall specify a qualified applicator that is
authorized, approved or licensed to install plaster works.
• Testing: Solid shall apply all materials used. Comply with the requirements of the
referenced standards when tested in accordance with the method indicated. And
will perform all such test at its own expense. All sampling and testing shall be
performed in a testing laboratory acceptable to the engineer. As per Egyptian
Standards Specifications (E.S.S).
6 EQUIPMENT
• Hand tools for anchoring
• Fasteners
• Set Scaffoldings for working at the higher level.
• Plumb & Level
• Drilling machine
Mention joint width
and sealant materials
7 PRODUCTS
• GRC units (cornices)
• Bolts
• Sealant
• Backer rod
• Fast setting epoxy
Wall
• Install GFRC units level, plumb, square and in alignment. Provide temporary
supports and bracing as required to maintain position, stability and alignment of
units until permanent connections are completed.
• Remove and replace damaged GFRC units when repairs do not comply with
requirements.
9 SAFEFTY
• All the safe practices will be adopted during the construction of concrete
foundation.
• Special work permits, wherever required, shall be obtained before
commencing work.
• Proper access for the labor and equipment shall be provided for the works.
• All machinery shall be checked for maintenance records.
• The site shall be cleaned from all the debris, steel waste, nails etc.