Professional Documents
Culture Documents
Stabilization Pond Rehab Expansion
Stabilization Pond Rehab Expansion
Student Group
Department of Civil Engineering
California State University, Chico
1
Lead Author: Alyssa Stutz
Collaborating Authors:
(in Alphabetacle Order)
Paul Anderson
Tim Arnold
Francis Booth
Brendan Finn
Kystle Galindo
Lisa Hall
Nicholas Mcgann
Frank O´Connell
Shane Salvador
Editors:
(in Alphabetacle Order)
Tim Arnold
Stewart Oakley
1
Loading Rates
The flow rate ranges from roughly 1,700 to 7,200 cubic meters per day. This means that
the BOD loading rate ranges from 340 to 1,450 kg/day. That equates to a loading rate of
26 to 113 g/m3-day for each of the two ponds.
Sludge Accumulation
The rate of sludge accumulation ranges from 1,200 to 2,400 cubic meters per year. This
means that it could be anywhere from 1.8 to 3.5 years before the ponds are 1/3 full of
sludge or 3.5 to 7.0 years before the ponds are 2/3 full.
Hydraulic Retention Time
Hydraulic retention times for the primary anaerobic ponds ranged from 7.6 to 1.8 days.
Hydraulic retention times for the 2.5 hectare facultative/maturation pond ranged from
24.6 to 5.7 days. This led to a total hydraulic retention time range from 32.2 to 7.5 days.
Log Removal
Using a temperature of 25 degrees Celsius, log removal through the anaerobic ponds
ranged from 1.35 to 0.77 and log removal through the facultative/maturation pond ranged
from 2.59 to 1.03. Total log removal ranges from 3.93 to 1.81. The World Health
Organization (WHO) recommends 2-3 log removal, therefore, WHO guidelines are met.
Valorization
Using a BOD/Nitrogen/Phosphorus ratio of 100/5/1, the amount of nitrogen and
phosphorus accumulated in one day ranges from 17 to 72 kilograms and from 3 to 14
kilograms, respectively. This means that the amount of nitrogen and phosphorus
accumulated in one year ranges from 6,205 to 26,280 kilograms and from 1,095 to 5,110
kilograms, respectively.
This leads to value ranges for nitrogen of $24,670 to $105,700 (at $0.40/100 g) and value
ranges for phosphorus of $145,110 to $621,900 (at $58.84/500 g).
If the effluent is used for irrigation, the water value ranges from $92 - $396
($0.00015/m3).
Table 1: Summary of Findings
Range
3
Flow Rate [m /day]: 1,700 7,200
BOD loading per pond [g/m3-d] 26 113
Sludge Accumulation [m3/yr]: 1,200 2,400
Time interval for desludging [yrs]: 1.8 3.5
Hydraulic Retention Time [days]: 32.2 7.5
Log Removal 3.9 1.8
Nitrogen Value [$/yr] $24,660 $105,700
Phosphorus Value [$/yr] $145,110 $621,900
Water Value [$/yr] $92 $396
Population Estimates
The design period for the Project is from year 2011 to 2016. The initial estimate of the
population in Villanueva, Honduras is roughly 51,400 for the year 2008. (Wolfram 2010)
According to the Central Intelligence Agency World Factbook, the population growth
rate in Honduras is 2.002%.
Using the following population growth equation:
= 0
where,
• N0 is the starting population
• N is the population after
• t is the time that has elapsed
• r is the growth rate
The population estimates for the years 2011 and 2016 are approximately 54,580 and
60,330, relatively.
Figure 1: Population estimates plotted on a yearly basis.
Cost of Desludging
The two current primary ponds will be desludged and the sludge will be stored onsite. A
midsize excavator, a D6 track tractor, and two 10 cubic meter dump trucks will be
available for rent.
The total quantity of sludge is approximately 9,000 cubic meters (as stated in the
previous section).
The excavator will be loading the two dump trucks and the tractor will be pushing
material toward the excavator and making the finishing touches once the lagoon side
slopes are formed. The tractor will need to be rented for a longer amount of time than the
excavator towards the end of construction.
For the excavator, a bucket size of 0.9 cubic meters and a cycle time of 45 seconds (0.75
min) were used (Caterpillar 1998).
