Building Estimate
Building Estimate
8 x 14 x 13 = 1456.00 Sft
8 x 2 x 14.00 x 10 = 2240.00 Sft
8 x 2 x 13.00 x 10 = 2080.00 Sft
2 x 70 x 15.00 = 2100.00 Sft
8 x 6 x 5.00 = 240.00 Sft
8 x 2 x 5.00 x 10 = 800.00 Sft
8 x 2 x 6.00 x 10 = 960.00 Sft
1 x 18 x 15.00 = 270.00 Sft
2 x 2 x 18.00 x 10 = 720.00 Sft
2 x 2 x 15.00 x 10 = 600.00 Sft
14 x 16 x 15.00 = 3360.00 Sft
14 x 2 x 16.00 x 10 = 4480.00 Sft
14 x 2 x 15.00 x 10 = 4200.00 Sft
1 x 25 x 15.00 = 375.00 Sft
2 x 2 x 25.00 x 10 = 1000.00 Sft
2 x 2 x 15.00 x 10 = 600.00 Sft
3 x 100 x 15.00 = 4500.00 Sft
3 x 2 x 100.00 x 10 = 6000.00 Sft
3 x 2 x 15.00 x 10 = 900.00 Sft
12 x 6 x 5.00 = 360.00 Sft
12 x 2 x 5.00 x 10 = 1200.00 Sft
12 x 2 x 6.00 x 10 = 1440.00 Sft
39881.00 Sft
(11-21-a-03) @Rs. 162.91 P M2 = 3706.41 M2 Rs. 603812
2- Preparing surface & painting with snowcem / weathershield paint : First coat
12- Supply and fixing of fancy type stainless steel chromium plate 2" dia
pipes stair railing 3/4" dia pipe fixed on specified space on steps in
horizontal positions, complete in all respects
= 200.00 Rft
(25-47) @Rs. 4,802.78 P M = 60.96 M Rs. 292763
8 x 14 x 13 = 1456.00 Sft
2 x 18 x 15 = 540.00 Sft
12 x 16 x 15 = 2880.00 Sft
1 x 70 x 10 = 700.00 Sft
1 x 110 x 10 = 1100.00 Sft
= 6676.00 Sft
(12-47) @Rs. 2,565.49 P M2 = 620.45 M2 Rs. 1591748
6 x 15 x 9 = 810.00 Sft
6 x 12 x 9 = 648.00 Sft
4 x 25 x 9 = 900.00 Sft
4 x 15 x 9 = 540.00 Sft
4 x 5 x 9 = 180.00 Sft
4 x 6 x 9 = 216.00 Sft
= 3294.00 Sft
(12-68) @Rs. 1,484.50 P M2 = 306.13 M2 Rs. 454456
2 x 15 x 12 = 360.00 Sft
2 x 25 x 15 = 750.00 Sft
= 1110.00 Sft
(12-47) @Rs. 2,565.49 P M2 = 103.16 M2 Rs. 264656
4 x 8 x 8 = 256.00 sft
8 x 8 x 6 = 384.00 sft
8 x 8 x 6 = 384.00 sft
= 1024.00 sft
(10-55-a) @Rs. 3,543.32 P M2 = 95.17 m2 Rs. 337208