Cost
Time Required Total Cost Total Cost
Equipment (L/hr)(hr) (HNL) (USD)
322B Excavator: 1,500125 186,900 9,878
D6 Bulldozer: 1,000133 132,600 7,008
Dump truck: 400 125 49,840 2,634
Dump truck: 400 125 49,840 2,634
Laborers (2): 60 125 7,476 395
Total: 426,656 22,551
TOTAL COST FOR WHOLE PROJECT: 2,131,916 112,681
System Analysis
Loading Rates
Research needed to be conducted to decide whether the original configuration of the
ponds needs to be changed based on the organic loading rates. Appendix D shows that
the original configuration does need to be changed. It was assumed that the influent fecal
coliform concentrations were the same as measured in Dr. Oakley’s monitoring study in
2003 – 5.64x107 coliforms/100 ml (Oakley 2005). The surface organic loading rates to
the two primary ponds in parallel are well above the maximum of 350 kg BOD/ha-day.
They range from 568 to 1,192 kg BOD/ha-day and average 905 kg BOD/ha-day.
To see if the range would fall below 350 kg BOD/ha-day, analysis was made to use all
four ponds as primary aerobic ponds. Still the loading rates were high, ranging from 284-
596 kg BOD/ha-day, with an average of 452 kg BOD/ha-day. Only 26% of the estimated
flow-rates fell below the 350 kg BOD/ha-day maximum.
This showed that perhaps an anaerobic system would be something to consider. So an
analysis was done for both two anaerobic and four anaerobic ponds. The final design
includes two anaerobic ponds instead of four. It was decided that two anaerobic ponds
would be used instead of four because there is a chance that four ponds could be under-
loaded. Also, while two of the primary anaerobic ponds are being used, the other two are
not, which allows for easy desludging in the future.
Hydraulic Retention Time
Appendix D also includes hydraulic retention times. Hydraulic retention times decreased
significantly when switching from four ponds to two ponds. Retention times for the two-
pond anaerobic system varied between 7.5 and 32.2 days.
Pathogen Removal and WHO Guidelines for Wastewater Reuse
Pathogen removal is also included in Table 5. Von Sperling’s method was used to
calculate the log removal (Mara 2003). The following equations were used:
Anaerobic Ponds:
Anaerobic Ponds:
Total log removal of fecal coliforms ranged from 1.8 to 3.9 with an average of 2.8. Log
removal in the two anaerobic ponds alone ranged from 0.8 to 1.3, and in the maturation
pond (with 12 baffles) 1.0 to 2.6. It is estimated that there is a 100% removal of helminth
eggs (Mara 2003).
It is planned that the wastewater will be used to irrigate the local sugarcane. The 2006
World Health Organization guidelines suggest a log removal of 3 for restricted irrigation
and highly mechanized harvesting (WHO 2006). Fortunately, using the two parallel
anaerobic ponds in parallel and the maturation pond in series gives a best-case scenario
log removal of 3.9, which exceeds the WHO guidelines.
System Configuration
Figure 2: Two Pond Anaerobic System Configuration
Anaerobic
Pond
1A
Anaerobic
Pond
2A
Anaerobic
Pond
1B
Anaerobic
Pond
2B
8
Sludge Accumulation
Because the ponds are anaerobic, sludge will accumulate in them more rapidly than if
they were aerobic ponds. The rate for sludge accumulation in anaerobic ponds in warm
climates is 0.04 cubic meters per person per day (Mara 2003). It is said that rates could be
as low as 0.01 but the high is used in this case as a factor of safety. Table 4 shows rates
of sludge accumulation depending on the percentage of people connected to the sewer
system.
Table 5: Sludge Accumulation
Guidelines for the Safe Use of Wastewater, Excreta and Greywater. Volume 2. Geneva,
Switzerland. World Health Organization, 2006. Print. pp. xvii.
"Planning for the future in Villanueva." USAID. USAID, 16 Jul 2009. Web. 11 Sep 2010.
<http://www.usaid.gov/stories/honduras/cs_honduras_villanueva.html>.
Viessman, Warren, Mark Hammer, Elizabeth Perez, and Paul Chadik. Water Supply and
Pollution Control. 8th ed. Upper Saddle River, NJ: Pearson Education, Inc., 2009. Print.
pp. 521-522.
World Factbook, The. “Central Intelligence Agency.” 2010. Web. 9 Sep 2010.<https:
//www.cia.gov/library/publications/the-world-factbook/geos/ho.html>.
.
Appendix A: Pond Volume and Cost Calculations
Appendix B: Loading Calculations
12
Appendix C: Sludge Accumulation and Valorization Calculations
Appendix D: System Configuration Analysis